Fletcher Hill, Inc. v. Crosbie

Annotate this Case
Fletcher Hill, Inc. v. Crobsibe (2002-348)178 Vt. 77; 872 A.2d 292

2005 VT 1

[Filed 14-Jan-2005]


       NOTICE:  This opinion is subject to motions for reargument under
  V.R.A.P. 40 as well as formal revision before publication in the Vermont
  Reports.  Readers are requested to notify the Reporter of Decisions,
  Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801 of
  any errors in order that corrections may be made before this opinion goes
  to press.


                                  2005 VT 1

                                No. 2002-348


  Fletcher Hill, Inc.	                         Supreme Court

                                                 On Appeal from
       v.	                                 Windsor Superior Court


  Susan Crosbie	                                 September Term, 2004


  Alan W. Cook, J.

  Matthew J. Ragaller of Boylan Associates, P.C., Springfield, for
    Plaintiff-Appellant.

  Martha M. Davis of Law Office of Martha M. Davis, Windsor, for
    Defendant-Appellee.

  PRESENT:  Dooley, Johnson and Skoglund, JJ., and Allen, C.J. (Ret.) and
            Gibson (Ret.), Specially Assigned

       ¶  1.  SKOGLUND, J.   This action arises out of the construction of
  a modular home by plaintiff Fletcher Hill, Inc. for defendant Susan
  Crosbie.  Fletcher Hill appeals (1) the trial court's denial of its request
  for attorney's fees, and (2) the court's determination of the rate of
  prejudgment interest.  We affirm.
   
       ¶  2.  Crosbie entered into a construction contract with Fletcher
  Hill for construction and installation of her modular home.  The contract
  contains a "late fee" provision which states that "[a]ll outstanding
  balances over 30 days due from date of invoice will be charged 2% per month
  interest plus attorney's fees."  Disputes arose during the course of
  construction, and ultimately Crosbie refused to pay Fletcher Hill the
  amount due on the final invoice.  Fletcher Hill filed a mechanic's lien
  against Crosbie's property, and then filed suit for breach of contract. 
  Crosbie counterclaimed, alleging that Fletcher Hill breached the contract
  because it did not complete the installation in a workmanlike manner.  She
  further claimed that Fletcher Hill breached the contract by not paying its
  subcontractors, thereby subjecting her property to a lien filed by a
  subcontractor.  Indeed, after filing a contractor's lien on the property,
  the complaining subcontractor obtained a judgment for $3500 against
  Fletcher Hill and then served Crosbie with a trustee process for that
  judgment.  

       ¶  3.  At trial, the jury found that Crosbie breached the contract by
  failing to pay the final invoice and awarded Fletcher Hill $15,067.  The
  jury also found that Fletcher Hill breached the contract by failing to
  perform in a workmanlike manner and awarded Crosbie $4000 for "sums spent
  to remedy any defects or omissions."  At a subsequent hearing to determine
  attorney's fees and prejudgment interest, the trial court refused to award
  either party attorney's fees, and awarded Fletcher Hill prejudgment
  interest at the statutory rate of 12% per year from the date the suit was
  filed.  Fletcher Hill appealed.  We review the trial court's ruling on
  attorney's fees and prejudgment interest for abuse of discretion.  Young v.
  N. Terminals, Inc., 132 Vt. 125, 130, 315 A.2d 469, 472 (1974).  

       ¶  4.  The court denied the parties' requests for attorney's fees for
  two reasons.  First, the court held that "to base an award of attorneys
  fees on a contract which the plaintiff violated would be contrary to law." 
  In short, the court held that Fletcher Hill could not collect fees under a
  contract that the jury found it had breached.  Second, the court ruled that
  under 9 V.S.A § 4007(c) neither party had substantially prevailed, so each
  party had to pay its own attorney's fees.  
   
       ¶  5.  "The American Rule ordinarily prohibits an award of
  attorney's fees absent a specific statutory provision or an agreement of
  the parties."  Galkin v. Town of Chester, 168 Vt. 82, 91, 716 A.2d 25, 31
  (1998).  An award of attorney's fees is proper where a contract
  specifically provides for them.  Foster & Gridley v. Winner, 169 Vt. 621,
  624, 740 A.2d 1283, 1287 (1999) (mem.); see also Mount Everest Ski Shops,
  Inc. v. Nordica USA, Inc., 736 F. Supp. 523, 527 (D. Vt. 1989) ("A
  contract, too, may vary the application of the [American] rule; the court
  may depart from the American Rule only to the extent which the contract
  provides.").  When a contract provides for attorney's fees, Vermont courts
  are loathe to revise the agreement struck by the parties and deny them the
  benefit of their bargain.  See Ianelli v. Standish, 156 Vt. 386, 389, 592 A.2d 901, 903 (1991) (granting attorney's fees to defendant in dispute over
  a real estate contract). 

       ¶  6.  Here, the parties negotiated and agreed to a "late fee"
  provision that provided for attorney's fees in the event of a balance
  overdue more than thirty days from the invoice date. Because this case
  involves a construction contract, we look to the specific statutes that the
  Legislature has promulgated concerning disputes arising therefrom.  See 9
  V.S.A. §§ 4001-4009 (setting forth, inter alia, owners' and contractors'
  payment obligations in the context of construction contracts).  Under those
  statutes, the default position is that "[t]he owner shall pay the
  contractor strictly in accordance with the terms of the construction
  contract."  Id. § 4002(a).  However, the owner's duty to pay the
  contractor, including a "late fee" provision like the one at issue here,
  must be considered in light of 9 V.S.A. § 4007(a): 
   
    Nothing in this chapter shall prevent an owner . . . from
    withholding payment in whole or in part under a construction
    contracting an amount equalling the value of any good faith claims
    against an invoicing contractor or subcontractor, including claims
    arising from unsatisfactory job progress, defective construction,
    disputed work or third-party claims.  

       ¶  7.  The trial court did not abuse its discretion in refusing to
  invoke the "late fee" provision concerning attorney's fees because Crosbie
  had a good faith basis under § 4007(a) for withholding payment of the
  outstanding balance for two reasons.  First, as the jury found, Fletcher
  Hill breached the contract by failing to complete the installation of the
  home in a workmanlike manner.  Indeed, Crosbie's counterclaim describes a
  list of substantial deficiencies, including the fact that the two
  structural halves of the house were not properly set on the foundation,
  with one side of the house resting approximately three-quarters of an inch
  higher than the other.  The jury confirmed Fletcher Hill's breach by
  answering Jury Interrogatory 4-"Did the Plaintiff breach the contract by
  not performing in a workmanlike manner at least in part?"-in the
  affirmative, and awarding Crosbie $4000.  In addition, in assessing
  Fletcher Hill's request for attorney's fees, the trial court noted that
  "there was an adequate basis in the record, had [the jury] chosen to do so,
  to provide more relief to the defendant," and that as a result of the
  "issues of poor workmanship" and "the substantial deficiencies in the
  construction," Crosbie "was within her rights to withhold funds under the
  circumstances."  
   
       ¶  8.  Second, prior to the time the home became ready for
  occupancy, the unpaid subcontractor filed an action and a mechanic's lien
  against Crosbie, demanding $5595 for labor and materials.  Thus, the record
  reveals that at the time the $15,000 final payment came due, Crosbie was
  aware of the deficiencies in the construction of the home and her potential
  liability to the subcontractor.  On this basis, the trial court declined to
  apply the prompt payment provision of the contract to the issue of
  attorney's fees after the jury verdict, reasoning that "to base an award of
  attorney's fees on a contract which the plaintiff violated would be
  contrary to law."  The trial court's decision correctly avoids the
  unfairness that would follow from penalizing Crosbie for, in effect,
  miscalculating the amount she was entitled to withhold.  It also comports
  with the Legislature's intent, as evidenced by § 4007(a), to permit a party
  to withhold payment until after the parties resolve their disputes,
  assuming the withholding party had a good faith basis.

       ¶  9.  The two cases relied upon by the dissent in reasoning that the
  contract provision should govern, post, ¶ 29, do not alter the analysis. 
  First, neither Weidner v. Szostek, 614 N.E.2d 879 (Ill. App. Ct. 1993), nor
  Fenner & Shea Construction Co. v. Wadkins, 511 P.2d 924 (Colo. Ct. App.
  1973), addressed a statutory scheme governing construction contracts
  similar to §§ 4001-4009.  Furthermore, in neither case did the trier of
  fact find that the contractor breached the contract by its deficiencies in
  workmanship, as the jury in this case did when it answered Jury
  Interrogatory 4 in the affirmative.  

       ¶  10.  The trial court also correctly declined to award attorney's
  fees under 9 V.S.A. § 4007(c).  Section 4007(c) states that
  "[n]otwithstanding any contrary agreement, the substantially prevailing
  party in any proceeding to recover any payment within the scope of this
  chapter shall be awarded reasonable attorneys' fees in an amount to be
  determined by the court or arbitrator, together with expenses."  Based on
  the jury's verdict and the damage awards, both parties requested an award
  of fees.  The court decided that neither party was entitled to attorney's
  fees under the statute because neither had "substantially prevailed."
   
       ¶  11.  On appeal, Fletcher Hill argues that the court erred because
  it did substantially prevail in this action.  It relies on simple
  mathematics, pointing to the fact that the jury's verdict was a net award
  of $11,067 in its favor.  To support its position, Fletcher Hill relies on
  an unpublished Washington Court of Appeals opinion, which held that the
  trial court properly awarded attorney's fees based on one party's receipt
  of a net judgment.  See Durall v. Simon, No. 18760-8-III, 2000 WL 1476157,
  at *3 (Wash. Ct. App. Oct. 5, 2000) (holding that because plaintiff
  received net judgment, trial court did not abuse its discretion in finding
  plaintiff was substantially prevailing party and thus entitled to fees).

       ¶  12.  While the mandatory language of § 4007(c) requires an award of
  attorney's fees to a substantially prevailing party, the question of
  whether any party to a lawsuit substantially prevailed is left to the trial
  court's discretion.  See, e.g., De Witt v. Liberty Leasing Co., 499 P.2d 599, 601 (Alaska 1972) ("The determination of which party prevailed is
  committed to the discretion of the trial court and is reviewable on appeal
  only for abuse.")  While acknowledging that, "in terms of sheer dollars and
  cents," plaintiff prevailed, the court did not "think the plaintiff
  substantially prevailed in this case.  I think it was clearly a split
  decision."  The court further explained:

    There were clearly issues of poor workmanship . . . in this case. 
    The defendant was within her rights to withhold funds under the
    circumstances.  There w[ere] substantial deficiencies in the
    construction, not the least of which is that a section of this
    house was offset, and other items too numerous to mention. . . .
    [T]he point was, it was not a clear victory in favor of the
    plaintiff.  
     
       ¶  13.  We have applied § 4007(c) to require an award of attorney's
  fees, but under circumstances that contrast sharply with this case.  For
  instance, we have held that where a subcontractor's claims against a
  contractor were dismissed on summary judgment, the trial court correctly
  awarded attorney's fees to the contractor as the substantially prevailing
  party.  DJ Painting, Inc. v. Baraw Enters., 172 Vt. 239, 246-47, 776 A.2d 413, 419-20 (2001).  Here, we have a jury verdict that resulted in awards
  to both parties.  In addition, the trial court, in calculating the interest
  due to Fletcher Hill, reduced the principal amount by $3500-the amount of
  the yet-to-be-satisfied judgment against Fletcher Hill in favor of the
  subcontractor who filed a lien and a trustee process against Crosbie. 
  Fletcher Hill fails to factor that reduction into its mathematical solution
  of which party substantially prevailed.  In light of the facts of this
  case, we find the court's exercise of discretion regarding attorney's fees
  sustainable.

       ¶  14.  Neither the language of § 4007(c) nor the case law cited by
  the dissent dictates that determining whether a party substantially
  prevailed turns on a simple mathematical comparison of the parties'
  respective recoveries.  First, although the dissent is correct that the
  statute "accords no discretion to the court to deny fees where it applies,"
  post, ¶ 34, determining "where it applies"-or identifying the substantially
  prevailing party-falls within the trial court's discretion, and does not
  flow automatically from the calculation of the net victor.  Furthermore,
  the use of the words "the substantially prevailing party," 9 V.S.A. §
  4007(c) (emphasis added), does not imply that there must be a substantially
  prevailing party in every case.  It indicates, as the dissent points out,
  that there can be, at most, one substantially prevailing party.  Applying
  the dissent's "net victor" approach, however, would mandate an award of
  fees in every construction contract case that does not result in a "draw,"
  since the net victor would automatically qualify as the substantially
  prevailing party.
   
       ¶  15.  The cases cited by the dissent do not compel the conclusion
  that the party with a net verdict is automatically the substantially
  prevailing party.  Indeed, several of the cases cited by the dissent make
  clear that identifying the substantially prevailing party is a matter for
  the trial court's discretion and cannot be reduced to merely calculating
  the net verdict.  See De Witt, 499 P.2d  at 600 ("The determination of which
  party prevailed is committed to the discretion of the trial court and is
  reviewable on appeal only for abuse."); Schmidt v. Colonial Terrace
  Assocs., 694 P.2d 1340, 1345 (Mont. 1985) (" 'No one factor should be
  considered in determining the prevailing party for the purpose of attorney
  fees.  The party that is awarded a money judgment in a lawsuit is not
  necessarily the successful or prevailing party.' " (quoting E.C.A. Envtl.
  Mgmt. v. Toenyes, 679 P.2d 213, 217-18 (Mont. 1984))); see also In re
  Marriage of Murphy, 763 N.E.2d 933, 938 (Ill. App. Ct. 2002) ("Like those
  who have grappled with the issue before us, we cannot definitively say what
  the term 'substantially prevail' means in all cases."), rev'd on other
  grounds, 786 N.E.2d 132 (Ill. 2003).  

       ¶  16.  Significantly, with one exception, the cases cited by the
  dissent for the proposition that the net victor is the substantially
  prevailing party do not address the term "substantially prevailing party." 
  See De Witt, 499 P.2d  at 600 (statute awarded attorney's fees to the
  "prevailing party"); Moss Constr. Co. v. Wulffsohn, 253 P.2d 483, 484-85
  (Cal. Dist. Ct. App. 1953) (statute awarded attorney's fees to the
  "successful party"); Corley v. Rivertown, Inc., 863 So. 2d 1244, 1246 (Fla.
  Dist. Ct. App. 2004) (statute awarded attorney's fees to the "prevailing
  party"); Szoboszlay v. Glessner, 664 P.2d 1327, 1333-34 (Kan. 1983)
  (statute awarded attorney's fees to the "successful party"); Schmidt, 694 P.2d  at 1345 (contract awarded fees to the "prevailing party").  Thus,
  these cases do not control our interpretation of § 4007(c).  The U.S.
  Supreme Court has pointed out that these terms are not synonyms, observing
  that fee-shifting statutes "contain varying standards as to the precise
  degree of success necessary for an award of fees-such as whether the fee
  claimant was the 'prevailing party,' the 'substantially prevailing' party,
  or 'successful.' "  Ruckelshaus v. Sierra Club, 463 U.S. 680, 684 (1983)
  (emphasis added).  The Second Circuit has observed that, in the context of
  a fee-shifting statute, "the term 'substantially' . . . alters the amount
  or degree of recovery necessary to obtain fees."  Union of Needletrades,
  Indus. & Textile Employees v. INS, 336 F.3d 200, 208 (2d Cir. 2003)
  (emphasis in original).  
   
       ¶  17.  The one case cited by the dissent involving a statute
  identical to § 4007(c) suggests that identifying the net victor does not
  end the inquiry.  In Bridges PBT v. Chatta, 2003 PA Super. 122, 821 A.2d 590, the court recognized that requiring an award of attorney's fees simply
  because a party won a net judgment would effectively "write out the
  modifier 'substantially.' " 2003 PA Super. ¶ 9.  Because we "presume that
  legislative language is inserted advisedly and not intended to create
  surplusage," In re South Burlington?Shelburne Highway Project, 174 Vt. 604,
  606, 817 A.2d 49, 52 (2002) (mem.), we refuse to read "substantially" out
  of § 4007(c) by equating the "substantially prevailing party" with the
  party holding a net judgment.  Cf. In re Marriage of Murphy, 763 N.E.2d  at
  938 ("We thus presume that the legislature was familiar with the
  construction courts had previously given to the term 'prevail' and opted
  instead that a party 'substantially' prevail to prevent application of the
  lower threshold for 'prevailing' that had been applied in other
  contexts.").

       ¶  18.  Next, we affirm the trial court's interest rate determination. 
  The court awarded Fletcher Hill prejudgment interest from the date the suit
  was filed, but declined to use the 2% per month interest rate specified in
  the contract.  Instead, the court utilized the statutory interest rate of
  12% per annum. 
   
       ¶  19.  The court did not abuse its discretion when it declined to
  apply the interest rate contained in the contract's "late fee" provision
  because, as explained above, the record indicated that Crosbie had a good
  faith basis for withholding the outstanding balance.  After concluding it
  was not bound by the contractual interest rate, the court correctly applied
  the statutory 12% interest rate found throughout 9 V.S.A. §§ 4001-4009. 
  For example, pursuant to 9 V.S.A. § 4002(d), payments to the contractor
  delayed beyond the due date will accrue interest, beginning on the
  twenty-first day, at a rate equal to that established by 12 V.S.A. §
  2903(b).  Section 2903(b) governs interest on judgment liens and sets the
  rate at 12% per annum.  See also 9 V.S.A. § 4003(d) (setting interest rate
  for late payments owed by contractor to subcontractor at the 12% annual
  rate established by 12 V.S.A. § 2903(b)); 9 V.S.A. § 4005 (pegging interest
  rate for overdue retainage to the interest provisions of §§ 4002-4003).  On
  this basis, we hold that the trial court's imposition of a 12% interest
  rate was not error.


       ¶  20.  Finally, Fletcher Hill argues that the court erred in awarding
  interest from the date the complaint was filed, claiming instead that
  interest should have been awarded from the date of Crosbie's breach. 
  Fletcher Hill failed to object to this ruling at the post-trial hearing,
  and issues raised for the first time on appeal will not be considered by
  this Court.  In re Lorentz, 2003 VT 40, ¶ 5, 175 Vt. 522, 824 A.2d 598
  (mem.).  Because Fletcher Hill assented to the date chosen by the court at
  the post-trial hearing, we treat the award of interest from the date of
  filing as the law of the case, and the trial court's ruling on this issue
  stands.

       Affirmed.


                                       FOR THE COURT:


                                       ___________________________________
                                       Associate Justice


------------------------------------------------------------------------------
                                 Dissenting
        

       ¶  21.  DOOLEY, J., dissenting.   Noting that the jury could have
  awarded more relief to defendant than it did, the trial court apparently
  felt that it would do rough justice by refusing to award attorney's fees to
  either party and by reducing plaintiff's interest recovery rate by half. 
  If the attorney's fees issue involved only a matter of discretion in the
  trial court, I would affirm for the reasons stated by the trial judge and
  the majority.  It is not, however, a matter solely of discretion, and the
  decision is contrary to the clear law governing this issue.  Similarly, the
  trial court's interest rate ruling is not sustainable on the rationale
  stated by the trial court or the majority, but if a further record is made,
  might be sustained on a different basis.  Accordingly, I would reverse the
  attorney's fees denial and remand the interest rate issue.  I dissent from
  the majority's decision to uphold the trial court rulings.

       ¶  22.  The central foundation of the majority's analysis of this
  appeal on both issues is that the jury found that defendant withheld the
  full final installment of her payment for the house in good faith and,
  despite the fact that the jury awarded plaintiff much more than it awarded
  defendant, plaintiff's claim for attorney's fees and contractual interest
  is defeated by this finding.  In fact, the jury made no such finding of
  good faith, and the finding it did make is contrary to the majority's
  assertion.

       ¶  23.  Plaintiff brought this action for $15,067, the amount that it
  asserted was due under the construction contract, plus attorney's fees,
  interest, and costs.  Defendant answered that plaintiff could not recover
  because it breached the contract in numerous respects, including that it
  failed to deliver the house at the time specified in the contract and
  failed to construct the house in accordance with the contractual
  specifications in numerous respects.  Defendant also counterclaimed for
  amounts that would allow her to complete the house in accordance with the
  specifications, for amounts to cover items that could not be fixed, and for
  costs and expenses in defending claims of unpaid subcontractors.
   
       ¶  24.  A major dispute at trial was whether defendant was justified
  in refusing to pay the entire last installment because of the deficiencies
  she claimed.  Relying on defendant's statements, plaintiff asserted that
  defendant had withheld the full amount not in good faith, but instead out
  of anger at plaintiff and to deprive it of any profit on the sale of the
  home.  Defendant asserted, to the contrary, that the deficiencies in the
  house exceeded the amount of the last payment due under the contract and
  justified her action in refusing to make that payment.

       ¶  25.  The trial court instructed the jury on the law, drawing
  heavily on our decision in VanVelsor v. Dzewaltowski, 136 Vt. 103, 105-06,
  385 A.2d 1102, 1104 (1978).  Dzewaltowski provides one possible outcome of
  a builder/owner contract dispute: "[I]f the contractor has rendered
  substantial performance of the contract, failing only in some minor
  particulars, the owner may set off against the contract price a fair
  allowance to make good the defects."  136 Vt. at 106, 385 A.2d  at 1104. 
  The trial court structured its instructions around this sentence, finding
  that it went to the heart of the parties' dispute.  The question of whether
  a party has substantially performed under a contract is a question of fact. 
  Vt. Structural Steel Corp. v. Brickman, 126 Vt. 520, 524, 236 A.2d 658, 661
  (1967).  Thus, the court instructed the jury to look first at whether
  plaintiff substantially performed and, if it found substantial performance,
  to look at whether any offset should be made.
   
       ¶  26.  The court submitted six interrogatories to the jury.  The
  jury was first asked whether plaintiff substantially performed the
  contract-defined in the instructions as an approximation of complete
  performance such that any defects "are not so serious as to deprive the
  owner of the intended use of the property"-and it answered "yes" to that
  question.  It was then asked the amount plaintiff was owed under the
  contract-defined in the instructions as "the amount due under the contact
  minus a fair allowance for defects or omissions in performance"-and the
  jury answered "$15,067," the exact amount plaintiff claimed was due it
  under the contract.  In response to question three, it found that defendant
  "breach[ed] the contract by not paying the Plaintiff the amount reasonably
  due it under the contract."  The jury went on to deal with defendant's
  counterclaim, finding plaintiff breached "by not performing in a
  workmanlike manner at least in part" and that the sum necessary to remedy
  any defects and omissions in plaintiff's performance was $4,000.

       ¶  27.  Contrary to the majority's position, the jury was never asked
  and never found that defendant acted in good faith in withholding the
  entire last payment of $15,067 because of her claims of omissions or
  defective work against plaintiff.  Nor did the jury find, as claimed by the
  majority, that defendant erred only in "miscalculating the amount she was
  entitled to withhold."  To the extent the jury verdict can be said to have
  addressed the good faith issue, it is inconsistent with such findings and
  consistent with plaintiff's view that defendant withheld the whole final
  payment out of spite.  The jury concluded that plaintiff substantially
  performed, that the offsets were relatively minor and did not interfere
  with defendant's use of the property, and that defendant breached by not
  paying the amount reasonably due.  They found offsets totaling only 26.5%
  of the unpaid last installment, less than 4% of the contract amount.

       ¶  28.  Without a jury finding that defendant withheld payment in good
  faith, and with a finding that plaintiff substantially performed and
  defendant did not pay the amount reasonably due, there are no grounds for
  denying attorney's fees to plaintiff.  Indeed, I believe that plaintiff is
  entitled to an award of fees under either of its theories: the contract
  provision and the prompt payment act, 9 V.S.A. § 4007(c).  The contract
  specifically provided for the recovery of attorney's fees paid to collect
  "outstanding balances over 30 days due from date of invoice."  The jury
  found that plaintiff had substantially performed, and therefore plaintiff
  could still enforce the contract's terms. 
   
       ¶  29.  The identical circumstances arose in Fenner & Shea
  Construction Co. v. Wadkins, 511 P.2d 924 (Colo. Ct. App. 1973), in which a
  construction contractor brought suit for breach of contract for failure to
  pay and the owners counterclaimed, arguing that the contractor had breached
  the contract by performing in an unworkmanlike manner.  511 P.2d  at 925. 
  The trial court found that the construction company "had substantially
  performed its obligations under the contract and that to the extent that it
  had failed to perform fully, its judgment against the [owners] would be
  reduced in an amount equal to that necessary to cure the complained of
  defects in workmanship."  Id.  The owners argued on appeal that the
  contractor should not receive fees because the defective work was a breach
  of the contract and therefore the contractor could not enforce the
  contract.  The appeals court rejected this argument, holding that where a
  party substantially performs, he "cannot be charged with a breach" such
  that he cannot recover attorney's fees under a contractual provision
  providing for recovery of such fees.  Id.; see also Weidner v. Szostek, 614 N.E.2d 879, 882-83 (Ill. App. Ct. 1993) (concluding that where contractor
  has substantially performed its contractual obligations, it can collect
  attorney's fees under contractual provision despite an offset for "the
  amount necessary to repair or replace the items not completed within the
  terms of the contract").  Contrary to the majority's statement, Fenner
  directly addresses plaintiff's contractual claim.  In Fenner, the trial
  court found that the contractor's defects in workmanship breached the
  contract, but awarded attorney's fees because the contractor had
  substantially performed and the amounts withheld were far in excess of a
  reasonable setoff.
   
       ¶  30.  Without citation to any authority, the majority concludes
  that the court could deny plaintiff attorney's fees under the contract for
  two reasons.  The first is that defendant claimed numerous deficiencies in
  performance, the jury found a few, and the trial court concluded that the
  jury could have found more.  In asserting this reason, the majority, like
  the trial judge, is warring with the jury determination that plaintiff
  substantially performed.  Indeed, the majority's view is transparent
  because it details one of the alleged construction defects, a defect that
  the jury could not have found, consistent with the monetary amount of its
  verdict for defendant.  The jury determines the facts in this case, not
  this Court or the trial judge, and its factual findings are directly
  contrary to those on which the majority relies.  

       ¶  31.  The second is that a subcontractor filed a mechanic's lien
  against defendant, and plaintiff will be required to pay the subcontractor
  out of its recovery.  This reason is at best irrelevant.  Indeed, it may be
  that none of plaintiff's recovery will go to profits or remuneration for
  the house construction, particularly if it is denied recovery of attorney's
  fees.  Why this economic reality should advantage defendant is not
  explained in the majority opinion.

       ¶  32.  The exact same situation arose in De Witt v. Liberty Leasing
  Co., 499 P.2d 599 (Alaska 1972), where the trial court tried to penalize a
  contractor for failing to pay a subcontractor by denying recovery of
  attorney's fees.  The Alaska Supreme Court held that the trial court does
  not have the discretion to refuse an award of fees for this purpose.  499 P.2d  at 601.  The court noted that the owner's refusal to pay the
  contractor deprived it of the funds to pay subcontractors, bringing about
  the default that the owner sought to take advantage of by avoiding paying
  the contractor's attorney's fees.  Id.  In essence, the majority is
  penalizing plaintiff because defendant failed to make a payment, a policy
  built on blaming the victim.
   
       ¶  33.  Citing Young v. Northern Terminals, Inc., 132 Vt. 125, 130,
  315 A.2d 469, 472 (1974), the majority begins with the statement that we
  review the trial court's ruling on attorney's fees to determine whether
  there is an abuse of discretion.  Young, however, is a case about the
  amount of an attorney's fee award, an issue on which the trial court does
  have discretion.  See 132 Vt. at 130, 315 A.2d  at 472 ("The trial court
  enjoys a large measure of discretion in fixing the reasonable value of
  legal services.").  Where the right to attorney's fees is provided in the
  contract, the contractor is entitled to an award as a matter of law. 
  Murphy v. Stowe Club Highlands, 171 Vt. 144, 163, 761 A.2d 688, 701-02
  (2000).  Plaintiff is entitled to an award as a matter of law in this case.

       ¶  34.  I can also find no ground to refuse to apply the prompt
  payment statute, 9 V.S.A. § 4007(c), which provides that "the substantially
  prevailing party in any proceeding to recover any payment within the scope
  of this chapter shall be awarded reasonable attorneys' fees."  See
  generally J. Hays, Prompt Payment Acts: Recent Developments and Trends,
  22-SUM Construction Law 29, 30 (explaining that eighteen states have prompt
  payment statutes similar to Vermont's statute).  The purpose of the prompt
  payment act is to provide protection to contractors and subcontractors. 
  See R.W. Sidley, Inc. v. United States Fid. & Guar. Co., 319 F. Supp. 2d 554, 560 (W.D. Pa. 2004) (decided under virtually identical Pennsylvania
  prompt payment act).  There is no dispute that the statute applies to this
  action if plaintiff comes within its specific terms.  We must apply it
  according to its plain meaning.  DJ Painting, Inc. v. Baraw Enters., 172
  Vt. 239, 247, 776 A.2d 413,420 (2001).  By its terms, it is mandatory and
  accords no discretion to the court to deny fees where it applies.  See
  Corley v. Rivertown, Inc., 863 So. 2d 1244, 1246 (Fla. Dist. Ct. App. 2004)
  (under similar Florida statute, court must award attorney's fees when the
  statute applies); John B. Conomos, Inc. v. Sun Co., 2003 PA Super. 310, ¶¶
  30-31, 831 A.2d 696 (under virtually identical Pennsylvania statute, court
  must award attorney's fees when the statute applies).
   
       ¶  35.  At the outset, I want to emphasize my main disagreement with
  the majority decision on the prompt payment act.  Although we have
  differences on the statute's meaning, and the discretion it accords to the
  trial judge as outlined below, my central point is that whether we label
  the trial court's action as an abuse of discretion or an erroneous
  construction of the law, under any possible standard of review, we cannot
  affirm the trial court's decision that plaintiff is not entitled to
  attorney's fees under the prompt payment act.  I return to this central
  point after discussing other differences with the majority decision.

       ¶  36.  The court denied attorney's fees under the statute for the
  following reasons:

    There's no question that the plaintiff prevailed, because in terms
    of sheer dollars and cents, he came out the winner.  But to say
    that that means that he substantially prevailed, I'm not prepared
    to do that.  And my reason is in part that I'm embarking [sic] the
    equitable powers of the Court which play in the area of attorney's
    fees.

  Although the majority recognizes that the statute is mandatory, it upholds
  the trial court decision as within its "exercise of discretion."  The
  majority concludes that there was no substantially prevailing party in this
  case because the "jury verdict . . . resulted in awards to both parties"
  and because part of plaintiff's recovery will go to pay off a
  subcontractor.  Ante, ¶ 13.
   
       ¶  37.  The statute awards attorney's fees to "the substantially
  prevailing party," recognizing that more than one party can recover,
  especially in a construction contract case, but only one party can be found
  to have prevailed.  9 V.S.A. § 4007(c) (emphasis added).  Thus, its
  language is consistent with the overwhelming law from around the country
  that in the case of offsetting verdicts, the holder of the net verdict on
  the main claim has prevailed.  See T. Goger, Annotation, Who Is the
  "Successful Party" or "Prevailing Party" for Purposes of Awarding Costs
  Where Both Parties Prevail on Affirmative Claims, 66 A.L.R.3d 1115, 1119-20
  (1975) (citing cases).  In a leading California case, the court found that
  the plaintiff construction company was the "successful party" where
  plaintiff won a net judgment even though the defendant homeowner had
  prevailed on a counterclaim for faulty construction.  Moss Constr. Co. v.
  Wulffsohn, 253 P.2d 483, 484-85 (Cal. Dist. Ct. App. 1953) (now superceded
  by statute, Cal. Civ. Proc. Code § 1032, defining prevailing party to
  include "the party with a net monetary recovery").  The court noted that
  "the party awarded the net judgment is the prevailing litigant and thus the
  successful party."  Id. at 485; accord De Witt, 499 P.2d  at 600
  (designating contractor as prevailing party even though homeowner allowed
  an offset and noting that trial court does not have discretion to refuse to
  award attorney's fees to penalize contractor for not paying subcontractor);
  Distefano v. Hall, 69 Cal. Rptr. 691, 697 (Ct. App. 1968) (naming
  contractor the prevailing party and awarding attorney's fees despite offset
  to owner because contractor received the net recovery); Corley, 863 So. 2d 
  at 1246 (entitling contractor to attorney's fees under similar Florida
  statute even though as a result of offset to owner, net recovery was less
  than a fifth of the amount of the last unpaid installment due from owner);
  Szoboszlay v. Glessner, 664 P.2d 1327, 1333-34 (Kan. 1983) (under landlord
  and tenant statute, tenant was successful in suit for return of a security
  deposit, and entitled to attorney's fees, even though landlord received
  smaller offsetting counterclaim judgment for unpaid rent); Schmidt v.
  Colonial Terrace Assoc., 694 P.2d 1340, 1345 (Mont. 1985) (in construction
  contract case, contractor was prevailing party and entitled to attorney's
  fees even though purchasers were awarded an offset equal to more than 50%
  of the amount awarded to contractor).  I see no reason not to follow the
  decisions from other states; they are clearly consistent with the language
  of our statute.

       ¶  38.  The majority appears to have two answers to the above
  analysis: (1) the net offset cases do not apply because "substantially
  prevailed" has a different meaning from "prevailed;" and (2) an award is a
  matter of discretion under the statute.
   
       ¶  39.  In making the former argument, the majority has drawn largely
  from federal law, quoting the Supreme Court in Ruckelshaus v. Sierra Club,
  463 U.S. 680, 684 (1983), as noting that federal fee-shifting statutes
  contain "varying standards" and Union of Needletrades, Industrial & Textile
  Employees v. INS, 336 F.3d 200, 208 (2d Cir. 2003), as saying that the
  addition of the word "substantially" goes to the amount or degree of
  recovery necessary to obtain a fee award.  In fact, the state of the
  federal law is best explained in Oil, Chemical & Atomic Workers
  International Union v. Department of Energy, 288 F.3d 452, 455 (D.C. Cir.
  2002):

    We have seen nothing to suggest that Congress sought to draw any
    fine distinction between "prevailing party" and "substantially
    prevail."  The Internal Revenue Code, for instance, defines
    "prevailing party" to mean a party who has "substantially
    prevailed." . . . Consistent with our practice (and the Supreme
    Court's) of viewing the various fee shifting statutes as
    interchangeable, we have in the past treated the "substantially
    prevail" language in FOIA as the functional equivalent of the
    "prevailing party" language found in other statutes.

  See also Loggerhead Turtle v. County Council of Volusia County, 307 F.3d 1318, 1322 n. 4 (11th Cir. 2002) (differences in language "are generally
  deemed inconsequential"); City of Chanute v. Williams Natural Gas Co., 31 F.3d 1041, 1047 (10th Cir. 1994) (party that "substantially prevails" in
  Clayton Act means the same as "prevailing party" in the Civil Rights
  Attorney Fee Act).  The Second Circuit Court of Appeals endorsed these
  decisions in Union of Needletrades.  336 F.3d  at 207-08.
   
       ¶  40.  Even if there is a difference between "prevailed" and
  "substantially prevailed," as argued by the majority, it is not clear that
  the former standard is easier for the person seeking fees to meet.  Just as
  the burden for plaintiff in establishing substantial performance is lighter
  than the burden of showing performance generally, the burden of showing
  that plaintiff substantially prevailed should be lighter than prevailing. 
  See J. Klein, Attorney's Fees and the Clean Water Act After Buckhannon, 9
  Hastings W.-Nw. J. Envtl. L. & Pol'y 109, 114 (2003).  As Oil, Chemical &
  Atomic Workers International Union points out, 26 U.S.C. § 7430(c)(4)-a
  section of the Internal Revenue Code authorizing award of attorney's fees
  to a taxpayer in certain circumstances-defines "prevailing party" as a
  party who "has substantially prevailed with respect to the amount in
  controversy."  288 F.3d  at 455.  The clear import of the section is that
  "substantially prevailing" is the easier standard to meet.  See also Manion
  v. Nagin, Civ. 00-238 ADMRLE, 2004 WL 234402, at *8 (D. Minn. 2004)
  (interpreting Florida law).

       ¶  41.  The Internal Revenue Code construction is similarly employed
  in the Washington cases.  Because of a general fee-shifting statute in that
  state, fully half the reported cases defining "substantially prevailing
  party" and "prevailing party" come from that state.  The Washington rule is
  summarized in the leading case of Riss v. Angel: "In general, a prevailing
  party is one who receives an affirmative judgment in his or her favor.  If
  neither wholly prevails, then the determination of who is a prevailing
  party depends upon who is the substantially prevailing party, and this
  question depends upon the extent of the relief afforded the parties."  934 P.2d 669, 681 (Wash. 1997) (citation omitted).  Under the Washington rule,
  "substantially prevailing party" represents a less rigorous standard than
  "prevailing party."  Whether the operative language is "prevailing party"
  or "substantially prevailing party," I would use the net offset rule.  It
  sets a bright line for administering an attorney's fee recovery policy.

       ¶  42.  The majority's second response brings me back to my primary
  point about the application of the prompt payment act to this case-unless
  we are prepared to give unlimited discretion to the trial court, the
  refusal to award attorney's fees in this case cannot be affirmed under any
  construction of the prompt payment act provision.  
   
       ¶  43.  Plaintiff in this case sought the remaining contract price of
  $15,067.  The jury verdict gave it $11,067, 73% of the requested amount. 
  In her answer and counterclaim, defendant sought three aspects of monetary
  relief: (1) a defendant's verdict on plaintiff's claim so plaintiff would
  not recover; (2) unspecified damages to put the house into the condition
  promised by the construction contract; and (3) damages in the amount of
  $15,000 for the items that could not be repaired.  There was no monetary
  figure attached to the second aspect of the damages, but the complaint
  itemized sixteen separate deficiencies that needed to be corrected,
  including resetting the house on the foundation.  Although we cannot assign
  a precise percentage to the extent of defendant's counterclaim recovery in
  relation to her demand, it is obviously a very small percentage.  Under any
  view of the term, and accounting for the discretion of the trial judge in
  applying the facts to the law, plaintiff substantially prevailed. 
   
       ¶  44.  The majority argues that we should follow Union of
  Needletrades, and hold that a party has substantially prevailed only if
  that party has prevailed to a considerable or large degree.  See 336 F.3d 
  at 208; In re Marriage of Murphy, 763 N.E.2d 933, 938 (Ill. App. Ct. 2002)
  (defining "substantially prevail" as prevailing to a "significant" degree),
  rev'd on other grounds, 786 N.E.2d 132 (Ill. 2003).  In a case the majority
  relies upon the contractor recovered only about a third of its claim
  because of offsets, obviously not meeting the requirement of a significant
  or considerable degree.  Bridges PBT v. Chatta, 2003 PA Super. 122, ¶ 10,
  821 A.2d 590.  In contrast, the plaintiff here easily met that standard,
  particularly because defendant's set-off was a small portion of plaintiff's
  award.  See Signal Mut. Indem. Ass'n v. AK-WA Inc., No. 92-36603, 1993 WL
  540283, at *3 (9th Cir. Dec. 30, 1993) (applying Washington law and
  reversing the trial court where plaintiff recovered almost 80% of the
  damages it sought and defendant recovered none); In re Marriage of Murphy,
  763 N.E.2d  at 939 (to "substantially prevail" party must "obtain at least
  50% of the relief she seeks").  Further, regardless of what degree is
  required, a party need not recover all of its claimed relief in order to
  substantially prevail.  Silverdale Hotel Assocs. v. Lomas & Nettleton Co.,
  677 P.2d 773, 774 (Wash. Ct. App. 1984).  

       ¶  45.  Although the majority endorsed Union of Needletrades for its
  holding that the court must look to the degree of recovery, neither the
  trial court nor the majority actually applied this standard.  The trial
  court apparently believed that once it found that plaintiff did not recover
  100% of its damages it had the "equitable powers" to deny attorney's fees. 
  The majority does not address the substance of the trial court decision;
  instead it discusses the equitable powers of the trial court.  Apparently,
  it believes that general powers of equity can trump both a contractual and
  statutory right to fees.  I agree that equity can in some circumstances
  create an additional power to award fees, see DJ Painting, Inc., 172 Vt. at
  246, 776 A.2d  at 419, but we have never held that equity can override a
  right to attorney's fees granted by statute or by a contractual term.

       ¶  46.  The result of the majority decision is that the trial court
  will have unlimited discretion to deny fees if a contractor recovers
  anything short of 100% of its claims.  In essence, the majority has
  rewritten the entitlement of the statute into a mere authorization.  The
  Legislature could have written the statute to authorize an award of fees,
  rather than to contain a command.  Under such a statute, the trial court
  would have had exactly the authority it claimed here.  See Gold Kist, Inc.
  v. Williams, 332 S.E.2d 22, 24 (Ga. Ct. App. 1985) (noting that, under
  Georgia law, trial court has discretion in assessing costs).  The exercise
  of discretion under our statute is inconsistent with its plain meaning.
   
       ¶  47.  I have a similar view of the trial court's action with
  respect to plaintiff's interest claim.  Plaintiff claimed interest on the
  judgment at 24%, the rate stipulated in the contract.  The trial court
  ruled that the contract rate was inapplicable because the case "went to
  trial" and instead used the statutory rate of 12%, suggesting that the
  contract rate would be usurious.  The majority upholds the decision on a
  different rationale, namely, that the jury found that defendant's refusal
  to pay the last installment was done in good faith.  The majority also
  relies on 9 V.S.A. § 4002(d) that provides for interest at the rate set in
  12 V.S.A. § 2903(b) "except as otherwise agreed."

       ¶  48.  Neither the rationale of the trial court nor that of the
  majority is sustainable.  As discussed above, the jury did not find that
  defendant withheld the $15,067 installment payment in good faith, and its
  finding that plaintiff substantially complied with its contractual
  obligations enables plaintiff to enforce the contract.  The prompt payment
  act provision, 9 V.S.A. § 4002(d), does not help defendant because it
  explicitly applies only if the parties have not "otherwise agreed," and
  they otherwise agreed in the contract before us.  Furthermore, the interest
  on default provision does not violate the usury statute.  The usury statute
  sets "the rate of interest or the sum allowed for forbearance or use of
  money [at] twelve percent per annum."  9 V.S.A. § 41a.  Under Lowell &
  Austin, Inc. v. Truax, 146 Vt. 448, 452-53, 507 A.2d 949, 951 (1985), the
  default provision does not violate the statute because it does not involve
  a loan or forbearance.  See Southwest Concrete Prods. v. Gosh Constr.
  Corp., 798 P.2d 1247, 1251-52 (Cal. 1990) (distinguishing late charges from
  loan or forbearance); R.A. Lord, Williston on Contracts § 20:34 (4th ed.
  1999) (explaining that late charges for a loan on default does not make a
  transaction usurious). 
   
       ¶  49.  Although the default provision is not usurious, it is a form
  of liquidated damages that may involve an illegal penalty.  See Highgate
  Assocs. v. Merryfield, 157 Vt. 313, 316, 597 A.2d 1280, 1282 (1991)
  (outlining test for determining if contract provision is a reasonable
  liquidated damages clause or illegal penalty).  I agree that the rate is
  suspect in the current low interest rate environment.  We held in Highgate,
  however, that the trial court must examine whether the creditor is seeking
  an unenforceable penalty under three criteria, and our standard of review
  of its conclusion is limited.  Id. at 315-16.  The trial court has not
  conducted the necessary analysis, and our limited standard of review
  prevents us from doing so in the first instance here.  I would remand for
  the analysis specified in Highgate.

       ¶  50.  In many cases, courts are required to reach a fair result,
  based on an approximation of where the equities lie.  This is not such a
  case.  Our preexisting contract law mandates that plaintiff be awarded
  attorney's fees in this case; the Legislature has reinforced this law by
  stepping in to protect construction contractors in situations where owners
  fail to pay for work done by allowing the contractor to recover attorney's
  fees incurred in pursuing a valid claim.  The policy question of what is
  fair has been determined by the Legislature and settled by contract law,
  and we have no discretion to avoid this clear law.  I dissent and am
  authorized to state that Justice Gibson joins this dissent.



                                      _____________________________________
                                      Associate Justice




Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.