In re Application of East Ohio Gas Co.
Annotate this Case
The Supreme Court affirmed the orders of the Public Utilities Commission of Ohio approving a stipulation that authorized Dominion Energy Ohio to implement its capital expenditure program rider (CEP Rider), holding that the Commission's orders were not unlawful or unreasonable.
Dominion filed an application to recover the costs of its capital expenditure program by establishing the CEP Rider at issue. Dominion and the Commission jointly filed a stipulation asking the Commission to approve the application subject to the staff's recommendations. The Commission modified and approved the stipulation. The Supreme Court affirmed, holding (1) the Commission did not violate an important regulatory principle in adopting the 9.91 percent rate of return; (2) the Commission did not inconsistently apply its precedent; (3) the Commission did not violate Ohio Rev. Code 4903.09; and (4) Appellants' manifest-weight-of-the-evidence argument failed.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.