2005 Washington Revised Code RCW 39.10.067: School district capital demonstration projects — Conditions. (Effective until July 1, 2007.)

    In addition to the projects authorized in RCW 39.10.061, public bodies may also use the general contractor/construction manager contracting procedure for the construction of school district capital demonstration projects, subject to the following conditions:

         (1) The project must receive approval from the school district project review board established under RCW 39.10.115.

         (2) The school district project review board may not authorize more than twenty-three demonstration projects valued over ten million dollars.

         (3) The school district project review board may not authorize more than two demonstration projects valued between five and ten million dollars and the authorization for the two demonstration projects shall expire upon the completion of the two projects.

    [2006 c 261 § 1; 2003 c 301 § 3; 2002 c 46 § 3; 2000 c 209 § 3.]

Notes:
         Effective date -- 2002 c 46: See note following RCW 39.10.051.

Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.