2017 Massachusetts General Laws
PART I ADMINISTRATION OF THE GOVERNMENT
TITLE XX PUBLIC SAFETY AND GOOD ORDER
Chapter 146 INSPECTION OF BOILERS, AIR TANKS, ETC. LICENSES OF ENGINEERS, FIREMEN, AND OPERATORS OF HOISTING MACHINERY
Section 50C Nuclear power plant operators and engineers; minimum supervising and shift requirements

Universal Citation: MA Gen L ch 146 § 50C (2017)

Section 50C. Every nuclear power plant shall have at least one nuclear power plant senior supervising engineer. One nuclear power plant operating engineer and one assistant nuclear power plant operator shall be the minimum requirement for each working shift.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.