Plains Builders, Inc., et al v. Steel Source, Inc., et alAppeal from 251st District Court of Potter County (opinion )
Annotate this Case
Download PDF
In The
Court of Appeals
Seventh District of Texas at Amarillo
No. 07-11-00198-CV
PLAINS BUILDERS, INC., ET AL, APPELLANTS
V.
STEEL SOURCE, INC., ET AL, APPELLEES
On Appeal from the 251st District Court
Potter County, Texas
Trial Court No. 95,423-C, Honorable Ana Estevez, Presiding
July 30, 2013
OPINION
Before QUINN, C.J., and CAMPBELL and HANCOCK, JJ.
This case arises from the construction of the Texas State Veterans’ Home in
Amarillo. Appellants are Plains Builders, Inc., and its surety Travelers Surety Company
of America while appellees and cross-appellants are Steel Source, Inc., and Steel
Source, a Division of Lloyd N. Moreau, L.L.C. (Steel Source).
Plains Builders
challenges an adverse money judgment in favor of Steel Source, Plains Builders and
Travelers challenge a finding of liability on a payment bond, and Steel Source contends
the trial court failed to award the full amount of its actual damages. We will reverse in
part and render judgment that Steel Source take nothing from Plains Builders and
Travelers on the payment bond claim and otherwise affirm the judgment of the trial
court.
Background
Plains Builders, as general contractor for the construction of the veterans’ home,
subcontracted with Construction Services, a proprietorship, to furnish material and labor
for the project. The recited value of the subcontract was $1,868,590. Construction
Services in turn subcontracted to Steel Source a portion of the labor and materials it
was to supply. The value of the Construction Services--Steel Source subcontract was
$880,000. Of this amount, the parties allocated $550,000 for materials and $330,000
for labor. After the contracts were signed, Plains Builders, Construction Services and
Steel Source signed a joint check agreement providing:
Applicable to the products and services furnished by Construction
Services to [Plains Builders] . . . and as a condition precedent to furnishing
said materials for use and incorporation in the [veterans’ home project],
Construction Services requests that until it is paid in full, all payments
made or to be made by [Plains Builders] to Construction Services with
respect to this project, be made payable jointly to Construction Services
and [Steel Source]. It is understood that all payments shall be timely and
in the form of an immediate and unconditional instrument, specifically a
Cashier’s Check. Upon issuance of a check by [Plains Builders], it shall
be promptly (within 3 business days) endorsed by Construction Services
and delivered to [Steel Source]. It is understood that this is a continuing
Agreement applicable to the original contract sum and any subsequent
billing related to this project only.
Plains Builders issued five cashier’s checks made jointly payable to Construction
Services and Steel Source. Construction Services refused to endorse each joint check
unless at the time of its endorsement Steel Source simultaneously delivered a cashier’s
check to Construction Services for a portion of the amount of the joint check.
2
As the veterans’ home project progressed, Construction Services began
experiencing significant cash flow problems.
Joint checks were issued by Plains
Builders in April and May 2006 for $125,557.83 and $125,337.49 respectively. At the
time, Steel Source had submitted a draw of $237,000 to Construction Services. Steel
Source retained $50,000 from the April check and a like amount from the May check but
released the balance to Construction Services. According to Steel Source, it did so
because Construction Services insisted, and because of the risk that work on the entire
project would halt if Construction Services could not continue.
Through an undated letter bearing a June 1, 2006 fax date stamp, Construction
Services then notified Plains Builders that it was “Discontinuing [the] joint checking
agreement with [Steel Source].”
According to the letter, the reason for the
discontinuance was, “Failure to complete punch out and reframing.
Construction
Service (sic) had to reframe a lot of walls, studs and misc. work.” At the time, Steel
Source did not know Construction Services had sent the letter.
Following this notice letter, Plains Builders issued four checks totaling $80,000 to
Construction Services as the sole payee and four checks totaling $134,151.78 to
Construction Services and West Texas Builders, a supplier of materials, as joint payees.
Plains Builders finally discharged Construction Services from the veterans’ home
project and expended some $750,000 completing the work left unfinished and making
up a payroll shortage of Construction Services. Steel Source asserted Construction
Services failed to pay it amounts due totaling $137,300. According to Steel Source, had
3
Plains Builders issued all checks due Construction Services according to the terms of
the joint check agreement, it would have received full payment.
Steel Source brought suit against Plains Builders, Travelers, and Construction
Services.1 A default judgment was taken against Construction Services. Steel Source
moved for summary judgment on a claim that Plains Builders breached the joint check
agreement to its damage. The trial court rendered a partial summary judgment in favor
of Steel Source on liability but reserved the issue of damages for trial. After a bench
trial, the court rendered judgment in favor of Steel Source and jointly and severally
against Plains Builders and Travelers on a claim for retainage in the principal amount of
$33,000 and against Plains Builders in the principal sum of $80,000 on the breach of
the joint check agreement claim. Findings of fact and conclusions of law were filed.
Plains Builders appeals and by cross-appeal Steel Source challenges the amount of
damages it was awarded.
Analysis
Appeal of Plains Builders
Challenges to the Partial Summary Judgment
By its first issue, including multiple sub-issues, Plains Builders challenges the
trial court’s grant of partial summary judgment in favor of Steel Source.
We review the trial court’s summary judgment de novo. Valence Operating Co.
v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005). A movant, on a traditional motion for
1
The record indicates in a separate suit Plains Builders obtained a default
judgment in the amount of $752,392.35 against Construction Services.
4
summary judgment on affirmative claims, bears the initial burden of showing its
entitlement to judgment as a matter of law by conclusively proving each element of its
cause of action. M.D. Anderson Hosp. & Tumor Inst. v. Willrich, 28 S.W.3d 22, 23 (Tex.
2000) (per curiam). Only if the movant satisfies this burden does the burden shift to the
non-movant to raise a genuine issue of material fact precluding summary judgment. Id.
A party seeking to recover for breach of a contract must prove: (1) the existence
of a valid contract; (2) its performance or tender of performance; (3) the defendant’s
breach of the contract; and (4) damages sustained by the plaintiff as a result of the
breach. Valero Mktg. & Supply Co. v. Kalama, Int'l, 51 S.W.3d 345, 351 (Tex.App.-Houston [1st Dist.] 2001, no pet.).
Plains Builders first asserts that the joint check agreement is not an enforceable
contract because it lacks consideration.
Joint check arrangements may be initiated by parties at the top or bottom
of the contract claim. For example, the general contractor may wish to
insure that the party receiving the check (e.g., the subcontractor) will
properly disburse the proceeds of the check to his supplier or
subcontractors. In this manner the general contractor reduces the
chances that his subcontractor will pocket the money and leave the
supplier unpaid, thus provoking the supplier to file mechanic’s liens or
make claims against the general contractor's payment bond.
Similarly, the supplier or sub-subcontractor may initiate the joint check
arrangement to make sure that the subcontractor won’t run off with the
progress payments and leave him out in the cold. The supplier may
desire this arrangement because the subcontractor is in financial trouble
or lacks assets, or because he has never done business with the
subcontractor before. Sometimes, the supplier will request a joint check
arrangement out of simple mistrust of him.
City of Philadelphia for the use of Allied Roofers Supply Corp. v. Joseph S. Smith
Roofing, Inc., 599 A.2d 222, 226 (Pa. Super. Ct. 1991) (quoting Barrett, Joint Check
5
Arrangements: A Release for the General Contractor and Its Surety, 8 Constr. Law. 7, 7
(1988)).
A contract must be based on a valid consideration; that is, mutuality of obligation.
Federal Sign v. Texas S. Univ., 951 S.W.2d 401, 408 (Tex. 1997). A contract lacking
consideration is unenforceable. Id. at 409.
Consideration is a present exchange bargained for in return for a promise.
It consists of either a benefit to the promisor or a detriment to the
promisee. The detriment must induce the making of the promise, and the
promise must induce the incurring of the detriment.
Roark v. Stallworth Oil and Gas, Inc., 813 S.W.2d 492, 496 (Tex. 1991) (citations
omitted); Minton v. Riverside State Bank, 399 S.W.2d 196, 198 (Tex.Civ.App.--Fort
Worth 1966, no writ). What constitutes consideration for a contract is a question of law.
Brownwood Ross Co. v. Maverick County, 936 S.W.2d 42, 45 (Tex.App.--San Antonio
1996, writ denied). The existence of a written contract presumes consideration for its
execution; therefore, a party alleging lack of consideration bears the burden to rebut the
presumption.
Doncaster v. Hernaiz, 161 S.W.3d 594, 603 (Tex.App.--San Antonio
2005, no pet.); Tex. R. Civ. P. 94.
We do not find in the summary judgment record evidence sufficient to raise an
issue of fact overcoming the presumption that sufficient consideration supported the
joint check agreement. Moreover, by obligating itself to make payments by cashier’s
checks made payable jointly to Construction Services and Steel Source, Plains Builders
incurred a detriment not otherwise required by its contract. In return, Plains Builders
obtained a measure of security against a claim on its bond by Steel Source. And by the
agreement, both Construction Services and Steel Source gained a measure of control
6
over payments made by Plains Builders of funds destined for the other. And, while
placed in the position of having to receive and handle all funds paid Construction
Services by Plains Builders, Steel Source gained a measure of assurance of payment
on its subcontract with Construction Services.
We find sufficient consideration
supported the joint check agreement.
Plains Builders next argues summary judgment was improper because by its own
terms the joint check agreement is not applicable to goods or services provided the
project by Steel Source, and Plains Builders raised an issue of fact as to whether Steel
Source sought as damages payment for goods or services it provided.
The
interpretation of the joint check agreement, however, is a question of law. No one
asserts on appeal it is ambiguous. Exxon Corp. v. Emerald Oil & Gas Co., 348 S.W.3d
194, 214 (Tex. 2011) (op. on reh’g) (noting when ambiguity is not raised by the parties,
interpretation of a contract is a question of law).
And we are shown no disputed
material facts whose disposition is essential to the legal determination.
This particular joint check agreement does not contain provisions providing for
allocation of the paid amounts between Construction Services and Steel Source; it
merely requires payment to them jointly and requires Construction Services’
endorsement.
With regard to any issue of fact assertedly raised with regard to
damages, we note the trial court denied Steel Source’s motion for summary judgment
as to the amount of damages.
Plains Builders next argues partial summary judgment was not proper because
Plains Builders satisfied its obligations under the joint check agreement. It asserts the
7
joint check agreement ceased by its own terms when Construction Services was fully
paid, and payment occurred “long before” Plains Builders stopped issuing joint checks.
The joint check agreement provides, “Construction Services requests that until it
is paid in full, all payments made or to be made by [Plains Builders] to Construction
Services with respect to this project, be made payable jointly to Construction Services
and [Steel Source].”
Plains Builders reasons that because it ultimately terminated
Construction Services from the project and obtained a default judgment against it in the
amount of $752,392.35, it may offset that amount against the sums Construction
Services was due under its subcontract, leaving Construction Services “fully paid” “long
before” the alleged breach of the joint check agreement by Plains Builders.
For two reasons, we cannot agree this assertion precluded summary judgment
that Plains Builders breached the joint check agreement. First, the summary judgment
record gives no indication that at the time Plains Builders issued checks to Construction
Services contrary to the terms of the joint check agreement, Construction Services was
fully paid. From the summary judgment record, it is undisputed that Plains Builders
complied with the notice Construction Services sent terminating the joint check
agreement.
Its response to Steel Source’s motion for summary judgment states it
complied with the notice not because Construction Services was fully paid, but “[a]s the
[joint check] agreement was for the benefit of Construction Services alone and because
it did not prohibit the cancellation of the agreement[.]” Secondly, and similarly, we
cannot see that the issue Plains Builders here asserts, that Construction Services was
“paid in full” under the joint check agreement because Plains Builders later incurred
costs to remedy its failure of performance under the construction contract, was
8
expressly presented in its response to the motion for summary judgment. See Tex. R.
Civ. P. 166a(c); McConnell v. Southside Indep. Sch. Dist., 858 S.W.2d 337, 341 (Tex.
1993) (requiring issues non-movant contends avoid movant’s entitlement to summary
judgment to be “expressly presented”).
Plains Builders next argues it raised an issue of fact supporting its affirmative
defense of payment. Plains Builders’ checks made jointly payable to Steel Source and
Construction Services totaled $1,223,275.71. Steel Source deposited these checks to
its bank account.
But it ultimately received only $806,410 because it remitted the
remaining amount totaling $417,165.71 to Construction Services via cashier’s checks.
The maximum claim of Steel Source under its subcontract with Construction Services
was $943,410. The fact it issued joint checks in amounts substantially more than Steel
Source’s maximum claim, Plains Builders argues, supports its affirmative defense of
payment.
What Plains Builders is asserting here is application of the “joint check rule,”
which has expressly been adopted by several states. As restated by the California
Supreme Court, the rule is that “[w]hen a subcontractor and his materialman are joint
payees, and no agreement exists with the owner or general contractor as to allocation
of proceeds, the materialman by endorsing the check will be deemed to have received
the money due him.” Post Bros. Constr. Co. v. Yoder, 20 Cal. 3d 1, 141 Cal. Rptr. 28,
569 P.2d 133, 135 (1977); see Brown Wholesale Elec. Co. v. Beztak of Scottsdale, 163
Ariz. 340, 788 P.2d 73, 76 (1990) (“when an owner or general contractor makes a
materialman and a subcontractor joint payees on a check that includes payment for
labor and materials furnished, and no other agreement exists between the materialman
9
and the owner or general contractor as to allocation of the proceeds, the materialman,
by endorsing the check, will be deemed to have been paid the money due him, up to the
amount of the joint check”); SFR, Inc. v. United States Fidelity & Guaranty Co., 2008 UT
App 31, ¶¶22, 177 P.3d 629; Anchor Concrete Co. v. Victor Sav. & Loan Ass’n, 1983
OK 60, 664 P.2d 396, 399 (applying rule). Among the cases cited by the Arizona, Utah
and Oklahoma courts in support of the rule is the opinion of Justice Barrow in F. & C.
Engineering Co. v. Moore, 300 S.W.2d 323 (Tex.Civ.App.--San Antonio 1957, writ ref’d
n.r.e.). Brown Wholesale Elec., 788 P.2d at 76; SFR, Inc., 177 P.3d at 635; Anchor
Concrete, 664 P.2d at 398.2
The cases we have reviewed in which the joint check rule has been applied are
cases enforcing materialmen’s liens or bonds securing payment or performance of the
construction contract.
See, e.g., F. & C. Engineering, 300 S.W.2d at 324; Brown
Wholesale Elec., 788 P.2d at 74; Post Bros. Constr. Co., 569 P.2d 134. Our case, a
suit based on breach of a joint check agreement, differs in that respect from all others
we have reviewed. As noted, the joint check agreement the parties here signed does
not address the subject of allocation of a check’s proceeds between Construction
Services and Steel Source. We agree with Steel Source that Plains Builders’ argument
in effect asks us to read into the joint check agreement a provision it does not contain.
In the absence of contract language warranting the inference Steel Source had an
obligation to retain funds necessary to keep its account current from each joint check as
2
As the Arizona court pointed out in Brown Wholesale Electric, 788 P.2d at 76,
federal courts have generally not followed the joint check rule in cases under the Miller
Act, 40 U.S.C. § 270b.
10
issued, Cf. F. & C. Engineering, 300 S.W.2d at 326, we will not apply the joint check
rule to support Plains Builders’ payment defense.
Plains Builders next asserts Steel Source waived the right to recover damages
for breach of the joint check agreement. Like its payment defense, Plains Builders’
waiver argument is based on Steel Source’s remission to Construction Services of parts
of the proceeds of the joint checks issued in April and May 2006.
Waiver is the intentional relinquishment of a known right or intentional conduct
inconsistent with claiming it. Massachusetts Bonding & Ins. Co. v. Orkin Exterminating
Co., Inc., 416 S.W.2d 396, 401 (Tex. 1967). Thus, establishing waiver of a contract
right requires proof of intent to relinquish the right. Johnson v. Structured Asset Servs.,
LLC, 148 S.W.3d 711, 723 (Tex.App.--Dallas 2004, no pet.) (citing Huffington v.
Upchurch, 532 S.W.2d 576, 580 (Tex. 1976)). We reiterate our observation that the
joint check agreement the parties signed required joint payment but did not contain
provisions addressing the division of a check’s proceeds between the joint payees. In
the absence of such provisions, and without application of the joint check rule, 3 we see
in Steel Source’s decision to permit Construction Services to retain part of the proceeds
of the April and May joint checks no evidence of an intent on the part of Steel Source to
relinquish its right to insist on Plains Builders’ further compliance with the agreement, or
its right to seek damages for its breach.
3
Some courts have characterized the effect of the joint check rule as a waiver by
the materialman of any claim against the payor to the amount of the joint check not
retained by the materialman. See SFR, Inc., 177 P.3d at 635.
11
Plains Builders next asserts it presented evidence raising an issue of fact on a
theory that Steel Source is estopped to assert its claim against Plains Builders. The
nub of the argument is “Steel Source should be estopped from asserting such claims
because it knowingly concealed facts from Plains Builders that Plains Builders was
entitled to know about. Had Plains Builders been made aware of this situation and the
new agreement which Steel Source and Construction Services had entered into
concerning payment from Construction Services to Steel Source, it could have ensured
that the monies were properly paid.”
Generally, equitable estoppel arises from conduct causing another party to
materially alter its position in reliance on that conduct. Tuscany Realty, Ltd. v. Tuscany
Gardens, L.P., No. 02-07-0421-CV, 2009 Tex. App. Lexis 9871, at *9 (Tex.App.--Fort
Worth Dec. 10, 2009, pet. denied) (per curiam, mem. op.). A party claiming an estoppel
must prove: (1) a false representation or concealment of material facts, (2) made with
knowledge, actual or constructive, of those facts, (3) with the intention that it should be
acted on, (4) to a party without knowledge or a means of obtaining knowledge of the
facts, (5) who detrimentally relies on the representation. Id. at *9-10. A party may be
estopped by its silence but only if it is “under a duty to speak, but refrains from doing so
and thereby leads another to act in reliance on a mistaken understanding of the facts.”
Casa El Sol-Acapulco, S.A. v. Fontenot, 919 S.W.2d 709, 718 (Tex.App.--Houston [14th
Dist.] 1996, writ dism’d by agr.).
Here, the summary judgment record contains no
evidence that Steel Source had a legal duty to disclose to Plains Builders how they
allocated the proceeds of the joint checks between them. Cf. Hoggett v. Brown, 971
S.W.2d 472, 487 (Tex.App.--Houston [14th Dist.] 1997, pet. denied) (citing Formosa
12
Plastics Corp. v. Presidio Engineers and Contractors, Inc., 941 S.W.2d 138, 146-47
(Tex.App.--Corpus Christi, 1995), rev’d on other grounds, 960 S.W.2d 41 (Tex. 1998)).4
Concluding the trial court did not err in rendering partial summary judgment
finding a valid joint check agreement and finding Plains Builders breached the
agreement, we overrule the Plains Builders’ first issue.
Issues Arising from Trial
Plains Builders and Travelers assert Steel Source is not entitled to recovery on
its payment bond claim because it did not provide timely notice of a claim for retainage,
as required by statute. We agree.
Among its theories of recovery, Steel Source alleged Plains Builders and
Travelers were jointly and severally liable for damages on Plains Builders’ payment
bond underwritten by Travelers. In the judgment, the trial court made two damage
awards. As noted, Steel Source was awarded $80,000 for breach of the joint check
agreement. Germaine to the present issue, Steel Source was also awarded $33,000,
jointly and severally against Plains Builders and Travelers, for retainage on the payment
bond claim.
“Chapter 2253 of the Texas Government Code, historically called the McGregor
Act, requires a prime contractor on a public-work contract to execute a payment bond to
4
As with its payment and waiver theories, Plains Builders’ estoppel argument
essentially is an effort to impose the joint check rule on the parties’ joint check
agreement. Some courts have used estoppel to characterize the operation of the joint
check rule, explaining that the material supplier, whose conduct has rendered the injury
possible, is estopped from imposing the loss on the general contractor. See Starkey
Constr., Inc. v. Elcon, Inc., 248 Ark. 958, 457 S.W.2d 509 (1970); City Lumber Co. v.
National Surety Corp., 229 S.C. 115, 92 S.E.2d 128, 131 (1956).
13
protect laborers and materialmen who work on or supply materials for the project.”
Dealers Elec. Supply Co. v. Scoggins Constr. Co., 292 S.W.3d 650, 652 (Tex. 2009);
Tex. Gov’t Code Ann. §§ 2253.001-.079 (West 2008 & Supp. 2012). The McGregor Act
defines “retainage” as the part of the payments under a public work contract that are not
required to be paid within the month following the month in which public work labor is
performed or public work material is delivered under the contract. Tex. Gov’t Code Ann.
§ 2253.001(7) (West 2008). To recover in a suit under § 2253.073 on a payment bond
for a claim for payment of retainage, a payment bond beneficiary whose contract with a
prime contractor or subcontractor provides for retainage must mail written notice of the
claim on a payment bond to the prime contractor and the surety on or before 90 days
after the final completion of the public works contract. Tex. Gov’t Code Ann. § 2253.046
(West 2008).
However, a payment bond beneficiary that does not have a direct contractual
relationship with the prime contractor for public work labor or material must give
“additional notice” in order to recover in a suit under § 2253.073 on a payment bond.
Tex. Gov’t Code Ann. § 2253.047(a) (West 2008). A payment bond beneficiary who
contracts with a subcontractor for retainage must mail, on or before the 15th day of the
second month after the date of the beginning of the delivery of public work material or
the performance of public work labor, written notice to the prime contractor that the
contract provides for retainage, and generally indicates the nature of the retainage.
Tex. Gov’t Code Ann. § 2253.047(b) (West 2008). The payment bond beneficiary must
mail, on or before the 15th day of the second month after each month in which the labor
was performed or the material was delivered, written notice to the prime contractor of a
14
claim for any unpaid public work labor performed or public work material delivered. A
copy of the statement sent to a subcontractor is sufficient notice. Tex. Gov’t Code Ann.
§ 2253.047(b) (West 2008).
The additional notice required for recovery by a payment bond beneficiary not
having a direct contractual relationship with the prime contractor avoids a possible
double payment obligation befalling a prime contractor and its surety when neither is
aware of a subcontractor’s retainage agreement with a claimant until after final
completion of the contract.
See Keetch Metal Works of Dallas, Inc. v. Yates, 378
S.W.2d 122, 124-25 & 125 n.1 (Tex.Civ.App.--Dallas 1964, no writ) (presenting
hypothetical fact pattern illustrating consequence when prime contractor and surety are
unaware of subcontractor’s retainage agreement with claimant).
Steel Source asserts it is not subject to the additional notice requirement of §
2253.047 because it had a direct contractual relationship with Plains Builders. It argues
the joint check agreement established the direct contractual relationship. We think the
argument ignores the plain language of the McGregor Act. See FKM P’ship Ltd. v. Bd.
of Regents of the Univ. of Houston Sys., 255 S.W.3d 619, 633 (Tex. 2008) (construing a
statute, court ascertains and gives effect to Legislature’s intent as expressed by its
language).
Steel Source’s retainage claim was for its labor. Section 2253.073 authorizes
suit by a “payment bond beneficiary who has provided public work labor or material
under a public work contract for which a payment bond is furnished under this chapter.”
“Public work labor” is defined as “labor used directly to carry out a public work.” Tex.
15
Gov’t Code Ann. § 2253.001(5) (West 2008). The additional notice requirement of §
2253.047 applies to a payment bond beneficiary “who does not have a direct
contractual relationship with the prime contractor for public work labor or material.” The
joint check agreement was not a contract between Steel Source and Plains Builders for
labor used directly to carry out construction of the veterans’ home. Steel Source had a
contract for that purpose, but its direct contractual relationship for supplying labor and
materials was with Construction Services, not the prime contractor. Cf. Dial Block Co.,
Inc. v. Mastro Masonry Contractors, 374 N.J. Super. 13, 863 A.2d 373, 378-79 (App.
Div. 2004) (discussing and citing federal cases finding joint check agreement does not
create direct contractual relationship required by federal Miller Act).
Because no direct contractual relationship existed between Plains Builders and
Steel Source for its public work labor, the notice requirements of § 2253.047 apply to
Steel Source’s McGregor Act claim for retainage.
Steel Source submitted a draw for labor performed on the project during
December 2005.
Thus its notice under § 2253.047(b) to Plains Builders was due
February 15, 2006. The earliest potential notice Steel Source points to in the record is a
fax it sent Plains Builders dated March 1, 2006. Even were we to accept Steel Source’s
argument the fax could satisfy § 2253.047, it was not timely notice. Tex. Gov’t Code
Ann. § 2253.047(b) (West 2008).
We sustain the third issue of Plains Builders. Steel Source will take nothing by
its claim against Plains Builders and Travelers for retainage on the payment bond.
Damages and Attorney’s Fees
16
In its fourth issue, Plains Builders argues the trial court awarded a double
recovery for breach of contract damages and retainage, the trial court’s findings
improperly incorporated its interlocutory summary judgment order, and no evidence
supported an award of attorney’s fees.
Because we will render judgment that Steel Source take nothing on its McGregor
Act claim, we dismiss as moot Plains Builders’ sub-issue claiming Steel Source
received an improper double recovery from the McGregor Act award of $33,000 and
$80,000 for breach of the joint check agreement. See Trulock v. City of Duncanville,
277 S.W.3d 920, 924 (Tex.App.--Dallas 2009, no pet.) (explaining mootness on appeal).
Plains Builders complains the trial court erred by making a conclusion of law
incorporating by reference its interlocutory summary judgment. As a general statement,
findings of fact and conclusions of law are not appropriate under summary judgment
procedure because “if summary judgment is proper, there are no facts to find, and the
legal conclusions have already been stated in the motion and response. The trial court
should not make, and an appellate court cannot consider, findings of fact in connection
with a summary judgment.” IKB Industries (Nigeria) Ltd. v. Pro-Line Corp., 938 S.W.2d
440, 441 (Tex. 1997).
But the thrust of the complaint seems to be the trial court
determined the breach of the joint check agreement by summary judgment but revisited
the issue at trial. Even were we to assume the trial court erred by incorporating its
summary judgment order into its post-trial conclusions of law, this record does not show
the error was harmful. Tex. R. App. P. 44.1(a). We overrule this sub-issue.
17
Plains Builders next argues the trial court erred in awarding Steel Source
attorney’s fees because Steel Source failed to segregate recoverable attorney’s fees
from nonrecoverable fees and did not offer evidence meeting the Andersen factors.
See Arthur Andersen & Co. v. Perry Equip. Corp., 945 S.W.2d 812, 818 (Tex. 1997).
Each of the two theories on which the trial court awarded Steel Source damages
also authorized recovery of attorney’s fees.5 The attorney for Steel Source testified to
the reasonableness and necessity of the attorney’s fees sought, expressing his opinion
that $34,200 was a reasonable and necessary fee. The parties stipulated that the
hourly fee rate charged by Steel Source’s attorney was reasonable.
The attorney
further testified a reduction in the total fee of ten percent would sufficiently segregate
work for which fees were recoverable from work for which they were not.6 The trial
court found the attorney for Steel Source “properly segregated the attorney’s fees and
limited the amount of attorney’s fees requested to claims for which such fees are
allowed by law.” The trial court further found $30,800 was a reasonable and necessary
attorney’s fee for the services of Steel Source’s attorney in the trial court but further
reduced the award to a total of $27,607.50 for such services.
In this bench trial, we think from the presentations of both sides the court was
sufficiently apprised of the novelty and difficulty of the issues involved.
The court
received in evidence the detailed billing statements prepared by Steel Source’s
attorney. These identify the person performing the work and contain a brief description
5
Tex. Civ. Prac. & Rem. Code Ann. § 38.001(8) (West 2008); Tex. Gov’t Code
Ann. § 2253.073(b)(2) (West 2008).
6
See Tony Gullo Motors I, L.P. v. Chapa, 212 S.W.3d 299, 313-14 (Tex. 2006)
(approving evidence segregating fees by percentages).
18
of the work including the date, the amount of time spent on the task, the hourly billing
rate applicable to the person performing the work, and the fee for the identified work.
Steel Source’s attorney was admitted to practice in Texas in 1985 and is board certified
in civil appellate law. While the evidence did not touch on each of the Andersen factors,
evidence of each of the factors was not required for the trial court to determine the
reasonableness of the fees. Arthur J. Gallagher & Co. v. Dieterich, 270 S.W.3d 695,
706 (Tex.App.--Dallas 2008, no pet.) (citing Lamajak, Inc., 230 S.W. 3d at 797).
On appeal Plains Builders also argues the award of attorney’s fees must be
reversed if we reverse one of the monetary awards for the breach of contract or
McGregor Act claims because Steel Source did not segregate its fees between those
claims. As the trial court found, attorney’s fees were recoverable under either claim.
We do not understand the authority Plains Builders cites, which includes Gullo and
Kosberg v. Brown, 601 S.W.2d 414 (Tex.Civ.App.--Dallas 1980, no writ), to require
segregation of fees in this circumstance. We overrule Plains Builders’ sub-issue
challenging the award of attorney’s fees.
Cross-Appeal of Steel Source
By a single issue on cross-appeal, Steel Source argues the trial court erred by
awarding it $80,000 on its breach of the joint check agreement claim rather than the
$137,300 it sought. It points to the trial court’s finding of fact that it furnished labor to
the project for which it was not paid, totaling $137,300. But Steel Source was not
entitled to damages measured by its loss under its contract with Construction Services,
but those resulting from Plains Builders’ breach of the joint check agreement, in other
19
words, those damages that were the natural, probable and foreseeable consequence of
its failure to include Steel Source as a joint payee on eight checks. See Abraxas Petro.
Corp. v. Hornburg, 20 S.W.3d 741, 758 (Tex.App.--El Paso 2000, no pet.) (standard for
damages for breach of contract). Steel Source’s contention in support of its crossappeal essentially is that the trial court’s $80,000 award of damages for breach of the
joint check agreement is not supported by factually sufficient evidence. Conducting
such an analysis, we keep in mind the role of the trial court as trier of fact and sole
judge of the credibility of the witnesses and the weight given their testimony, Rego Co.
v. Brannon, 682 S.W.2d 677, 680 (Tex.App.--Houston [1st Dist.] 1984, writ ref’d n.r.e.),
and keep in mind we may not substitute our opinion for that of the trier of fact merely
because we might have reached a different conclusion. Herbert v. Herbert, 754 S.W.2d
141, 144 (Tex. 1988). We first examine all of the evidence, Lofton v. Texas Brine Corp.,
720 S.W.2d 804, 805 (Tex. 1986), and, having considered and weighed all of the
evidence, set aside the verdict only if the evidence is so weak or the finding is so
against the great weight and preponderance of the evidence that it is clearly wrong and
unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986); Garza v. Alviar, 395 S.W.2d
821, 823 (Tex. 1965).
Here, the evidence shows that including Steel Source as a joint payee was not a
guarantee it ultimately would receive any particular amount. Other payees had their
claims on the funds, and business considerations came into play when the joint payees
allocated the check amounts between them.
Steel Source allowed Construction
Services to retain funds from the April and May 2006 joint checks not because it was
entitled to them but because Construction Services insisted and Steel Source feared it
20
otherwise would be unable to continue work.
The difficulty of evaluating the
consequences of failing to include Steel Source as a payee on the final four checks is
particularly great because, if Steel Source had been included, the checks would have
had three payees.
After reviewing all of the evidence, we conclude that the trial court’s damage
award is not against the great weight and preponderance of the evidence, nor is it
clearly wrong or unjust. See Cain, 709 S.W.2d at 176. We overrule Steel Source’s sole
issue on cross-appeal.
Conclusion
We reverse and render judgment that Steel Source take nothing on its bond
claim for retainage from Plains Builders and Travelers. Otherwise, having overruled or
dismissed the issues of Plains Builders and the sole issue of Steel Source on crossappeal, we affirm the judgment of the trial court.
James T. Campbell
Justice
21
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.