2019 Massachusetts General Laws
Part I - Administration of the Government
Title XXII - Corporations
Chapter 164a - New England Power Pool
Section 24 - Transmission Lines of Electric Utilities; Petition for Authority to Construct, Use or Take Rights of Way by Eminent Domain Authorized

Universal Citation: MA Gen L ch 164a § 24 (2019)

Section 24. Lines for transmission of electricity which are electric power facilities, as defined in section one, shall, irrespective of the destination of the electricity to be transmitted thereover, be lines for the transmission of electricity for which an electric utility may petition under section seventy-two of chapter one hundred sixty-four for authority to construct and use, or continue to use, or to take by eminent domain under chapter seventy-nine lands, or rights-of-way or widenings thereof.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.