FirstEnergy Service Co. v. FERC, No. 12-1461 (D.C. Cir. 2014)
Annotate this CaseFirstEnergy, acting on behalf of its affiliates (ATSI), filed a complaint with FERC contending that the imposition of costs from transferring from one Regional Transmission Organization (RTO) to another on ATSI was unjust and unreasonable. The Commission disagreed and dismissed the complaint. FirstEnergy then petitioned for review. The court denied the petition for review because FirstEnergy failed to carry its burden under section 206 of the Federal Power Act, 16 U.S.C. 824(e), that Schedule 12 of PJM's, the RTO FirstEnergy transferred to, tariff was unjust and unreasonable as applied to ATSI.