2005 Washington Revised Code RCW 39.04.050: Contents of original estimates.
Original estimates shall show in detail the estimated cost of the work; the estimated quantities of each class of work; the estimated unit cost for each class; the estimated total cost for each class; the time limit, allowed for the completion of the work and the estimated dates of commencement and completion.
[1986 c 282 § 3; 1923 c 183 § 4; RRS § 10322-4.]
| Severability -- 1986 c 282: See RCW
82.18.900.
|
Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.