AURC III, LLC v. Point Ruston Phase II, LLC (Majority)
Annotate this Case
The case involves AURC III LLC, an Oregon limited liability company, and several Washington and Delaware limited liability companies collectively referred to as Point Ruston. Point Ruston purchased a 97-acre former copper smelter and environmental clean-up site located on the Puget Sound waterfront in Ruston and Tacoma, Washington, for $169,000,000 and developed it in phases. To fund the second phase of development, Point Ruston negotiated a $66 million loan from American United Development Group, which created AURC III LLC to raise and manage funds from foreign investors seeking United States residency. After disbursing the full amount of the loan, AURC filed an amended complaint against Point Ruston, alleging that Point Ruston was delinquent on interest payments in breach of its loan agreement. The superior court ordered Point Ruston and AURC to engage in arbitration as per their loan agreement.
The arbitrator issued an interim award only on the amount of current and default interest due and awarded $10,969,015 to AURC. The arbitrator then issued a final award for the same amount, as well as awarding attorney fees and arbitration fees and expenses. In total, Point Ruston was required to pay over $11.4 million. AURC moved to confirm the award and for presentation of judgment. Initially, Point Ruston agreed AURC was “entitled to confirmation of the Award and entry of a Final Judgment” but opposed attaching the arbitrator’s awards to that judgment. Before the court could enter the written confirmation order and judgment, Point Ruston paid the award and filed a motion to dismiss the case as moot because no live dispute remained. After AURC alerted the court that it received the award amount from Point Ruston, the court denied the motion to dismiss. The court entered the confirmation order with the interim and final awards attached as exhibits, as well as a judgment against Point Ruston. AURC filed a full satisfaction of judgment.
Point Ruston appealed on two grounds. It challenged (1) the superior court’s denial of the motion to dismiss and (2) the court’s decision to attach the arbitration awards to the confirmation order. Division Two of the Court of Appeals affirmed in an unpublished opinion. Point Ruston sought review in the Supreme Court of the State of Washington, which was granted.
The Supreme Court of the State of Washington held that when a party seeks a confirmation order, RCW 7.04A.220 requires issuance of the order subject to narrow exceptions inapplicable here. Payment of an arbitration award does not render the underlying case moot. The court also held that attaching an arbitrator’s award merely identifies the basis for the confirmation order. Accordingly, the court affirmed the Court of Appeals.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.