2016 Kentucky Revised Statutes CHAPTER 376 - STATUTORY LIENS .010 Mechanics' and materialman's liens -- Filing of statement of amount claimed -- Notice to owner or agent -- Definitions of "labor" and "supplies."
Download as PDF
376.010 Mechanics' and materialman's liens -- Filing of statement of amount
claimed -- Notice to owner or agent -- Definitions of "labor" and "supplies."
(1)
(2)
(3)
(4)
Any person who performs labor or furnishes materials, for the erection, altering, or
repairing of a house or other structure or for any fixture or machinery therein, for
the excavation of cellars, cisterns, vaults, wells, or for the improvement in any
manner of real property including the furnishing of agricultural lime, fertilizer,
concrete pipe or drainage tile, crushed rock, gravel for roads or driveways, and
materials used in the construction or maintenance of fences, by contract with, or by
the written consent of, the owner, contractor, subcontractor, architect, or authorized
agent, shall have a lien thereon, and upon the land upon which the improvements
were made or on any interest the owner has therein, to secure the amount thereof
with interest as provided in KRS 360.040 and costs. The lien on the land or
improvements shall be superior to any mortgage or encumbrance created subsequent
to the beginning of the labor or the furnishing of the materials, and the lien, if
asserted as hereinafter provided, shall relate back and take effect from the time of
the commencement of the labor or the furnishing of the materials. The lien shall not
be for a greater amount in the aggregate than the contract price of the original
contractor, and should the aggregate amount of the liens exceed the price agreed
upon between the original contractor and the owner there shall be a pro rata
distribution of the original contract price among the lienholders.
The lien shall not take precedence over a mortgage or other contract lien or bona
fide conveyance for value without notice, duly recorded or lodged for record
according to law, unless the person claiming the prior lien shall, before the
recording of the mortgage or other contract lien or conveyance, file in the office of
the county clerk of the county wherein he has furnished or expects to furnish labor
or materials, a statement showing that he has furnished or expects to furnish labor
or materials, and the amount in full thereof. The lien shall not, as against the holder
of a mortgage or other contract lien or conveyance, exceed the amount of the lien
claimed or expected to be claimed as set forth in the statement. The statement shall,
in other respects, be in the form prescribed by KRS 376.080.
No person who has not contracted directly with the owner or his agent shall acquire
a lien under this section unless he notifies in writing the owner of the property to be
held liable or his authorized agent, within seventy-five (75) days on claims
amounting to less than $1,000 and one hundred twenty (120) days on claims in
excess of $1,000 after the last item of material or labor is furnished, of his intention
to hold the property liable and the amount for which he will claim a lien. It shall be
sufficient to prove that the notice was mailed to the last known address of the owner
of the property upon which the lien is claimed, or to his duly authorized agent
within the county in which the property to be held liable is located.
No person who has not contracted directly with the owner or his authorized agent
shall acquire a lien under this section on an owner-occupied single or double family
dwelling, the appurtenances or additions thereto, or upon other improvements for
agricultural or personal use to the real property or real property contiguous thereto
and held by the same owner, upon which the owner-occupant's dwelling is located,
(5)
(6)
unless he notifies in writing the owner of the property to be held liable or his
authorized agent not more than seventy-five (75) days after the last item of material
or labor is furnished, of the delivery of the material or performance of labor and of
his intention to hold the property liable and the amount for which he will claim a
lien. It shall be sufficient to prove that the notice was mailed to the last known
address of the owner of the property upon which the lien is claimed, or to his duly
authorized agent. This notice is in lieu of the notice provided for in subsection (3).
Notwithstanding the foregoing provisions of this subsection, the lien provided for
under this section shall not be applicable to the extent that an owner-occupant of a
single or double family dwelling or owner of other property as described in this
subsection has, prior to receipt of the notice provided for in this subsection, paid the
contractor, subcontractor, architect, or authorized agent for work performed or
materials furnished prior to such payment. The contractor or subcontractor cannot
be the authorized agent under this subsection. This subsection shall apply to the
construction of single or double family homes constructed pursuant to a
construction contract with a property owner and intended for use as the property
owner's dwelling.
For purposes of this section, "labor" includes but is not limited to all supplies and
work done by teams, trucks, machinery, and mechanical equipment, whether the
owner furnishes a driver or operator or not.
(a) "Supplies" includes small tools and equipment reasonably necessary in
performing the work required to be done, including picks, shovels, sledge
hammers, axes, pulleys, wire cables, ropes, and other similar items costing not
more than fifty dollars ($50) per item, and tires and tubes furnished for use on
vehicles engaged in the performance of the work.
(b) "Supplies" also includes the cost of labor, materials, and repair parts supplied
or furnished for keeping all machinery and equipment used in the performance
of the work in good operating condition; and shall include the agreed or
reasonable rental price of equipment and machinery used in performing the
work to be done:
1.
The lien for rental equipment or machinery shall not be more than the
aggregate sum of six (6) months' rental, and the aggregate amount of
such rental shall not exceed sixty percent (60%) of the agreed value of
the machinery or equipment; and
2.
The liens for supplies as defined in this subsection are subordinate to the
liens for labor, material, and supplies as defined in this section.
Effective: July 15, 2002
History: Amended 2002 Ky. Acts ch. 66, sec. 1, effective July 15, 2002. -- Amended
1994 Ky. Acts ch. 167, sec. 1, effective July 15, 1994. -- Amended 1988 Ky. Acts ch.
259, sec. 1, effective July 15, 1988. -- Amended 1984 Ky. Acts ch. 385, sec. 1,
effective July 13, 1984. -- Amended 1978 Ky. Acts ch. 384, sec. 501, effective June
17, 1978. -- Amended 1974 Ky. Acts ch. 173, sec. 1. -- Amended 1972 Ky. Acts ch.
191, sec. 1. -- Amended 1952 Ky. Acts ch. 9, sec. 1, effective June 19, 1952. -Recodified 1942 Ky. Acts ch. 208, sec. 1, effective October 1, 1942, from Ky. Stat.
sec. 2463.
Disclaimer: These codes may not be the most recent version. Kentucky may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.