Ohio Power Co. v. Burns
Annotate this Case
In this dispute over whether Ohio Power Company, a private agency authorized to appropriate property under Ohio Rev. Code 163.01(B) and (C), was entitled to any of the necessary presumptions set forth in Ohio Rev. Code 163.09(B)(1) in establishing the necessity of easements through eminent domain to upgrade electric transmission lines, the Supreme Court held that the court of appeals properly reversed the trial court's determination that the appropriations at issue were necessary.
Specifically, the Supreme Court held (1) the term "appropriation" in Ohio Rev. Code 163.09(B)(1) means the appropriation of the "parcel or contiguous parcels in a single common ownership, or interest or right therein," as identified in the petition filed by an agency under Ohio Rev. Code 163.05; (2) because neither Ohio Power's board of directors nor the Ohio Siting Board reviewed the appropriations Ohio Power was not entitled to a rebuttable presumption under section 163.09(B)(1)(a) or an irrebuttable presumption under section 163.09(B)(1)(c); and (3) Ohio Power was entitled to a rebuttable presumption under section 163.09(B)(1)(b) because it provided evidence of the necessity for the appropriations. The Court remanded this case for further proceedings.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.