In re Allco Renewable Energy Limited et al.
Annotate this CaseAllco Renewable Energy Limited appealed a Public Utility Commission (PUC) order which found that Allco had begun “site preparation for . . . an electric generation facility” without first obtaining a certificate of public good (CPG) in violation of 30 V.S.A. 248(a)(2)(A). The PUC enjoined Allco from any further site preparation unless certain criteria were satisfied and explained that, following another hearing, it would determine a civil penalty for Allco’s violation under 30 V.S.A. 30(a). On appeal, Allco challenged the PUC’s injunction order. Because there was not yet a final appealable order, the Vermont Supreme Court dismissed this appeal for lack of jurisdiction.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.