International Transmission Co. v. Federal Energy Regulatory Commission, No. 19-1190 (D.C. Cir. 2021)
Annotate this Case
The DC Circuit denied a petition for review brought by three electrical transmission companies (Transcos), subsidiaries of the same parent company, challenging FERC's decision to reduce the enhanced return on equity FERC had previously authorized them to collect from ratepayers due to their status as standalone transmission companies.
The court rejected ITC's contention that FERC arbitrarily and capriciously departed from precedent establishing a particular methodology to assess Transco independence. The court explained that FERC, consistent with its stated intent in Order No. 679, never established any definitive methodology, let alone the one ITC claims it did. In this case, FERC has consistently applied a case-by-case approach to determining Transco independence, considering ownership and business structure as part of that inquiry since it first granted a Transco adder in 2003. When the adder was codified in 2006, Order No. 679 built on prior practice by identifying certain criteria that ITC now mistakenly claims constitute "a new corporate-structure test." The court also rejected ITC's contention that FERC exceeded its statutory authority by reducing ITC's Transco adders without first finding the adders to be unjust and unreasonable. Rather, the court concluded that there was substantial evidence to support FERC’s finding that the merger had reduced ITC's independence, thereby rendering the existing adders unjust and unreasonable.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.