Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission, No. 19-1091 (D.C. Cir. 2021)
Annotate this Case
In 2016, the Federal Energy Regulatory Commission approved, as just and reasonable, cost allocations filed by PJM, the Mid–Atlantic’s regional transmission organization, for a project to improve the reliability of three New Jersey nuclear power plants. The Commission denied a complaint lodged by Delaware and Maryland alleging a large imbalance between the costs imposed on the Delmarva transmission zone and the benefits that zone would accrue from the project. On rehearing in 2018, the Commission reversed course, concluding that application of PJM’s cost–allocation method to the project violated cost–causation principles and was therefore unjust and unreasonable under the Federal Power Act, 16 U.S.C. 824e. The Commission’s replacement cost–allocation method shifted primary cost responsibility for the project from the Delmarva zone to utilities in New Jersey.
The New Jersey Agencies argued that the Commission departed from precedent without adequate explanation, made findings that are unsupported by substantial evidence, and failed to respond meaningfully to objections raised during the proceedings. The D.C. Circuit denied their petitions for review. The Commission reasonably decided to adopt a different cost–allocation method for the type of project at issue here and adequately explained its departure from the cost allocations it had approved in 2016.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.