Russ Skallerup and Beauford E. Myers, Individually and o/b/o a class of similarly situated persons, and Burchwood Bay Sewer Improvement District, and Carpenter Dam Catherine Heights Sewer Improvement District v. City of Hot Springs, Arkansas, and Honorable Mike Bush, Mayor of Hot Springs, Arkansas, in his official capacity
Annotate this Case
Download PDF
ARKANSAS COURT OF APPEALS
NOT DESIGNATED FOR PUBLICATION
SARAH J. HEFFLEY, JUDGE
DIVISION I
RUSS SKALLERUP and BEAUFORD E.
MYERS, Individually and o/b/o a class of
similarly situated persons, and
BURCHWOOD BAY SEWER
IMPROVEMENT DISTRICT, and
CARPENTER DAM – CATHERINE
HEIGHTS SEWER IMPROVEMENT
DISTRICT
APPELLANTS
V.
CITY OF HOT SPRINGS, ARKANSAS,
and HONORABLE MIKE BUSH, Mayor
of Hot Springs, Arkansas, in his official
capacity
APPELLEES
CA 07-1022
May 7, 2008
APPEAL FROM THE GARLAND
COUNTY CIRCUIT COURT
[NO. CV-2004-1156-I]
HONORABLE JOHN HOMER WRIGHT,
CIRCUIT JUDGE
REVERSED AND REMANDED
Appellants brought this class-action suit challenging disparate sewer rates imposed by
the City of Hot Springs, specifically contesting the higher rates charged to residents outside
the city limits than those who reside within the city. The circuit court granted summary
judgment to the City. On appeal, appellants contend summary judgment should not have
been granted because: (1) the City breached its contracts with the districts and their
customers; (2) the City should be estopped from charging appellants higher rates; (3) the
circuit court erred in refusing to hold that the issues determined in this action were res
judicata; (4) the City’s imposition of a higher debt-service charge on customers outside the
city limits was unreasonable and, therefore, invalid. We hold that the evidentiary items
presented by the parties left a material fact unanswered, and accordingly, we reverse and
remand.
In the late 1960s and early 1970s, the City was forced to construct a regional
comprehensive sewer collection and treatment system for the City and its area of reasonablyanticipated growth due to serious pollution problems with Lake Hamilton. State and federal
agencies imposed a building ban precluding any new construction in and around Hot Springs
until these problems had been addressed, which had a disastrous effect on Garland County’s
economy. Several improvement districts were formed inside and outside the City in response
to this problem, and federal funds were released for the construction of a comprehensive
sewer project to serve the area within the city limits and a large part of the five-mile planning
area outside the city limits. The sewer improvements within the districts were substantially
financed by the landowners/members. Appellants Burchwood Bay and Carpenter Dam were
among these districts.
In 1980, the City and the districts entered into written agreements providing that the
districts would dedicate their sewer improvements, once completed, to the regional sewer
system, which promised to charge “all customer users within the district at the same rate
established by ordinance as other customer users of the system.” Burchwood’s improvements
were formally dedicated to the City in 1997 through an agreement and assignment, which
conveyed the sewer improvements in exchange for the City’s agreement to provide services
within the district “in accordance with the City’s policy, unless the same shall conflict with
… any existing contracts of the district.” Carpenter Dam entered into similar agreements
-2-
CA 07-1022
when it dedicated its improvements to the City.
Until June 21, 2004, the City charged its users the same rates whether they were
inside or outside the city limits; however, on that date, the City enacted Ordinance No.
5274, which imposed a rate schedule that was significantly higher for the customers outside
the city limits than it was for those inside the city limits. This ordinance also imposed a
higher debt-service charge for residents outside the city limits.
On November 8, 2004, appellants filed this action challenging the ordinance. In their
complaint, appellants alleged that the City breached its contractual obligations to the districts
and their members when it enacted the ordinance; that the City should be estopped from
enacting the ordinance because the districts and their members had relied on the City’s
promises to charge the districts’ members the same rate as other users; that the City’s decision
to disparately increase the debt-service charge violated appellants’ rights of due process and
equal protection under the Arkansas Constitution; that the debt-service charge was actually
an improperly-levied tax; and that the disparate rates were unreasonable. Appellants asked
for a declaratory judgment and temporary and permanent injunctive relief. On September
2, 2005, a class was certified of all persons who had paid wastewater bills for services outside
the city limits since the ordinance’s effective date.
After the lawsuit was filed, appellants learned of a prior dispute between some of the
districts and the City, which was settled by a consent decree in the Garland County
Chancery Court in 1994. In that case, a city ordinance that allowed the City to impose
additional burdens on customers outside the city limits for connection to the sewer system
-3-
CA 07-1022
was invalidated. Specifically, the court found that: (1) the property owners and former district
members were third-party beneficiaries of the contracts between the districts and the City;
(2) the districts were formed and taxes were paid by the district members in reasonable
reliance on the City’s promises and past practices of allowing connection to the city water
and sewer system with no other prerequisites required, and the City was now estopped from
requiring property owners to either annex to the City or promise to do so in the future in
order to obtain city water and sewer service; (3) the resolution requiring annexation to the
City violated an agreement between the City and the United States Environmental
Protection Agency, which stated that the sewer system would be a regional one, that the
City would accept connections and provide service to property outside the city limits, and
no mention was made of any preconditions to providing that service.
On September 8, 2006, appellants moved for partial summary judgment on their
requests for declaratory and injunctive relief. In their accompanying brief, appellants argued
that the ordinance should be declared invalid on the basis of estoppel; that the City had
breached its contracts with the districts and their customer users; that the customer users of
the districts were third-party beneficiaries of the City’s contracts with the districts; and that
the ordinance was unconstitutional.
In response, the City argued that the agreements between the City and the
improvement districts had expired when the districts were dissolved; that there was no order
or agreement in effect prohibiting the City from establishing different rates for customers
inside and outside the City and, therefore, no justifiable reliance; and that Ark. Code Ann.
-4-
CA 07-1022
§§ 14-234-110 and 14-234-111 (Repl. 1998) permitted the imposition of different rates. In
reply, appellants argued that the dissolution of the districts did not end the City’s contractual
obligations to users in the districts. Relying on the 1994 consent decree, appellants argued
that the City was actually in contempt of court in enacting the latest ordinance.
In its supplemental response brief, the City contended that the original contract
between the City and Burchwood Bay was not the final contract between those parties,
noting that they executed a new contract on April 21, 1982, which stated:
Sewer Rates. The City covenants and agrees to maintain rates for the services of the
System, including increases from time to time as necessary to always provide net
revenues of the System sufficient to pay as due all requirements of Sewer Bonds,
Contractual Payments, and all other obligations payable from revenues of the System,
and to make adequate provision for the depreciation of the System.
The City also stated that, just before its dissolution on June 2, 1997, Burchwood entered into
another contract with the City, which stated:
In consideration of said Agreement by said DISTRICT, the CITY agrees to operate
and maintain the constructed system … and to collect user charges, levy industrial cost
recovery charges, to operate and maintain the collection systems and the pump
stations, and other project appurtenances and equipment, and further, to enforce the
sewer use ordinance developed by the CITY as more particularly set out in the
United States Environmental Protection Agency grant program.
The City also stated that the Carpenter Dam-Catherine Heights District had entered into
similar agreements on July 12, 1983, and July 30, 1996.
The City contended that the later agreements did not require the City to treat all users
the same and that, by entering into the 1982, 1983, 1996, and 1997 contracts, the parties had
modified their original contracts that did require all users to be treated the same. The City
-5-
CA 07-1022
distinguished this case from the situation presented in the previous lawsuit by noting that (1)
when the 1993 lawsuit was filed and settled, the improvement districts had not yet been
dissolved, and (2) the 1993 action did not involve sewer rates or user charges. The City
asserted that the 1994 consent order simply established that connection to the City’s sewer
service could not be withheld from the plaintiffs.
On November 3, 2006, the City moved for summary judgment for the same reasons
that it had argued in response to appellants’ motion for partial summary judgment.
On December 8, 2006, the circuit court issued an order denying appellants’ motion
for partial summary judgment, stating:
1.
The current contracts entered into between the various improvement
districts and the City of Hot Springs do not provide for equal rates
between the district users and in-city users.
2.
The pleadings and exhibits presented do not establish the elements of
estoppel.
3.
Garland County Chancery Court Case No. 93-1639, styled as Burchwood
Bay-Highway 7 South Sewer Improvement District No. 20, et al vs
Ellis, et al, filed in 1993, does not address the issue presented by this
case, and the Consent Order entered therein does not control this case.
4.
From the foregoing, the Court finds no basis to grant the Plaintiffs’
Motion for Partial Summary Judgment on Counts VI and VII, and
therefore the same is denied.
On June 13, 2007, the circuit court granted summary judgment to the City.
Appellants requested findings of fact and conclusions of law on June 15, 2007, and moved
for reconsideration on June 18, 2007. On July 11, 2007, appellants filed their notice of appeal
from the grant of summary judgment to the City. The circuit court later entered the
-6-
CA 07-1022
following findings of fact and conclusions of law: (1) there is no contractual obligation
requiring the City to charge the members of the districts the same rates as other users; (2)
promissory estoppel can be a basis for relief only when there is no contract, and in this case,
the parties entered into contracts; (3) no citation of authority was submitted that would
support the contention that the members of the districts were denied due process and equal
protection; (4) the method of setting the rates complies with the contracts existing between
the City and the members of the districts, as well as the relevant case law; (5) the ordinance
is constitutional and consistent with relevant statutory authority and case law; (6) [appellants]
are not entitled to any injunctive relief.
Summary judgment is appropriate when there are no genuine issues of material fact,
and the moving party is entitled to judgment as a matter of law. Pakay v. Davis, 367 Ark.
421, 241 S.W.3d 257 (2006). Once the moving party has established a prima facie
entitlement to summary judgment, the opposing party must meet proof with proof and
demonstrate the existence of a material issue of fact. Id. On appellate review, this court
determines if summary judgment was appropriate based on whether the evidentiary items
presented by the moving party in support of the motion leave a material fact unanswered.
Id. This court views the evidence in a light most favorable to the party against whom the
motion was filed, resolving all doubts and inferences against the moving party. Id. The
standard is whether the evidence is sufficient to raise a fact issue, not whether the evidence
is sufficient to compel a conclusion. Wagner v. General Motors Corp., 370 Ark. 268, ___
S.W.3d ___ (2007). Summary judgment is not proper where the evidence, although in no
-7-
CA 07-1022
material dispute as to actuality, reveals aspects from which inconsistent hypotheses might
reasonably be drawn and reasonable minds might differ. Technology Partners, Inc. v. Regions
Bank, 97 Ark. App. 229, 245 S.W.3d 687 (2006).
We first address appellants’ breach-of-contract argument. In its argument in support
of summary judgment, appellee argued that the City’s agreements in the original contracts
were no longer enforceable because the districts later entered into agreements that formally
assigned their sewer improvements to the City, and those later agreements did not include
language requiring district users to be charged the same rate as city users. In effect, the City
argued that the later agreements superseded, or modified, the earlier contract, and the trial
court appears to have agreed with that argument. In its findings of fact and conclusions of
law, the trial court found that contracts were entered into between the parties, but there was
no contractual obligation requiring the City to charge the members of the districts the same
rates as other users.
On appeal, appellants contend that finding was in error because the later agreements
did not repudiate or modify the original agreement, and in fact, the later agreements
expressly stated that the City would provide services within the district “in accordance with
the CITY’S policy, unless the same shall conflict with … any existing contracts of the
DISTRICT.” In response, appellee contends that the later agreements were a modification,
and further, that our supreme court found, in a similar situation, that a modification of the
contract was not necessary for the City to increase rates in a disparate manner. In Delony v.
Rucker, 227 Ark. 869, 302 S.W.2d 287 (1957), our supreme court addressed the issue of
-8-
CA 07-1022
whether the Little Rock municipal waterworks may charge its nonresident consumers higher
rates than those paid by residents of the city. Contrary to the ruling of the trial court, the
supreme court held that the challenged legislation was not void and that the City could
charge disparate rates as long as they were reasonable. The supreme court also addressed an
additional argument raised by a water improvement district, which asserted that the increased
rate schedule impaired the obligation of a contract between it and the city. Our supreme
court addressed this argument as follows:
In 1925 the private company which then owned what is now the municipal
waterworks system agreed to sell water to the residents of this district at the same rates
that were then, or might later be, in effect within the city. The performance of this
contract was assumed by the municipality when it purchased the system in 1936. It
is now asserted by the district that the imposition of the higher nonresident rates
constitutes an unconstitutional impairment of the obligation of its contract. To this
contention there are two answers. First, an agreement fixing public utility rates to be
charged in the future is subject to the sovereign's reserved power of rate regulation
and must yield to the exercise of that power. Camden v. Arkansas Light & Power Co.,
145 Ark. 205, 224 S.W. 444; North Little Rock Water Co. v. Water Works Comm. of
City of Little Rock, supra. Second, this particular contract contains no provision fixing
the period of its duration; it is therefore terminable at the will of either party. Fulghum
v. Town of Selma, 238 N.C. 100, 76 S.E.2d 368; Childs v. City of Columbia, supra.
227 Ark. at 874, 302 S.W.2d at 290.
Appellee asserts that the factual basis of Delony is analogous to the case at bar, the only
difference being that the City and the districts have also modified their written contracts via
the later Agreement and Assignment documents. First, we are not convinced that the fact
situation in Delony is sufficiently analogous to the present facts to be controlling. In Delony,
the city of Little Rock voluntarily undertook to provide services to consumers outside the
municipal boundaries. In doing so, it bought the existing waterworks system from a private
-9-
CA 07-1022
company and assumed its contract with nonresidents. In the case at bar, the City was forced
to construct a regional comprehensive sewer system. Improvement districts were formed
inside and outside the City’s boundaries, and these districts’ landowners/members largely
financed the sewer improvements, which they ultimately dedicated to the City. Thus, the
cost of the system was funded by members of districts both within and without the city
limits.
Second, we do not agree that it is clear, as a matter of law, that the later agreements
between the City and the districts superseded or modified the earlier agreement, nor do we
necessarily agree that the later agreements allowed disparate rates between city and non-city
members of the same district, as opposed to disparate rates between districts only. Under
general contract law, both parties must agree to a modification of a contract and to the terms
of the modification. Luningham v. Ark. Poultry Federation Ins. Trust, 53 Ark. App. 280, 922
S.W.2d 1 (1996). In interpreting contracts, the fundamental inquiry centers on determining
the intent of the parties at the time of the agreement. Moss v. Allstate Ins. Co., 29 Ark. App.
33, 776 S.W.2d 831 (1989). Whether the later contracts were a modification of the original
agreement, or whether the later contracts’ silence as to the clause in question constituted a
waiver by the districts, are questions of fact that should have been tried. We therefore reverse
and remand for further proceedings. Because we decide that summary judgment was
inappropriate as to this issue, we decline to address appellants’ other arguments.
Reversed and remanded.
HART and VAUGHT, JJ., agree.
-10-
CA 07-1022
-11-
CA 07-1022
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.