Town of Rutland v. City of Rutland

Annotate this Case
Town of Rutland v. City of Rutland (97-430); 170 Vt. 87; 743 A.2d 585

[Filed 22-Oct-1999]


NOTICE:  This opinion is subject to motions for reargument under V.R.A.P. 40
as well as  formal revision before publication in the Vermont Reports. 
Readers are requested to notify the  Reporter of Decisions, Vermont Supreme
Court, 109 State Street, Montpelier, Vermont 05609-0801 of any errors in
order that corrections may be made before this opinion goes to press.


                                No. 97-430


Town of Rutland	                                 Supreme Court

	                                         On Appeal from
     v.		                                 Rutland Superior Court

City of Rutland	                                 April Term, 1999
East Mountain Land Company and
John A. Russell Corp.


Alden T. Bryan, J.


       Mark L. Sperry and Kevin E. Brown of Langrock Sperry & Wool,
  Middlebury, for Plaintiff-Appellee.

       Paul S. Kulig and Katherine G. Bulchanan (On the Brief) of Keyser,
  Crowley, Carroll, George & Meub, P.C., Rutland, for Defendants-Appellants.


PRESENT:  Amestoy, C.J., Dooley, Morse, Johnson and Skoglund, JJ.


       JOHNSON, J.   Defendants East Mountain Company and John A. Russell
  Corporation  appeal the superior court's ruling that a water line under
  Gleason Road in the Town of Rutland is  the property of the Town.  John A.
  Russell Corp. (Russell) was the general contractor for a  development owned
  by East Mountain Company and installed the water line at issue.  After a 
  dispute with the Town over whether it would compensate Russell/East
  Mountain for the line,  East Mountain agreed to sell the water line to the
  City of Rutland.  The trial court declared the  line belonged to the Town. 
  We affirm.

       In 1985, Congregational House, Inc. began construction of ninety-nine
  condominium 

 

  units on forty-four acres located in the Town, on the north side of Gleason
  Road.  Russell was  engaged as the general contractor.  Congregational
  House abandoned the project in 1986.  East  Mountain Company, owned by the
  individual John A. Russell, bought the land and continued to  develop the
  parcel.  Russell Corp. remained the general contractor, and the development
  was  named Heritage Hill.

       The Town of Rutland completely surrounds the City of Rutland.  Gleason
  Road runs east  from Route 4 in the City of Rutland.  It is in the City for
  approximately one-quarter mile and  then enters the Town.  The Heritage
  Hill development is in the Town.  The water line that  services Heritage
  Hill runs along the south side of Gleason Road from Route 4 in the City and 
  crosses into the Town along with Gleason Road.  At the entrance to Heritage
  Hill, the line  crosses under Gleason Road into the development.  The line
  carries water from the City water  system.

       In September 1986, Russell obtained permission from the City to
  install the water line  within the City's right-of-way along Route 4 and
  Gleason Road.  The agreement stated "the line  w[ill] be built . . . and
  prepared according to the plans prepared by Aronson & Olson, Inc. and  will
  become a City water main once it's completed."  The City and Russell agreed
  to transfer the  line without compensation, in exchange for the permission
  to install it in the City right-of-way.

       This case concerns the parallel agreement made with the Town of
  Rutland.  No one  disputes that there was an agreement to have the Town
  take over the Gleason Road water line on  completion.  Russell, however,
  maintains that the Town agreed to pay compensation for the line,  and the
  Town denies it.  As Russell did not quitclaim the line, East Mountain chose
  to 

 

  resolve the dispute in November, 1992, by signing a contract with the City
  of Rutland purporting  to transfer the disputed section of line (within the
  Town boundaries) to the City.  East Mountain  received no compensation at
  the time but would receive "hook-on" fees from users who tapped  into the
  line after the date of the contract.  These fees would be paid almost
  solely by Town  residents.

       In May 1993, the Town filed suit to have the disputed section of line
  declared free of any  right, title, or interest of the City and to declare
  the November 1992 agreement between the City  and East Mountain void.  The
  City counterclaimed, seeking ownership of the entire water  distribution
  system of the Town by condemnation.  In July 1994, Rutland Superior Court
  granted  the Town's motion for summary judgment dismissing the City's
  counterclaim.  The Town's  claims proceeded to trial.

       After a bench trial, the court entered a decision for the Town.  The
  court made specific  findings of fact that the Town had granted permission
  for installation of the line at a warned  hearing, attended by
  representatives of the owners and general contractor for Heritage Hill. 
  The  court further found that both parties expected the line to become Town
  property upon completion  without compensation being paid.  The court
  concluded, "John Russell has simply changed his  mind.  He later saw it to
  his advantage to demand compensation."  The court awarded ownership  of the
  Gleason Road water line within Town limits to the Town.  Defendants East
  Mountain  Company and John A. Russell Corporation (Defendants) appeal.  The
  City did not appeal the  court's decision.

       Defendants allege that the trial court erred in deciding:  (1) that
  the water line in Gleason  Road became the property of the Town by
  operation of law; (2) that there was an agreement 

 

  between the Town and Russell and concluding that the agreement was not
  barred by Vermont's  Statute of Frauds; (3) that William Kollhepp,
  Russell's agent, had authority to form the  agreement; (4) that the dig
  permit, without reservations or conditions regarding the water line,  was
  irrelevant to the inquiry; and (5) that the meeting at which the agreement
  was made  complied with Vermont's Open Meeting Law. 

       Conclusions of law by the trial court will be upheld if supported by
  the findings.  See  Abbiati v. Buttura & Sons, Inc., 161 Vt. 314, 318, 639 A.2d 988, 990 (1994).  Therefore, our  review of the challenged conclusions
  begins with the court's findings and our determination of  whether the
  findings support the conclusions.  

       The central finding at issue in this case was that Russell agreed to
  transfer the line in  exchange for the Town's permission to install it in
  Gleason Road.  The existence of an  agreement is ordinarily a question of
  fact for the trier.  This principle is borne out by our cases,  see, e.g.,
  Toys, Inc. v. F.M. Burlington Co., 155 Vt. 44, 582 A.2d 123 (1990).  There,
  we  noted that the question of whether a contract existed depends on facts
  as well as the reasonable  inferences to be drawn from them, and is also
  influenced by the situation of the parties and the  subject matter.  See
  id. at 50, 582 A.2d  at 126-27.  Other jurisdictions have stated the general 
  rule more clearly, see, e.g., Simmons v. Simmons, 708 A.2d 949, 963 (Conn.
  1998) (existence  of contract is, at least initially, question of fact);
  Fleet Bank--N.H. v. Christy's Table, Inc., 681 A.2d 646, 648 (N.H. 1996)
  (whether meeting of minds occurred is factual question to be  determined by
  trier of fact); June Roberts Agency, Inc. v. Venture Properties, Inc., 676 A.2d 46, 48 (Me. 1996) (existence of contract is question of fact to be
  determined by jury).  

       We turn first to whether the trial court erred in concluding that
  there was an agreement 

 

  between the Town and Russell to turn over the completed water line to the
  Town, without  payment by the Town.  Defendants do not attack the trial
  court's findings, yet contend there was  insufficient evidence of a meeting
  of the minds and therefore argue there was no contract.  

       After a review of the trial court's findings of fact and the evidence
  below, we conclude  there is sufficient evidence to support the trial
  court's finding of an agreement between the  parties.  The trial court
  found that the Rutland Town Board of Selectmen held a meeting in late  1985
  or early 1986, for which notice had been given, to hear Russell's request
  for permission to  install a water line in Gleason Road.  Russell was
  represented by William Kollhepp, its Director  of Development, who had
  handled the Act 250 permitting and planning commission proceedings  for
  Heritage Hill.  After Kollhepp requested permission to install the line,
  Board member  Rodney Gallipo asked that the line be deeded to the Town on
  completion.  Kollhepp agreed to  deed the line to the Town, and the Board
  then voted to grant permission for the installation.    

       Later correspondence between the parties involved in the construction
  confirms that there  was an agreement to transfer the line to the Town upon
  completion.  Correspondence between  the City and the Town demonstrates the
  Town's intentions.  On March 18, 1987, the Board  wrote to the mayor of the
  City: "The Town would like to take [the Gleason Road water line]  over as a
  Town line so that qualifying members of the public within the Town may use
  it.  It is  awaiting approval under paragraph (7) of the [1972 water
  supply] Agreement before doing so."   The Board's letter indicates that the
  only step remaining before the Town took the line over was  the resolution
  of a disagreement between the Town and City about the amount of water the
  line  could carry. The letter suggests the contract between Russell and the
  Town was fully 

 

  performed: the Town granted permission to install, Russell installed and no
  further performance  was required. Compensation for the line was no part of
  the bargain. 

       The court below placed particular emphasis on a letter written by Carl
  Anderson, an  attorney who was a Vice-President of Russell for the period
  at issue and functioned as Russell's  in-house counsel.  Anderson wrote to
  the Board on September 25, 1988, to congratulate the  Town on its settling
  the dispute with the City over the water line's capacity.  Then he turned
  to  the Town's pending request for a quitclaim of title to the Gleason Road
  water line.  

          As you may recall, in the past we have been reluctant to Quit 
     Claim the water line to Rutland Town because your attorney, Mark 
     Sperry, had opined that if the Town owned the water line it might 
     not be able to limit service through the water line to just Heritage 
     Hill.  In addition since the City had approved only enough water for 
     the Heritage Hill development, distribution of that allocation 
     through that water line to other users would have jeopardized the 
     completion of Heritage Hill.
          In anticipation of our ability now to transfer the water line to 
     you I request that you provide me with the following items:
          1.  A copy of the fully executed agreement between the Town and 
     the City so that I can confirm for myself that there is sufficient 
     water available under the agreement to accommodate the completion of 
     the Heritage Hill development.
          2.  A draft or sample of any proposed Quit Claim which you might 
     require in order to convey the pipeline from East Mountain Land Company 
     to the Town of Rutland.
          3.  Any other items that you might deem to be necessary or required 
     in connection with the transfer of the line.


  In this listing of the paperwork necessary to tie up the transfer,
  Russell's in-house lawyer,  Anderson, makes no mention of compensation nor
  suggests in any way that compensation was  part of the agreement.  Like the
  letter from the Town to the City, this letter evidences the  parties'
  understanding that the agreement was performed by both sides and only the
  technicality  of transferring the line remained.

       Although this evidence is pieced together from a number of different
  and indirect 

 

  sources, no other explanation presents itself.  The documents demonstrate
  that both parties  expected the Town to take over the line; Russell would
  not have installed the line without  permission from the Town, and the Town
  had a practical need to control its streets as well as to  provide water to
  other residents, motivating its request that the line be deeded to it.  The
  only  reasonable inference is the one made by the trial court: there was a
  simple quid pro quo  agreement whereby the Town permitted installation and
  Russell agreed to deed the line to the  Town. While one might wish the
  trial court's findings had been more direct, there was no other  conclusion
  to reach from the facts before the court. (FN1)

       Defendants offered no contradictory evidence.  In fact, defendants
  Russell Corp. and the  City elected not to question John Russell when he
  was called as plaintiff's witness below, and  therefore failed to provide
  an alternative explanation of how permission to install the line was 
  obtained and on what terms.   Defendants called only two witnesses, neither
  of whom rebutted  the account given by plaintiff's witness of the meeting
  at which the agreement was reached.   Defendants' witnesses testified
  primarily about the absence of the minutes of the Board meeting,  an issue
  irrelevant to the central question of whether an agreement was reached at
  that meeting.  Because defendants provided no other account of how the line
  came to placed in the Town's  right-of-way along Gleason Road, the only
  reasonable inference that could be drawn from the  evidence was that
  plaintiff's account was correct. 

 

       Defendants cite only two cases in support of their proposition that
  there was no meeting  of the minds between the Town and Russell.  These
  cases are inapposite.  Bell v. Town of  Grafton, 133 Vt. 1, 3-4, 328 A.2d 408, 409 (1974) held there was no meeting of the minds  where, in
  negotiating a contract to sell land, the proposed deed was rejected by one
  party and no  later agreement was reached.  That is not the case we have
  here; the one fact beyond dispute is  that all parties expected the Town to
  take over the line on completion.  Defendants suggest we  should import an
  additional term, payment to Russell, into that contract, but the evidence
  before  the trial court does not support such a reading.  Reynolds v.
  Sullivan, 136 Vt. 1, 3-4, 383 A.2d 609, 611 (1978) concerned a preliminary
  option agreement that did not provide terms for  payment, interest or
  security and we therefore deemed it too vague to be enforced.  The credible 
  evidence presented by the Town does not show a vague, preliminary
  agreement.  Defendants  have offered no evidence of obtaining permission at
  any time other than the late 1985/early 1986  Board meeting; therefore it
  is only reasonable to assume they did obtain permission at that time  and
  the Board did insist that the line be deeded to the Town on completion.  No
  other  explanation for the course of events set out below makes sense.

       Next, we respond to defendants' assertion that Kollhepp, Russell's
  agent, lacked the  authority to contract on behalf of Russell and that
  therefore East Mountain took without notice of  the condition created by
  the contract with the Town.  Defendants would apparently have us  believe
  Kollhepp lacked authority to do any of the things he quite evidently did,
  such as  represent Russell at Act 250 hearings and Town Planning Commission
  proceedings.  If it were  true that Kollhepp lacked the authority to
  contract on behalf of Russell, it is hard to imagine how  this project ever
  got built.  Kollhepp was found by the lower court to have been in charge of 

 

  marketing and development for Russell.  He was also found to have appeared
  at all Act 250 and  other meetings to obtain permits for Heritage Hill.  He
  plainly succeeded at these endeavors.   Defendants, however, would have us
  believe he was somehow limited in his appearance as  Russell's agent before
  the Town Board of Selectmen.  It is impossible to find a basis for such a 
  limitation.  Kollhepp was a Vice-President of Russell during the year in
  question; he had the title  Director of Development.  He was known to other
  parties in the construction as the person in  charge of permitting and
  construction.  Defendants do not contend that the line was installed 
  without permission; therefore someone was getting permission and
  contracting with Russell's  approval.   Again, defendants offered no
  evidence to contradict the inference of authority created  by plaintiff's
  evidence; they even declined to question John Russell, who presumably would
  have  been in the best position to know the scope of Kollhepp's authority.  
	
       There can be no other conclusion but that Kollhepp had at least
  apparent authority to  contract with the Town to exchange the water line
  for permission to install it in the place most  advantageous for Russell -
  the Town's Gleason Road right-of-way.  See, e.g., New England  Educational
  Training Service, Inc. v. Silver Street Partnership, 148 Vt. 99, 105, 528 A.2d 1117,  1120 (1987) (under doctrine of apparent authority, agent binds
  principal when third-party  reasonably relies on representations that agent
  acting within scope of authority).  

       We now turn to the argument that the Statute of Frauds bars
  enforcement of the  agreement between the Town and Russell because there is
  no written agreement.  The court  below found that an oral agreement was
  made when the Town granted permission to install the  line and Russell
  promised to deed the line to the Town without payment.   The Statute of
  Frauds  requires several types of agreements to be written in order to be
  enforced.  Defendants point to 

 

  12 V.S.A. § 181(5), which provides that a contract for the sale of lands,
  tenements or  hereditaments must be in writing.   

       Assuming, arguendo, that the installation agreement could be construed
  as a sale of  lands, this case would fall within the rule established by
  Nutting v. Freda, 153 Vt. 501, 502, 572 A.2d 896, 897 (1990).  There, the
  trial court's findings supported the conclusion that the  plaintiff had
  altered his position in reasonable reliance on the defendant's oral promise
  and  therefore injustice could be avoided only by specific enforcement. 
  This Court held that the  defendant's oral promise to convey real property
  fell under an exception to the Statute of Frauds.  See id. (citing
  Restatement (Second) of Contracts § 129 (1981)). In the instant case, the
  Town  undertook a substantial forbearance, permitting Russell to install a
  ten-inch water main in  Gleason Road, and did so in reasonable reliance on
  the agreement made at the meeting with  William Kollhepp that the line
  would become part of the Town's water system upon completion.  See
  Restatement (Second) of Contracts § 139(2) (FN2) (factors supporting
  enforcement of  promise).  This performance by the Town of its part of the
  bargain has altered the positions of  the parties and enforcement of the
  agreement is needed to prevent injustice.

       Defendants further claim that because they failed to obtain a dig
  permit, which under  statutory authority should have included conditions
  such as the transfer of the line, there was no  agreement that the line be
  transferred.  This argument is meritless.  The trial court concluded: 

 

  "If Russell failed to apply for a required permit, this in no way limits
  the Town's rights or  impairs its ownership.  We find the lack of the
  permit is not relevant to this controversy." 

       We agree with the trial court.  Under 19 V.S.A. § 1524 (now superseded
  by 19 V.S.A.  § 1111), persons proposing to install pipes and wires in
  highways must obtain a permit and the  issuing entity must include any
  conditions imposed.  The burden is on the developer to apply for  and
  obtain permits.  See id. at § 1524(a) ("Permits must be obtained by anyone
  or any  corporation wishing to use as defined in this section any part of
  the highway right-of-way either  in the state or town system.").  The trial
  court correctly concluded that the absence of the dig  permit was due to
  Russell's oversight and has no bearing on whether Russell and the Town 
  agreed the line was to be transferred without compensation.  

       Lastly, we look at the defendants' contention that Vermont's Open
  Meeting Law bars  enforcement of this contract.  Defendants argue that
  because plaintiff has not produced the  minutes of the Board meeting at
  which the contract was formed, that meeting did not comply  with Vermont's
  Open Meeting Law.  See 1 V.S.A. § 312(b) (requiring minutes to be taken of
  all  meetings of public bodies).  Therefore, defendants assert that the
  meeting was illegal and that an  action taken by the Board at the meeting
  is void. 

       Defendants' argument has no merit.  First, the trial court found that
  the meeting was duly  warned and therefore open to the public.  The
  uncontroverted testimony detailed that minutes  were taken by one of two
  people and filed according to custom.  Thus, the trial court did not find 
  that minutes had not been taken at the meeting, but only that no copies of
  the minutes can  presently be found.  We decline to adopt a rule that
  invalidates decisions of public bodies  because the minutes of a meeting
  have been lost.  See Valley Realty & Dev., Inc. v. Town of  

 

  Hartford, 165 Vt. 463, 467, 685 A.2d 292, 295 (1996) ("Invalidation of
  public action is often an  'extreme remedy' that may be inappropriate for
  the underlying violation.").  The intent of the  Open Meeting Law was "to
  give public exposure to governmental decision-making. The purpose  is not
  to create 'vehicles for individuals displeased with governmental action to
  obtain reversals  of substantive decisions.'" Id. at 467-68, 685 A.2d  at
  295 (internal citations omitted).  

       Affirmed. 

	                               FOR THE COURT:



	                               _______________________________________
	                               Associate Justice



------------------------------------------------------------------------------
                                  Footnotes


FN1.  The trial court also provided an alternative ground for its decision,
  concluding that the  water line became the property of the Town by
  operation of law.  Defendants have challenged  this conclusion but because
  we affirm the trial court's holding that an agreement was reached  for
  transferring the line without further compensation, we need not reach the
  alternative  ground.  We note only that such a holding would not be
  inconsistent with the language of 19  V.S.A. § 1102, prohibiting anyone
  from obtaining a right or interest in a public highway. 
       
FN2.  Section 129 of the Restatement (Second) of Contracts concerns the
  enforcement of oral  promises with respect to the transfer of an interest
  in land.  Section 139 of the Restatement  (Second) of Contracts reiterates
  the same rules as general principles for the enforcement of  contracts
  governed by the Statute of Frauds.  See Restatement (Second) of Contracts §
  139  (1981). The factors supporting enforcement are listed under § 139, but
  the rule is the same as  that in § 129. 
 


Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.