§ 23-4-502 - Filing interim rate schedule.


AR Code § 23-4-502 (2012) What's This?

Any public utility as defined in ยง 23-1-101 may recover all costs and expenses reasonably incurred by such a utility as a direct result of legislative or regulatory requirements relating to the protection of the public health, safety, and the environment by filing with the Arkansas Public Service Commission, no more frequently than once every six (6) months, an interim rate schedule which would impose a separate surcharge in addition to its currently effective rates until the implementation of new rate schedules in connection with the next general rate filing of the utility wherein such additional expenditures can be included in the utility's base rate schedules.

Disclaimer: These codes may not be the most recent version. Arkansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.