IDT Corp. v. Tyco Group, S.A.R.L.

Annotate this Case
Download PDF
================================================================= This opinion is uncorrected and subject to revision before publication in the New York Reports. ----------------------------------------------------------------No. 135 IDT Corp. et al., Appellants, v. Tyco Group, S.A.R.L., et al., Respondents. Stephen P. Younger, for appellants. Thomas E. L. Dewey, for respondents. JONES, J.: At issue in this breach of contract action is whether the settlement agreement made the negotiation and execution of further agreements a pre-condition to the parties' obligation. We hold that it did and affirm the order of the Appellate Division. By written settlement agreement entered October 10, - 1 - - 2 - No. 135 2000, IDT and Tyco agreed to drop their pending lawsuits. The pending lawsuits arose from a dispute between IDT and Tyco over a Memorandum of Understanding. IDT claimed that Tyco owed it $30,000,000 after withdrawing from a joint venture to construct a fiber optic communications network. against IDT. Tyco also had a claim All pending claims between the parties were discharged pursuant to the settlement agreement. The settlement agreement, among other things, also called for Tyco to provide IDT with an "indefeasible right of use" (IRU)1 of certain fiber optic capacity free of charge for a fifteen year period. The capacity was to be on Tyco's TyCom Global Network (TGN), a subsea cable system planned to connect North America, Asia and Europe. At the time of the settlement, the TGN was not yet constructed. The agreement states that "[t]he IRU shall be documented pursuant to definitive agreements to be mutually agreed upon and, in any event, containing terms and conditions consistent with those described herein." These further definitive agreements, and the IRU, were to be in writing and consistent with Tyco's standard agreements with similarly situated customers. Tyco's standard agreements were not in existence at the time the settlement was made. On June, 12 2001, Tyco submitted the proposed IRU 1 An IRU is a legal interest that confers a right of access to some or all of the capacity in a telecommunications cable system of another party. - 2 - - 3 document to IDT. No. 135 The submitted IRU had provisions that IDT claims were inconsistent with the settlement agreement, including one for decommissioning the network after five years, without IDT's permission. In addition, IDT claimed there were other terms and conditions in the IRU which were inconsistent with the settlement agreement. The parties negotiated over the draft, however, and IDT eventually acquiesced in a decommissioning provision. Negotiations continued to be active, but flagged after a sharp drop in the market greatly reduced the value of the capacity Tyco had agreed to supply. The negotiations finally came to an end in March 2004. On May 5, 2004 IDT brought suit against Tyco, alleging breach of the settlement agreement. After Tyco filed its answer and counterclaims, IDT moved for summary judgment on the issue of liability and on Tyco's counterclaims. Tyco cross-moved for summary judgment on IDT's breach of contract claim. Supreme Court granted IDT's motion, finding Tyco liable, and dismissed Tyco's counterclaims and cross-motion. The Appellate Division reversed Supreme Court's order by denying IDT's summary judgment motion and granting Tyco's cross-motion to dismiss the complaint. The court held that (1) the settlement agreement was not a fully enforceable contract when entered into, (2) the agreement was contingent on the negotiation of additional terms and (3) Tyco's proposal of purportedly inconsistent terms did not constitute a breach of contract. The Appellate Division granted IDT leave to - 3 - - 4 - No. 135 appeal and certified the following question to this Court: "Was the order of this Court, which reversed the order of the Supreme Court, properly made?" We now affirm the order of the Appellate Division and answer the certified question in the affirmative.2 IDT asserts that the settlement agreement was a fully enforceable contract which bound the parties. It further claims that the settlement agreement was breached on June 12, 2001 when Tyco submitted the IRU containing terms inconsistent with the terms of the settlement agreement. First, IDT says the IRU had a "decommissioning" provision which provided that Tyco could decommission the network after 5 years without IDT's permission even though IDT has an indefeasible right to use the network for 15 years free of charge. Second, it required IDT to pay for the premature shutdown of the network despite IDT's entitlement to free access, as well as free operations, administration and management of the network. In addition, IDT argues that the IRU required IDT to waive its damage remedies in the event that Tyco 2 The parties debate whether the settlement is a Type I or Type II preliminary agreement as used in federal line of cases, such as, Brown v Cara (420 F3d 148 [2nd Cir 2005]) and Teachers Inc. and Annuity Ass'n of America v Tribune Co. (670 F.Supp 491 [SDNY 1987]). While we do not disagree with the reasoning in federal cases, we do not find the rigid classifications into "Types" useful. In reaching its decision the Appellate Division constructed a new category - a "contingent Type I agreement." However, we find that it is enough to ask in this case, whether the agreement contemplated the negotiation of later agreements and if the consummation of those agreements was a pre-condition to a party's performance. In the instant matter, it clearly was. - 4 - - 5 - No. 135 breached the settlement agreement, even though IDT had dismissed its prior claim against Tyco as part of the settlement agreement. At the outset, we agree with IDT that the parties entered into a valid settlement agreement. "[S]tipulations of settlement are judicially favored and may not be lightly set aside" (Will of Kanter, 209 AD2d 365 [1st Dept 1994] [internal citations omitted]). As we said in Hallock v State of New York (64 NY2d 224, 230 [1984]), "strict enforcement [of settlement agreements] not only serves the interest of efficient dispute resolution but is also essential to the management of court calendars and integrity of the litigation process." Although there was a valid settlement agreement in this case, Tyco's obligation to furnish capacity never became enforceable because agreed-upon conditions, were not met. "[A] contract is to be construed in accordance with the parties' intent, which is generally discerned from the four corners of the document itself. Consequently, 'a written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms' (MHR Capital Partners LP v Presstek, Inc., 12 NY3d 640, 645 [2009], quoting Greenfield v Philles Records, 98 NY2d 562, 569 [2002])." Further, "a condition precedent is 'an act or event, other than a lapse of time, which, unless the condition is excused, must occur before a duty to perform a promise in the agreement - 5 - - 6 - No. 135 arises' (Calamari and Perillo, Contracts § 11-2, at 438 [3d ed]; see Restatement [Second] of Contracts § 224; see also Merritt Hill Vineyards v Windy Hgts. Vineyard, 61 NY2d 106, 112-113). Most conditions precedent describe acts or events which must occur before a party is obliged to perform a promise made pursuant to an existing contract, a situation to be distinguished conceptually from a condition precedent to the formation or existence of the contract itself (see M.K. Metals v Container Recovery Corp., 645 F2d 583)" (Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d 685, 690 [1995]). Here, the settlement agreement contemplated the occurrence of numerous conditions, i.e., the negotiation and execution of four additional agreements, most importantly, the IRU. Regarding the IRU, the clear intent of the parties was that it had to be executed before any handover of capacity. As such, it cannot be said that defendants breached the settlement agreement by merely proposing an IRU which allegedly contained terms inconsistent with settlement. Nevertheless, under the settlement agreement, the parties were required to negotiate the terms of the IRU and other agreements in good faith. Despite the fact that (1) the parties negotiated various open terms on and off for almost three years and (2) each side had a right to require conformance with Tyco's standard agreements, except to the extent that any term conflicted with the settlement agreement -- i.e., - 6 - the parties - 7 - No. 135 had an alternative mechanism for determining those terms if the negotiations were unsuccessful: the IRU was never executed. Finally, the record does not support a finding that Tyco breached any of its obligations. Accordingly, the order of the Appellate Division should be affirmed, with costs, and the certified question answered in the affirmative. * * * * * * * * * * * * * * * * * Order affirmed, with costs, and certified question answered in the affirmative. Opinion by Judge Jones. Judges Ciparick, Graffeo, Read, Smith and Pigott concur. Chief Judge Lippman took no part. Decided October 22, 2009 - 7 -

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.