Sundown Energy LP v. HJSA No. 3 (Per Curiam)
Annotate this Case
In this contract dispute involving the correct interpretation of a mineral lease's "continuous drilling program" provision the Supreme Court held that the court of appeals erred in reversing partial summary judgment for the lessee on the contract-construction issue.
Lessor and Lessee were the successors-in-interest to an oil-and-gas top lease covering a 30,450-acre parcel of land. At the end of the primary term, Lessee was required to reassign to Lessor all of Lessee's operating rights in each tract of the lease not then held by production unless Lessee was engaged in a "continuous drilling program." Notwithstanding Lessee's continued drilling operations, Lessor filed a suit seeking a declaration that the lease had terminated. The trial court granted partial summary judgment for Lessor, concluding that the lease had not terminated as to non-producing tracts. The court of appeals reversed. The Supreme Court reversed, holding (1) under the lease's special definition of drilling operations, activities other than spudding-in a well are sufficient to maintain the lease as to non-producing tracts; and (2) the record conclusively established that Lessee was engaged in a continuous drilling program within the meaning of the lease.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.