D.J. Painting, Inc. v. Baraw Enterprises, Inc.

Annotate this Case
D.J, Painting, Inc. v. Baraw Enterprises, Inc. (99-401); 172 Vt. 239;
776 A.2d 413

[Filed 11-May-2001]


       NOTICE:  This opinion is subject to motions for reargument under
  V.R.A.P. 40 as well as formal  revision before publication in the Vermont
  Reports.  Readers are requested to notify the Reporter of  Decisions,
  Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801 of
  any  errors in order that corrections may be made before this opinion goes
  to press.


                                No. 1999-401


D.J. Painting, Inc.	                         Supreme Court

                                                 On Appeal from
     v.	                                         Lamoille Superior Court


Baraw Enterprises, Inc. and 	                 November Term, 2000
E.F. Wall and Associates, Inc.


Ben W. Joseph, J.

William L. Durrell of Barr & Associates, Stowe, for Plaintiff-Appellant.

J. Scott Cameron of Zalinger Cameron & Lambek, P.C., Montpelier, for 
  Defendants-Appellees.


PRESENT:  Amestoy, C.J., Dooley, Morse, Johnson and Skoglund, JJ.


       JOHNSON, J.  Plaintiff DJ Painting, Inc. appeals three orders of the
  superior court in favor  of defendants Baraw Enterprises, Inc. (Baraw) and
  E.F. Wall & Associates, Inc (Wall).  On appeal,  plaintiff argues that the
  trial court erred in (1) dismissing plaintiff's motion for a writ of
  attachment to  perfect a mechanic's lien; (2) granting defendants' motion
  for summary judgment on plaintiff's  contract claims; and (3) awarding
  attorneys' fees to defendants.  We affirm the dismissal of plaintiff's 
  motion for a writ of attachment, the granting of defendants' motion for
  summary judgment and the  award of attorneys' fees to defendant Wall.  We
  reverse the award of attorneys' fees to defendant  Baraw because the court
  erred in awarding fees based on plaintiff's bad faith.

 

       In September 1997, defendant Wall entered into a contract to serve as
  a general contractor for  improvements to defendant Baraw's property, the
  Stoweflake Resort, in Stowe, Vermont.  The total  value of the contract was
  approximately $3.2 million.  Wall then engaged plaintiff DJ Painting in a 
  standard subcontract agreement to provide taping, painting and vinyl wall
  covering services for the  project.  At the time it was executed, the
  subcontract anticipated paying plaintiff approximately  $110,500 for
  plaintiff's materials, labor and equipment.  All of plaintiff's work was
  subject to the  approval of the project architect.  Plaintiff did not enter
  into any contract with Baraw.

       Relevant clauses from the standard subcontract are as follows.  First,
  the subcontractor agrees  that all work is "subject to the final approval
  of the Architect/Engineer or other specified  representative of the Owner." 
  If the subcontractor fails to perform the specified work, then with  notice
  and opportunity to cure, the general contractor may "terminate the
  Subcontractor's  employment."  All claims "arising out of, or relating to,
  this Subcontract or the breach thereof shall  be decided by Arbitration."

       As the project progressed, Wall notified plaintiff that its work did
  not meet the standards set  forth in the subcontract.  For instance, a
  letter dated May 7, 1998, from Joseph Bordas, president of  Wall, to
  plaintiff states "the workmanship fails to meet the specified standards." 
  The record contains  evidence that plaintiff was notified several more
  times of this problem and given an opportunity to  cure.   In June 1998,
  Wall terminated plaintiff and directed plaintiff to "remove your tools, 
  equipment and personnel from the Stoweflake site."  Although plaintiff
  submitted requisitions  totaling $112,925, Wall paid plaintiff $72,925 for
  the work performed that was approved by the  project architect. 
  Subsequently, Wall credited Baraw $40,000 towards the total contract price
  owed  by Baraw to Wall.

 

       Plaintiff filed a lien against Baraw's property in October 1998
  pursuant to 9 V.S.A. § 1921,  and simultaneously filed suit against both
  defendants in superior court.  In its five count complaint,  plaintiff
  sought (1) to perfect the lien by attaching Baraw's property pursuant to 9
  V.S.A. § 1924; (2)  to recover for unjust enrichment against Baraw; (3) to
  recover in quantum meruit against Baraw; (4)  to recover for breach of
  contract against Wall; and (5) to recover for wrongful termination against 
  Wall.  In response, Wall posted a bond of $40,000, which was later
  increased to $50,000 at the  court's suggestion to cover any interest or
  costs should full damages be awarded to plaintiff.  In  December 1998,
  because of the bond posted by Wall, the court dismissed plaintiff's motion
  for a writ  of attachment against Baraw's property.  Wall also filed a
  counterclaim against plaintiff alleging  breach of contract.

       In a subsequent order, the court granted defendants summary judgment
  on plaintiff's  remaining claims.  As to the two claims against Wall, the
  court ruled that the subcontract specifically  provides that all claims
  arising out of the agreement shall be submitted to binding arbitration.  As
  to  the two claims against Baraw, the court ruled that it is not equitable
  for plaintiff to assert these  claims against Baraw when plaintiff had a
  contractually agreed upon recourse against Wall.  Two  weeks later, upon
  defendants' petition, the court awarded attorneys' fees to defendants
  pursuant to  V.R.C.P. 54.

       Following the trial court's disposition, plaintiff filed an
  arbitration claim against Wall for the  remaining $40,000 on the contract
  price.  After a one day hearing, the arbitrator awarded plaintiff  $14,700,
  plus $2,500 interest on its claim. Neither party appealed the arbitration
  decision, and Wall  paid plaintiff the full amount of the award.  That
  finalized plaintiff's actions against Wall.

 

       Plaintiff appeals the court's decision regarding the writ of
  attachment, the claims against  Baraw, and the award of attorneys' fees. 
  Plaintiff raises three issue on appeal.  First, plaintiff argues  that
  Wall's bond does not adequately substitute for a writ of attachment to
  perfect the lien. (FN1)   Second, plaintiff contends that summary judgment
  was inappropriate on its quantum meruit and  unjust enrichment claims. 
  According to plaintiff, whether or not plaintiff performed its work 
  adequately is an issue of fact that should have survived summary judgment. 
  Otherwise, Baraw  received a benefit-the painting-for which it paid no
  compensation.  Furthermore, plaintiff argues, it  ought to be able to
  recover for the fair value of the services rendered, regardless of the
  benefit  conferred on Baraw.  Because this value was not determined,
  plaintiff contends summary judgment  was error.  Finally, plaintiff claims
  that the court improperly awarded attorneys' fees to defendants by  relying
  on a bad faith standard.

                             I. Contract Claims

       Plaintiff acknowledges that it has no written contract with Baraw. 
  Therefore, plaintiff relies  on the equitable doctrines of unjust
  enrichment and quantum meruit for recovery.  Because plaintiff  disputes
  that its work was substandard, it claims that Baraw received the benefit of
  $40,000 worth of  services for which it did not have to pay.  At the very
  least, plaintiff contends that it expended 

 

  money on labor and equipment on the job and it should be compensated. 
  Under either of these  theories, plaintiff seeks to impose a quasi-contract
  obligation on Baraw to make plaintiff  whole. (FN2)

       Claims for quasi-contract are based on an implied promise to pay when
  a party receives a  benefit and the retention of the benefit would be
  inequitable.  In re Estate of Elliott, 149 Vt. 248,  252, 542 A.2d 282, 285
  (1988).  The questions before the Court are whether plaintiff has alleged 
  sufficient facts to prove that a benefit was conferred upon defendant
  Baraw, whether Baraw accepted  the benefit, and whether it would be
  inequitable for Baraw not to compensate plaintiff for its value.   Center
  v. Mad River Corp., 151 Vt. 408, 412, 561 A.2d 90, 93 (1989).  The parties
  dispute the  degree to which plaintiff's work met the architect's
  standards, and actually conferred a benefit on  Baraw.  For the purpose of
  our discussion, however, we assume that plaintiff did confer a benefit on 
  Baraw through the taping and painting services, and that Baraw did accept
  this benefit.  See Rubin v.  Town of Poultney, 168 Vt. 624, 625, 721 A.2d 504, 506 (mem.) (1998) (on summary judgment we  take all allegations made
  by the nonmoving party as true).   Even assuming that plaintiff's work was 
  at least partially acceptable, to survive summary judgment, plaintiff, as
  the nonmoving party, must  still demonstrate sufficient evidence to support
  the equity prong of the prima facie case.  Id.

       In analogous cases, we have established that "[t]he most significant
  requirement for a  recovery on quasi contract is that the enrichment to the
  defendant be unjust."  Ray Reilly's Tire Mart, 

 

  Inc. v. F. P. Elnicki, Inc., 149 Vt. 37, 40, 537 A.2d 994, 995 (1987).  See
  also Center, 151 Vt. at 413,  561 A.2d  at 94 (where there is no evidence of
  inequity there can be no damages on quasi-contract  theory); Harman v.
  Rogers, 147 Vt. 11, 18, 510 A.2d 161, 165 (1986) (implied contract claim
  fails  where plaintiff failed to sustain burden of showing mutual
  expectation of payment).  The proper  inquiry is "whether, in light of the
  totality of circumstances, it is against equity and good conscience  to
  allow defendant to retain what is sought to be recovered."  Legault v.
  Legault, 142 Vt. 525, 531,  459 A.2d 980, 984 (1983).  Therefore, plaintiff
  must demonstrate that it would be unfair for Baraw  not to pay plaintiff
  additional money above and beyond what plaintiff received from the contract 
  with Wall and the arbitration award against Wall.

       When we look at the "totality of circumstances," we find that this is
  not the ordinary quasi-contract case in which one party has performed work
  for another party without the formality of a  contract, that the party
  benefitted has accepted the services, and therefore ought to be required to
  pay  for them.  Cf. Hedges v. Schinazi, 144 Vt. 605, 481 A.2d 1046 (1984). 
  The specific work for which  payment is requested here was covered by a
  contract with a third party, the general contractor, Wall,  which in turn
  contracted with defendant.  Although the existence of the contract with
  Wall does not  necessarily preclude a remedy against defendant, the terms
  of the contract and the remedies exercised  under it become highly relevant
  in determining whether denying further payment to plaintiff is  unjust,
  such that we should imply a contract where there is none.

       Under the terms of the contract with Wall, plaintiff agreed that its
  work would be subject to  the approval of the architect.  The architect did
  not fully approve, and payment was withheld.   Eventually, as outlined
  above, plaintiff submitted under the contractual terms to arbitration,
  where  the quality of plaintiff's work was at issue.  The dispute was
  resolved in arbitration, and an  

 

  additional $17,200 was paid to plaintiff over and above the initial
  payments made, under the  contract, of approximately two-thirds of the
  contract price.  The arbitration award was not appealed.   Baraw, through
  its general contract with Wall, paid plaintiff for the full benefit of
  plaintiff's work as  determined by the arbitrator, performed on Baraw's
  property.  
  
       Plaintiff brought forward no other facts in response to summary
  judgment that would suggest  that plaintiff's fully utilized contractual
  remedies with Wall unfairly resulted in an unjust enrichment  of Baraw. 
  Plaintiff did not rely to its detriment on a promise to pay by Baraw, nor
  did plaintiff rely  on Baraw's ability to pay when it contracted with Wall. 
  See Frank W. Whitcomb Constr. Corp. v.  Cedar Constr. Co., 142 Vt. 541,
  546, 459 A.2d 985, 988-89 (1983).  Plaintiff has not identified any  reason
  why it would be just for plaintiff to receive additional compensation, such
  as collusion  between the architect and Wall, or Wall and Baraw. 
  Plaintiff's claim is simply an avoidance of the  contract with Wall.  In
  reality, plaintiff is seeking in quasi-contract the remainder of the
  contract  price with Wall, or as plaintiff states in its brief, "[i]f the
  work met the standards required by the  contract, then equity and good
  conscience demand that the Plaintiff be compensated for its work.  If  the
  work was deficient, the Plaintiff is entitled to something less and
  possibly nothing at all."  In  other words, plaintiff is attempting to
  relitigate its claim against Wall by pursuing Baraw.  At this  point, to
  require Baraw to pay plaintiff above the amount it paid Wall would force
  Baraw to pay  twice for the same service.  Morrisville Lumber Co. v.
  Okcuoglu, 148 Vt. 180, 184, 531 A.2d 887,  889 (1987) ("The retention of a
  benefit is not unjust where defendants have paid for it. . . .  To allow 
  plaintiff to recover in these circumstances would be to require defendants
  to pay twice.").

       In Morrisville, the plaintiff subcontractor supplied lumber to a
  general contractor who was  building a vacation home for the defendant
  owner.  After the owner terminated the general because 

 

  of a contract dispute, the plaintiff sued the general to recover for the
  materials and supplies it had  provided before the general was terminated,
  and the plaintiff won a judgment by default.  When  plaintiff's judgment
  against the general was not satisfied, the plaintiff looked to the owner
  for  recovery.  Id. at 182, 531 A.2d  at 888.  The relationship between the
  parties in that case and the  present litigants are nearly identical.  The
  Court in Morrisville denied the plaintiff's unjust  enrichment claim
  because, like the case at bar, the defendant owner had already fully paid
  the general  contractor for the all the benefits the owner had received. 
  Id. at 184, 531 A.2d  at 889.  Where an  owner has fulfilled its financial
  obligation to a general contractor, a subcontractor cannot rely on the 
  owner to satisfy the relationship between the subcontractor and the
  general.  See DCB Constr. Co. v.  Central City Dev. Co., 940 P.2d 958, 963
  (Colo. Ct. App. 1996) (absent special circumstances,  benefit conferred
  upon owner by performance of contract with a third party cannot form the
  basis of  claim of unjust enrichment); Henning v. Security Bank, 564 N.W.2d 398, 403 (Iowa 1997) (absent  contractual privity with a homeowner,
  a subcontractor has no valid quasi-contract claim against the  homeowner);
  Commerce P'ship 8098 Ltd. P'ship v. Equity Contracting Co., 695 So. 2d 383,
  390  (Fla. Dist. Ct. App. 1997) (where owner has given consideration for
  subcontractor's work by paying  general the contract price, subcontract
  cannot claim unjust enrichment against the owner); Kujawa v.  Billboard
  Cafe at Lucas Plaza, Inc., 10 S.W.3d 584, 589 (Mo. Ct. App. 2000)
  (ordinarily, landlord  not liable on quantum meruit theory for value of
  services provided at request of tenant); Peace River  Elec. Coop. v. Ward
  Transformer Co., 449 S.E.2d 202, 213-14 (N.C. Ct. App. 1994) (owner not 
  unjustly enriched by subcontractor's performance when general was fully
  paid by owner, despite  ongoing dispute over payment between general and
  subcontractor).

 
        
       As we stated in Morrisville, "[t]he success of a claim for unjust
  enrichment depends on the  particular facts and circumstances of each
  case."  148 Vt. at 184, 531 A.2d  at 889.  We find no  inequity here because
  plaintiff has alleged none.  Failure to receive the contract price under
  the  circumstances of this case is not enough to prove that Baraw has been
  unjustly enriched.  Moreover,  it can hardly be equitable to impose a
  contract on the parties that completely undermines the  contractual
  relationships that the parties themselves have created.  The point of
  hiring a general  contractor for a construction job is for the general to
  manage the job and hire the subcontractors.   The owner does not deal
  directly with the subcontractors, and often is unaware of the identity of
  the  subcontractors.  See id. at 183-84, 531 A.2d  at 889; Whitcomb, 142 Vt.
  at 542, 459 A.2d  at 986.  The  owner pays the general contractor, but if
  the general does not pay the subcontractors, the  subcontractors have the
  statutory lien mechanism to attach money as yet unpaid to the general 
  contractor.  9 V.S.A. § 1921.  That was not the case here, as the general's
  failure to pay the  subcontractor arose out of a dispute over the work,
  which was fully resolved under the contract  between general and
  subcontractor.  The contract between the general, Wall, and the
  subcontractor,  plaintiff, sufficiently protected the rights of the
  parties.   No equitable relief is warranted and  summary judgment was
  appropriate on this issue.

                            II.  Attorneys' Fees

       The trial court awarded defendants attorneys' fees on the basis of two
  theories.  The first is  bad faith.  The court held that plaintiff acted in
  bad faith when it filed suit against Baraw and Wall  despite the
  arbitration clause in the subcontract agreement.  By suing both Wall and
  Baraw without  first seeking arbitration, plaintiff disregarded contract
  obligations and imposed litigation costs on  defendants.  The second theory
  under which the court imposed attorneys' fees is statutory.  The court 

 

  used 9 V.S.A. § 4007(c), which states "the substantially prevailing party
  in any proceeding to recover  any payment within the scope of this chapter
  shall be awarded reasonable attorneys' fees," as  additional support for
  the award to Wall only.  The court found that Wall was a substantially 
  prevailing party because it won summary judgment on plaintiff's claims.

       The court erred in awarding attorneys' fees based on plaintiff's bad
  faith.  We apply the  'American Rule' with regard to attorneys' fees, which
  means that parties must bear their own  attorneys' fees absent a statutory
  or contractual exception.  Myers v. Ambassador Ins. Co., 146 Vt.  552, 558,
  508 A.2d 689, 692 (1986).  This Court has, however, recognized the ability
  of courts to use  their equity power to award fees "as the needs of justice
  dictate."  In re appeal of Gadhue, 149 Vt.  322, 327, 544 A.2d 1151, 1154
  (1988).  This power may be invoked "only in exceptional cases and  for
  dominating reasons of justice."  Sprague v. Ticonic Nat'l Bank, 307 U.S. 161, 167 (1939).  In  Gadhue, we quoted the New Hampshire Supreme Court in
  explaining the type of conduct that would  justify an award of attorneys'
  fees.

    Bad faith conduct held to justify the award of counsel fees has
    been  found where one party has acted in bad faith, vexatiously,
    wantonly,  or for oppressive reasons where the litigant's conduct
    can be  characterized as unreasonably obdurate or obstinate, and
    where it  should have been unnecessary for the successful party to
    have brought  the action.

  Gadhue, 149 Vt. at 329, 544 A.2d  at 1155 (quoting Harkeem v. Adams, 377 A.2d 617, 619 (1977)).   Applying this standard, in both Gadue and Harkeem
  attorneys' fees were awarded when a litigant was  compelled to appear more
  than once in the state supreme court before obtaining relief.

 

       Plaintiff's conduct is not so outrageous as to warrant an award of
  attorneys' fees on this  ground.  Defendants have won on the merits at the
  trial court and before this Court.  Multiple trips  through the state court
  system were not required.  Nor is there any indication that plaintiff acted 
  obdurately or obstinately in conducting the litigation.  The trial court
  correctly points out that a  reasonable reading of the subcontract
  agreement might foreclose the action prosecuted by the  plaintiff here.  We
  cannot find, however, that plaintiff's conduct is such that "dominating
  reasons of  justice" require an award of attorneys' fees.  Thus, we reverse
  the award of fees for defendant Baraw.

       As for defendant Wall, however, we agree with the trial court that
  under 9 V.S.A. § 4007(c)  attorneys' fees are appropriate.  Our paramount
  goal in statutory construction is to give effect to the  Legislature's
  intent, Burlington Elec. Dep't v. Vermont Dep't of Taxes, 154 Vt. 332, 335,
  576 A.2d 450, 452 (1990), and thus we apply the plain meaning of a statute
  where the language is clear and  unambiguous, Reed v. Glynn, 168 Vt. 504,
  506, 724 A.2d 464, 465 (1998).   Section 4007 is part of  Chapter 102 of
  Title 9, which explicitly governs construction contracts.   It is clear
  that Wall is the  "substantially prevailing party" in a "proceeding to
  recover any payment" due under a construction  contract.  Plaintiff's
  arguments to the contrary are without merit.  Defendant Wall was sued for 
  breach of contract and wrongful termination.  Because there was an
  arbitration clause in the contract  between Wall and plaintiff, plaintiff's
  claims were dismissed on summary judgment.  The  counterclaims brought by
  Wall were raised simply to preserve its rights, should Wall not succeeded 
  to dismiss the case against it.  The dismissal of those counterclaims on
  summary judgment can  hardly be seen as a victory for plaintiff.

 


       Affirmed in part, reversed in part.




                                       FOR THE COURT:



                                       _______________________________________
                                       Associate Justice



------------------------------------------------------------------------------
                                  Footnotes


FN1.  Plaintiff, in its brief, argued that posting of the $50,000 bond by
  defendants does not substitute  for plaintiff's right to attach the
  property.  It contends that nowhere in the statutory scheme outlining the 
  lien procedure is there a mention of bond substitution.  At oral argument,
  however, plaintiff conceded that  the attachment issue is moot because, in
  effect, the posted bond protects plaintiff's potential recovery.   Thus, we
  need not reach the merits of this issue.  Cf. Newport Sand & Gravel Co. v.
  Miller Concrete  Constr. Inc., 159 Vt. 66, 68, 614 A.2d 395, 396 (1992)
  (noting in dicta that bond posted by general  contractor obviated the need
  for a writ of attachment to enforce lien filed under 9 V.S.A. § 1921).

FN2.  Plaintiff argues that its claims for unjust enrichment and quantum
  meruit are distinct causes of  action.  In fact, the distinction between
  the two lies not in the alleged wrong committed by the defendant  but
  rather in the measure of recovery for that wrong. "Unjust enrichment
  focuses on the value of the  benefit actually conferred upon the defendant. 
  Quantum meruit, on the other hand, is determined by the  reasonable value
  of plaintiff's services regardless of their value to defendant."  In re
  Estate of Elliott, 149  Vt. 248, 253 n.2, 542 A.2d 282, 285-86 n.2 (1988). 
  Although we need not decide the issue because of our  disposition of this
  case, it would appear that plaintiff cannot recover on both equitable
  claims.  To do so  would allow plaintiff recovery twice for the same harm,
  just applying a different measure of damages.



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.