2005 Washington Revised Code RCW 60.28.020: Excess over lien claims to contractor.

    After the expiration of the thirty day period, and after receipt of the department of revenue's certificate, and the public body is satisfied that the taxes certified as due or to become due by the department of revenue are discharged, and the claims of materialmen and laborers who have filed their claims, together with a sum sufficient to defray the cost of foreclosing the liens of such claims, and to pay attorneys' fees, have been paid, the public body shall pay to the contractor the fund retained by it or release to the contractor the securities and bonds held in escrow.

         If such taxes have not been discharged or the claims, expenses, and fees have not been paid, the public body shall either retain in its fund, or in an interest bearing account, or retain in escrow, at the option of the contractor, an amount equal to such unpaid taxes and unpaid claims together with a sum sufficient to defray the costs and attorney fees incurred in foreclosing the lien of such claims, and shall pay, or release from escrow, the remainder to the contractor.

    [1975 1st ex.s. c 104 § 2; 1970 ex.s. c 38 § 2; 1967 ex.s. c 26 § 23; 1955 c 236 § 2; 1921 c 166 § 2; RRS § 10321.]

Notes:
         Application -- 1992 c 223: See RCW 39.04.901.

         Effective date -- 1967 ex.s. c 26: See note following RCW 82.01.050.

Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.