New England Partnerships, Inc. v. Rutland City School District

Annotate this Case
New England Partnership, Inc. v. Rutland City School Dist. (2000-108); 
173 Vt. 69; 786 A.2d 408

[Filed 14-Sep-2001]

[Motion for Reargument Denied 29-Oct-2001]


       NOTICE:  This opinion is subject to motions for reargument under
  V.R.A.P. 40 as well as formal  revision before publication in the Vermont
  Reports.  Readers are requested to notify the Reporter of  Decisions,
  Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801 of
  any  errors in order that corrections may be made before this opinion goes
  to press.


                                No. 2000-108


New England Partnership, Inc.	                 Supreme Court

                                                 On Appeal from
     v.	                                         Washington Superior Court


Rutland City School District	                 June Term, 2001



Mary Miles Teachout (findings and conclusions) and Alden T. Bryan (judgment 
  order), JJ.

Michael B. Clapp, Burlington, for Plaintiff-Appellant. 

William H. Meub and Erin Gallivan (On the Brief) of Keyser Crowley, P.C., 
  Rutland, for Defendant-Appellee.


PRESENT:  Amestoy, C.J., Dooley, Morse, Johnson and Skoglund, JJ.


       SKOGLUND, J.   In this dispute over payment due under a construction
  contract, appellant  New England Partnership, Inc. (NEPI), architects of a
  building and remodeling project for appellee  Rutland City School District
  (district), appeals the Washington Superior Court's determination that  the
  amount still owed on the contract to NEPI was $41,059.  NEPI argues that
  the trial court erred in  (1) its calculation of the contingent fee amount
  due pursuant to paragraph six of the addendum to the  contract; (2) its
  determination of the "basic compensation" amount pursuant to paragraph 3 of
  the  addendum agreement; (3) its calculation of the amount of prejudgment
  interest to be awarded NEPI;  and (4) its holding that the Prompt Pay Act,
  9 V.S.A. §§ 4001-4009, does not apply to 

 

  paragraph 6 of the addendum.  The district presents three cross claims as
  well: that the trial court  erred in (1) its determination that NEPI was
  owed any amount under the contingent fee agreement in  paragraph six of the
  addendum; (2) its calculation of the contingent fee amount pursuant to 
  paragraph six of the addendum; and (3) its award of attorney's fees to
  NEPI.  We agree with NEPI on  its first, second, and third arguments, and
  disagree with its fourth argument as well as the arguments  presented by
  appellee on cross-appeal.  We therefore affirm the trial court's decision
  in part, reverse  in part, and remand. 					

                            I. Factual Background

       We begin with the facts, as found by the trial court, which are
  relevant to this appeal.  On  December 8, 1989, the parties entered into a
  written agreement in which NEPI would provide the  district with
  architectural services for the building of a new high school and the
  renovation of other  buildings.  The agreement was memorialized in a
  standard American Institute of Architects contract,  and incorporated a
  budget dated November 16, 1989 which had previously been developed by NEPI 
  for the district for bond vote purposes.  The agreement specified in
  paragraph 11.2 the "basic  compensation" NEPI was to receive for its
  services. It stated, in pertinent part, that "basic  compensation" shall be
  computed as "[t]he Stipulated Sum of Eight Hundred Twenty Five Thousand 
  Dollars (Gross Fee of $853,000.00 less $28,000.00 credit for payments for
  pre-bond services)[.]"    On May 16, 1990, the parties agreed to change the
  compensation portion of the agreement to reflect a  cost of $8,804 for
  insurance, resulting in a new basic compensation fee of $816,196.   

       In June 1990 the district's Act 250 permit request was denied.  In
  August, when it appeared  that it would be some time before the permit
  would be obtained, NEPI stopped working on the plans 

 

  for the high school.  In January 1991, NEPI informed the district that when
  the project resumed, its  fees would need to be increased as a result of
  the delay.

       The Act 250 permit was granted in the summer of 1992, and NEPI resumed
  work on the  drawings.  On July 23, 1992, NEPI informed the district of
  what would be necessary to complete the  project, and that completion would
  cost the district $466,373 in additional fees above and beyond the 
  original contract amount.  Despite NEPI's letter providing a description of
  the bases for these  increased costs, the district was upset over this
  increased amount, finding it difficult to understand  why, with the
  construction drawings 58% complete, so much in additional fees was
  necessary.

       On July 28, NEPI provided a new budget which called for a total
  project cost of $16 million -  substantially higher than the $8.7 million
  project cost at the time of the bond vote.  The district  requested that
  NEPI come up with a fixed fee for the completion of the project, and during
  the next  three months NEPI worked with the district to develop a budget
  and scope for the project that would  be in balance with the district's
  available funding.  On September 14, a budget in line with the  available
  funding was presented to the district, with construction costs for the high
  school at  $9,002,000, not including a four-percent construction
  contingency.  The budget included a fixed fee  for NEPI's services for the
  entire project at $1,095,585, plus $91,475 in start-up costs.  At this
  time,  NEPI indicated that it was willing to address the issue of the near
  $150,000 in project suspension  costs by making payment for them contingent
  on the project being bid below the budget for  construction.  

       On October 13, 1992, the parties met to negotiate a revised contract,
  as the original  agreement was due to expire.  As a result of these
  negotiations, on November 23, 1992 the parties  agreed on the terms of an
  addendum to the contract.  Subsequently, the district contacted a 

 

  construction company to manage the construction project, and on April 13,
  1993 the district and the  construction company agreed on a "guaranteed
  maximum price" (GMP) for the overall project of  $10,183,406, including a
  guaranteed maximum price of $8,759,405 for construction of the high  school
  portion of the project.  The construction project agreed to with the
  construction company  differed from that planned by NEPI, as the district
  specifically eliminated from this later agreement  certain items present in
  the NEPI plans and drawings in order to ensure that the district would have 
  money left over.  The project then went out for bidding, and the project,
  as bid on, resulted in a  savings of $342,760.   

       On July 12, 1993, NEPI submitted a bill to the district for the
  contingency fee called for  under paragraph six of the addendum.  The bill
  referred to $9,001,500 as the amount by which the  contingency was to be
  calculated, and claimed that the GMP, as adjusted for bid savings, was
  below  this amount.  The district did not pay the bill for the contingency. 

                         II. NEPI's Claims on Appeal

       NEPI first argues the trial court erred in calculating the suspension
  contingency amount as  described in paragraph six of the addendum. 
  Paragraph six provides:

    Owner agrees to pay Architect additional contingent compensation 
    over that already set out above.  The contingent compensation will
    be  50% of the amount, if any, by which the high school GMP, as 
    adjusted through completion of bidding, is lower than the October
    13,  1992, estimate, attached hereto, up to a maximum contingent 
    compensation of $50,000.00.  For example, if the adjusted GMP is 
    $50,000.00 lower than the October 13, 1992 estimate, Architect
    will  receive $25,000.00, if the adjusted GMP is $101,000.00 or
    more  lower than the October 13, 1992 estimate, Architect will
    receive only  $50,000.00.  The calculation of the contingent
    compensation will be  made at the completion of bidding and
    payment shall be made out of  initial bond proceeds.      

 

  NEPI claims that the trial court erred in adjusting the "high school GMP"
  upwards, as there was no  provision in the addendum for such an upward
  adjustment.    

       We note initially, as to NEPI's claims that paragraph six does not
  provide for any upward  adjustment of the "high school GMP," that the
  addendum does not specifically state that the  adjustment to be made at the
  completion of bidding is limited to decreasing the "high school GMP" 
  amount.  NEPI's proposed construction of the phrase "as adjusted through
  completion of bidding"  allows only a downward adjustment of the high
  school GMP.  NEPI does not, however, indicate  whether this argument was,
  if ever, presented to the trial court.  The trial court's decision makes no 
  reference to whether there was an issue as to the ambiguity of the language
  NEPI now challenges.  It  found that portions of paragraph six were
  ambiguous, but it did not state whether or not it had  concluded, or even
  considered, if the adjustment language at issue here was ambiguous.  
  Accordingly, we will not search the record to determine if the issue was
  preserved for review.  See   In re Wright, 131 Vt. 473, 490, 310 A.2d 1, 10
  (1973) ("This Court is not required nor about to  undertake a search for
  claimed error where it is not adequately briefed, supported by argument, or 
  pointed out in the record before us.").  Therefore, absent any indication
  the argument was raised  below, the matter is not before us on appeal. 
  Bull v. Pinkham Eng'g Assocs., 170 Vt. 450, 459, 752 A.2d 26, 33 (2000)
  ("Contentions not raised or fairly presented to the trial court are not
  preserved for  appeal.").   

       The trial court did conclude that the second portion of the suspension
  contingency in  paragraph six - referring to the "October 13, 1992
  estimate"-was ambiguous because of the  unresolved question of whether that
  description referred to the budgeted amount in the estimate with,  or
  without, the 4% construction contingency amount included.  However, the
  trial court did not find 

 

  or conclude that the first portion of the contingency clause, pertaining to
  the high school GMP, was  ambiguous.  Nor did it present any other
  reasoning or authority supporting its decision to add back to  the "high
  school GMP" the items it categorized as "items that were eliminated from
  the guaranteed  maximum price contract, but were clearly in the October
  13th, 1992 drawings" and "items that  although not clearly depicted on
  either the October 13th, 1992 drawings or specifically named in the 
  budget, are ones that both sides expected through representations and
  discussions would be  components of the building as defined in the addendum
  contract."   The court also refused, when so  requested by NEPI, to
  describe with any particularity the individual components of each of these 
  categories. 

       "The trial court has a fundamental duty to make all findings necessary
  to support its  conclusions, resolve the issues before it, and provide an
  adequate basis for appellate review."   Secretary, Agency of Natural Res.
  v. Irish, 169 Vt. 407, 419, 738 A.2d 571, 580 (1999); see also  V.R.C.P.
  52(a); Roy v. Mugford, 161 Vt. 501, 507, 642 A.2d 688, 692 (1994).  "It is
  the duty of the  court, in making findings of facts, to sift the evidence
  and state the facts.  The purpose of V.R.C.P.  52 findings is to make a
  clear statement to the parties, and to this Court if appeal is taken, of
  what  was decided and how the decision was reached."  Arnold v. Arnold, 141
  Vt. 118, 120, 444 A.2d 890,  891 (1982) (emphasis in original) (citations
  and internal punctuation omitted).  "Findings made  under Rule 52,
  V.R.C.P., are required to report the factual ingredients essential to the
  disposition."   Standard Packaging Corp. v. Goodrich, 131 Vt. 57, 59, 300 A.2d 541, 543 (1972).

       The trial court's "findings" on the categories of project items
  eligible for add-back failed to  satisfy the requirements of V.R.C.P. 52. 
  The court's refusal to identify the components of the  categories it
  decided to add back deprived the parties an opportunity to challenge the
  propriety of the 

 

  court's decision of what should or should not be included in the add-back. 
  This is particularly  pertinent to this case, as both sides have claimed
  error in either what was, or was not, added  back. (FN1)  This omission
  also deprived this Court the opportunity to meaningfully review the trial 
  court's findings.  Therefore, we remand the matter back to the trial court
  to enter findings identifying  the specific items, and their prices, which
  composed the four add-back categories, and to provide the  reasoning
  supporting making such add-backs to the "high school GMP."


       The district argues that the trial court did not need to provide
  specific findings on what items  composed each of the categories of
  add-backs, citing Bonanno v. Bonanno, 148 Vt. 248, 251, 531 A.2d 602, 604
  (1987) for the proposition that "[w]hile it is the better practice to
  articulate the  specific facts upon which the ultimate facts are based, it
  is not reversible error to omit to do so."  In  Bonanno, the trial court
  failed to provide information on why certain insufficiencies rendered a 
  custody evaluation report's recommendation invalid.  Id. at 251, 531 A.2d 
  at 604.  We held that the  evaluation report was not the sole basis for the
  court's conclusion, and that the report was just one  factor considered in
  making its custody award.  Id.  The present case is clearly distinguishable
  from  Bonanno, as the findings omitted here are not simply one of several
  other factors the court examined  in making the conclusion challenged on
  appeal, and thus Bonanno does not apply to the present case.

 

       NEPI further argues that the trial court erred as a matter of law in
  concluding that NEPI's  estimate of the high school guaranteed maximum
  price was $9,001,500 rather than $9,361,600.  The  trial court concluded
  that there was an ambiguity in addendum paragraph six's reference to the 
  "October 13, 1992 estimate" as to whether or not the addendum language
  includes the 4%, or  $360,100, construction contingency amount present in
  the estimate.  The pertinent portion of the  estimate reads as follows:	

             1.  ESTIMATED EXPENSES
                 A. HIGHSCHOOL/TECHNICAL CENTER
             . . . . 
                    6.  Contingency:  4% x $9,001,500      360,100
                                                        $9,361,600

  Upon examining the evidence presented, the court determined that the lower
  number, without adding  in the 4% construction contingency, was the correct
  amount.  

       The issue of whether or not a contract term is ambiguous is a matter
  of law for the trial court  to decide.  Isbrandtsen v. North Branch Corp.,
  150 Vt. 575, 577, 556 A.2d 81, 83 (1988).    "Ambiguity will be found where
  a writing in and of itself supports a different interpretation from that 
  which appears when it is read in light of the surrounding circumstances,
  and both interpretations are  reasonable."  Id. at 579, 556 A.2d  at 84. 
  Extrinsic evidence may be introduced to aid in the  construction of a
  written instrument once an ambiguity has been found.  Id. at 577, 556 A.2d 
  at 83. 

       The trial court correctly identified that paragraph six makes no
  mention of whether or not the  4% construction contingency is applicable to
  the calculation of the suspension contingency.  In  examining how to
  resolve this ambiguity, the trial court found that NEPI used the lower
  figure in its  own initial billing for the contingency fee, and that in
  notes from meetings on January 4 and 5, 

 

  1993, NEPI used the lower figure as a reference point for the cost of the
  building.  These findings are  sufficient to support the trial court's
  decision resolving the ambiguity; therefore, we will not disturb  its
  conclusion on appeal.  State v. Austin, 165 Vt. 389, 398, 685 A.2d 1076,
  1082 (1996) ("We will  uphold the trial court's legal conclusions if
  reasonably supported by its findings."). 

       NEPI's next argument is that the court erred in setting at $967,296
  the basic compensation  payable to it under paragraph three of the
  addendum, and, as a result, the district received a double  credit for
  $28,000 in pre-bond work performed by NEPI.  Paragraph three reads as
  follows:

    The Architect's total compensation under Article 11.1 & 11.2 is 
    amended from $853,000.00 to $1,004,100.00.  All sums paid 
    Architect to date will be treated as compensation under this
    portion of  this Agreement and credited against the $1,004,100.00. 

       The December 8, 1989, contract called for "basic compensation" for
  basic services in the  amount of $825,000, an amount arrived at by
  subtracting $28,000 "credit for pre-bond services" from  the "gross fee" of
  $853,000.  Also, on May 16, 1990, the parties agreed to change the
  compensation  portion of the agreement to reflect a cost of $8,804 for
  insurance, which further reduced the basic  compensation amount.  The court
  concluded that paragraph three of the addendum was ambiguous as  to whether
  or not these credits were to be subtracted from the new amount.  The court
  stated that  "[t]here is something of an ambiguity there" and resolved this
  ambiguity in favor of the district.  It  stated that "the most reasonable
  way to read the addendum together with the original contract is  simply to
  replace the $853,000 number with the $1,004,100 number."  The court further
  concluded  that the effect of the addendum was to change the basic
  compensation amount to $1,004,100, subject  to a reduction of $28,000
  credited in paragraph 11.2.1 of the December 8, 1989 

 

  contract, as well as the $8,804 change reflecting the cost of insurance,
  resulting in a basic  compensation amount of $967,296. 

       "A provision in a contract is ambiguous only to the extent that
  reasonable people could differ  as to its interpretation."  Isbrandtsen,
  150 Vt. at 577, 556 A.2d  at 83.  If a court finds a writing to be 
  ambiguous, "the proper interpretation becomes a question of fact, to be
  determined on all relevant  evidence."  Kipp v. Chips Estate, 169 Vt. 102,
  107, 732 A.2d 127, 131 (1999).  

    We will not set aside a trial court's findings unless clearly
    erroneous,  nor disturb its conclusions if they are reasonably
    supported by the  findings.  Findings are viewed in the light most
    favorable to the  judgment, disregarding modifying evidence, and
    will not be disturbed  merely because they are contradicted by
    substantial evidence; rather,  an appellant must show that there
    is no credible evidence to support  the finding.
         
       Agency of Natural Res. v. Glens Falls Ins. Co., 169 Vt. 426, 432, 736 A.2d 768, __ (1999)  (citations omitted).
 
       Extrinsic evidence may be introduced to aid in the construction of a
  written instrument once  an ambiguity has been found.  Isbrandtsen, 150 Vt.
  at 577, 556 A.2d  at 83.  In this case, examination  of the October 13, 1992
  estimate makes clear that the trial court's construction of the addendum
  and  contract will result in the district receiving a double credit for
  $28,000 worth of pre-bond services.   Under the trial court's construction,
  the credit is first received by the district in the October 13, 1992 
  estimate's calculation of the $1,004,100 total compensation amount, as that
  number includes the  "pre-bond credit" of $28,000.  The second credit is
  manifest in paragraph 11.2.1 of the December 8,  1989 contract when the
  original $853,000 amount is replaced, per the trial court's construction of
  the  addendum, with $1,004,100, because this paragraph requires the
  additional subtraction of  "$28,000  credit for payments for pre-bond
  service." 

 

       The district makes no argument in support of the trial court's
  interpretation of paragraph three  of the addendum - it simply states that
  appellant's argument is without merit.  After examining the  October 13,
  1992 estimate, it does not appear that the trial court's conclusion is
  reasonably supported  by the findings.  The trial court made no findings on
  the issue of how to construe the contract.  It  simply concluded that there
  was an ambiguity, took evidence on the issue, and then resolved the  issue
  in favor of the district - all without giving a factual basis for so
  holding.  It did note that the  $1,004,100 amount is available in the
  estimate, even though "[i]t is only available by adding and  subtracting
  certain numbers that require [a] certain amount of sophistication and
  understanding of  that budget."  However, the estimate also specifically
  indicates the $28,000 pre-bond credit was  already taken out in the
  calculation of the estimated expense of the design of the high school
  portion  of the project, and there is no credible evidence in the record
  supporting a conclusion contrary to this  evidence.  Therefore, we disagree
  with the trial court's conclusion that, upon replacing "$853,000.00"  in
  paragraph 11.2.1 of the contract with "$1,004,100.00," the district is also
  entitled to the additional  $28,000 credit provided in paragraph 11.2.1.  

       NEPI's next argument is that the trial court erred in calculating the
  interest award of $8,640,  claiming that the court abused its discretion
  and erred as a matter of law when it calculated the  interest at the rate
  of 6% "rather than the legal rate of interest of 12%."  9 V.S.A. § 41a(a)
  provides  that "the rate of interest . . . for forbearance or use of money
  shall be twelve percent per annum  computed by the actuarial method."  We
  recognized in Greenmoss Builders, Inc. v. King, 155 Vt. 1,  8, 580 A.2d 971, 975 (1992), that "[i]nterest is a legal right of the plaintiff.  When
  a debt becomes  payable, if the contract does not stipulate a rate of
  interest, the statutory or legal rate applies."   "Reversal of the court's
  prejudgment interest award is warranted only if the method of calculation 

 

  chosen was so 'irrational as to amount to an abuse of discretion.'"  Remes
  v. Nordic Group, Inc., 169  Vt. 37, 41, 726 A.2d 77, 80 (1999) (citing In
  re Merrill, 157 Vt. 150, 154, 596 A.2d 345, 348  (1991)).  In the present
  case, neither side argues that the contract contained a provision for 
  prejudgment interest awards or any other interest rate provision applicable
  in this situation.   Therefore, the trial court's application of a 6%
  interest rate, in the absence of any mention of interest  rates in the
  contract itself, and contrary to the clearly-enumerated statutory rate of
  12%, constitutes  an abuse of discretion warranting reversal.  

       NEPI's final argument is that the trial court erred in holding that
  the Prompt Pay Act (PPA), 9  V.S.A. §§ 4001-4009, does not apply to
  paragraph six of the addendum.  The PPA was enacted in  1991, and applies
  only to contracts entered into on or after January 1, 1992.  See id.  The
  contract at  issue in this case was entered into on December 8, 1989, and
  modified by the addendum agreement  on November 23, 1992.  The question
  raised is whether the PPA therefore has effect on the contract,  or the
  addendum, or both.

       NEPI states that the PPA applies to paragraph six of the construction
  contract, as that  paragraph "is completely independent of any of the
  provisions or terms contained in the 1989  Agreement."  They claim that
  this paragraph reflects a settlement agreement reached by the parties 
  regarding costs incurred when the project was suspended because of Act 250
  problems,  and is "not  merely an alteration of provisions contained in the
  1989 Agreement" but is "instead an entirely new  agreement reached in
  settlement."  We disagree.  It is a generally understood principle of
  contract  construction that "[t]he modification of a contract results in
  the establishment of a new agreement  between the parties which pro tanto
  supplants the affected provisions of the original agreement while  leaving
  the balance of it intact."  Beacon Terminal Corp. v. Chemprene, Inc., 429 N.Y.S.2d 715, 

 

  717-18 (1980) (citing in part 6 Corbin, Contracts, § 1293).  Thus, the
  addendum provision is not  itself a stand-alone agreement, and NEPI's
  argument for application of the PPA fails.

                 III. The District's Claims on Cross-Appeal

       The first claim by the district is that the condition precedent to
  payment of the contingency  fee described in paragraph six of the addendum
  was never met.  In support of this position, the  district claims that the
  district provided testimony showing that the intent of the district was to
  pay  the contingency only if the district received the school as
  contemplated on October 13, 1992, and,  since the school as built deviated
  from that contemplated design, the condition was not met.   

       "We interpret the contract according to its terms and the parties'
  intent as expressed in the  contract language."  Suchoski v. Redshaw, 163
  Vt. 620, 622, 660 A.2d 290, 292 (1995).  From the  plain meaning of the
  language of paragraph six, there is no expression that the intent of the
  parties  was to attach the satisfaction of the contingency to the actual
  building received.  The language  provides that the contingency is met if
  "the high school GMP, as adjusted through completion of  bidding, is lower
  than the October 13, 1992 estimate," and makes no mention of the finished
  project  as such would relate to the contingency being met.  We therefore
  reject the district's argument.

       The district's second claim is that the trial court erred in awarding
  attorney's fees to NEPI  because the award was tied to finding a
  contingency, and because the trial court stated that under the 
  circumstances NEPI was entitled to attorney's fees.  As we disagree with
  the district that the  paragraph six contingency was not met, we address
  only the claim that the court erred in "finding"  that the contract
  entitled NEPI to fees in this case.  The contract provides that, should a
  party breach  the agreement, the party "forced to take any action to
  collect sums due it . . . may also recover all  costs of collection
  (including court costs and reasonable legal fees)."  "We will not disturb
  the trial 

 

  court's findings of fact unless they are unsupported by the evidence or
  clearly erroneous."  State v.  Zaccaro, 154 Vt. 83, 86, 574 A.2d 1256, 1258
  (1990).  By arguing that the court's statement that  NEPI is entitled to
  attorney's fees in this case is the equivalent of reading the contract as
  mandating  attorney's fees in the event of a breach, the district displays
  a misunderstanding of the word "entitle."  To be entitled to fees is not
  only to have a mandatory right to such, but also to "furnish with proper 
  grounds for seeking or claiming."  Black's Law Dictionary 477 (5th ed.
  1979).  In light of the trial  court's finding that the contingency was
  owed to NEPI, its conclusion that NEPI was also entitled to  attorney's
  fees under the contract was supported by the evidence.

       Affirmed in part, reversed in part, and remanded.



                                       FOR THE COURT:



                                       _______________________________________
                                       Associate Justice




------------------------------------------------------------------------------
                                  Footnotes


FN1.  One of the district's claims on cross-appeal is that the trial
  court erred in failing to add-back category four as well, arguing that
  this category contains items taken out but contemplated  under the October
  13, 1992 estimate.  However, as the district fails to provide any support
  for this  proposition in the four sentences it devotes to the argument in
  its brief, we will not address it on  appeal.  See State Farm Mut. Auto
  Ins. Co. v. Powers, 169 Vt. 230, 242, 732 A.2d 730, 738 (1999)  (noting
  this Court will not address issues inadequately briefed).   



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.