Proc Gas Consum v. FERC, No. 98-1075 (D.C. Cir. 1999)

Annotate this Case

This opinion or order relates to an opinion or order originally issued on May 21, 1999.

United States Court of Appeals for the district of columbia circuit No. 98-1075 September Term, 1998

Process Gas Consumers Group, et al., Petitioners v.

Federal Energy Regulatory Commission, Respondent Tennessee Gas Pipeline Company, et al., Intervenors

Consolidated with No. 98-1089



Before: Edwards, Chief Judge, Wald and Rogers, Circuit Judges.

O R D E R

It is ORDERED by this Court that the opinion filed on May 21, 1999, is amended as follows:

Page 18, the last full sentence should read:

It is often impossible to offer a higher rate or to request more capacity because the only pipeline capacity that could be of any use to the existing customer is already spoken for.

FOR THE COURT: Mark J. Langer, Clerk

Filed on August 4, 1999