Thomas J. Hennen v. Jerry McGinty and Villas by Design, Inc.--Appeal from 157th District Court of Harris County
Annotate this Case
Download PDF
Affirmed as Modified in Part, Reversed and Remanded in Part, and Majority and
Dissenting Opinions filed January 20, 2011.
In The
Fourteenth Court of Appeals
___________________
NO. 14-08-00983-CV
___________________
THOMAS J. HENNEN, Appellant/Cross-Appellee
V.
JERRY MCGINTY AND VILLAS BY DESIGN, INC., Appellees/Cross-Appellants
On Appeal from the 157th District Court
Harris County, Texas
Trial Court Cause No. 2005-41193
DISSENTING OPINION
A homeowner recovered $651,230.72 as the reasonable and necessary cost to repair
his house to remedy the homebuilder’s failure to comply with its contract. To affirm the
trial court’s judgment, we must conclude the record contains legally sufficient evidence
that this amount was a reasonable and necessary cost to repair the house. Because the
evidence is legally insufficient on this point, this court should reverse rather than affirm the
judgment for this damage award.
Background
In February 2001, appellant/cross-appellee Thomas J. Hennen bought a vacant lot
facing Galveston
Bay in Seabrook, Texas.
In May 2001,
Hennen
and
appellee/cross-appellant Villas By Design, Inc. (hereinafter, ―Villas‖) entered into a
contract for Villas to build a house on that lot. Hennen moved into the house in November
2002 and experienced various problems, including numerous water leaks or areas of water
intrusion in the house. Though Villas tried to address these problems and stop water from
entering the house, Hennen continued to have problems and informed Villas of this
situation. In an email sent on June 19, 2003, Hennen asked Villas to return the keys to
Hennen’s house and told Villas that on June 23, 2003, he would begin pursuing all
available legal recourse against Villas.
After June 2003, Villas did not have access to the house and Hennen did not give
Villas permission to undertake any further repairs. In July 2003, Hennen discovered
extensive and noticeable mold damage to the vertical walls going up to the ceiling in an
upstairs bathroom. During that same month, Hennen retained a lawyer to represent him in
pursuing his claims against Villas. In August 2003, an inspection company, PE Services,
inspected Hennen’s house and conducted mold testing.
PE Services determined
significant fungal contamination permeated the house. Following Hennen’s receipt of PE
Services’s report in October 2003, water damage and mold was identified in the exterior
walls, interior walls, ceilings, flooring, areas around several plumbing fixtures, and inside
the heating, ventilation, and air conditioning systems.
Hennen learned that water
penetration in the house was so widespread that repairing the damage would require
replacement of the entire roof, all of the home’s stucco, and every window in the house.
Hennen retained the services of Richard Guerra-Prats, a Corpus Christi contractor.
In its October 2003 report, PE Services documented repairs that needed to be made on the
house and recommended mold remediation. According to Guerra-Prats, PE Services
2
prepared a mold-remediation protocol. Based on this protocol, in 2003, Guerra-Prats
estimated the cost to remediate the mold using this protocol and to then build back the parts
of the house altered by the remediation. This 2003 estimate was not introduced into
evidence at trial and was not the basis of Hennen’s request for damages at trial. Though
Hennen met with attorneys and had various inspections and tests performed on the house,
Hennen did not file suit until June 22, 2005, two years after he denied Villas access to the
house.
Between June 2003 and May 2008, when this case went to trial, no work was
performed to prevent or mitigate water intrusion into the house. Consultant Mike Krismer
provided Hennen with a mold-remediation protocol for the house in July 2006. Based on
this protocol, in January 2007, Guerra-Prats provided Hennen with a detailed estimate as to
how much it would cost, in January 2007, to remediate the mold using this protocol and to
then build back the parts of the house altered by the remediation.
The total cost
Guerra-Prats estimated was $651,230.72.1 This January 2007 estimate and Guerrra-Prats’s
trial testimony are the only evidence Hennen offered at trial to meet his burden of proving
the amount of the reasonable and necessary cost to repair his house. The jury found that
this amount was $651,230.72, the amount of Guerra-Prats’s estimate, and the trial court
rendered judgment awarding Hennen this amount of damages.
Standard of Review
In their second cross-issue on appeal, Villas and appellee/cross-appellant Jerry
McGinty (hereinafter collectively, ―Villas Parties‖) assert, among other things, that the
evidence is legally insufficient to support the jury’s finding that $651,230.72 was the
reasonable and necessary cost to repair Hennen’s house. When reviewing the legal
1
In part of its opinion, the majority indicates that this estimate was performed in 2003. See ante at pp.
3–4. However, this estimate was made in January 2007, more than four years after the water intrusion
began at the house.
3
sufficiency of the evidence, we consider the evidence in the light most favorable to the
challenged finding and indulge every reasonable inference that would support it. City of
Keller v. Wilson, 168 S.W.3d 802, 823 (Tex. 2005). We must credit favorable evidence if
a reasonable fact finder could and disregard contrary evidence unless a reasonable fact
finder could not. See id. at 827. We must determine whether the evidence at trial would
enable reasonable and fair-minded people to find the facts at issue. See id. The fact
finder is the only judge of witness credibility and the weight to give to testimony. See id.
at 819.
Need for Evidence Beyond Proof of What One Contractor Would Charge
Texas has a strong public policy in favor of preserving freedom of contract. See
Fairfield Ins. Co v. Stephens Martin Paving, LP, 246 S.W.3d 653, 664 (Tex. 2008).
Unless their contract is contrary to an applicable law or public policy, parties in Texas
enjoy a broad freedom of contract. See In re Prudential Ins. Co. of Am., 148 S.W.3d 124,
129 (Tex. 2004).
This means that contractors generally have the right to charge
unreasonably high prices for their goods and services, and parties have the freedom to
choose to pay unreasonably high prices for goods and services. See id. In light of this
freedom of contract, evidence of the amounts charged or paid is not legally sufficient
evidence that these charges are reasonable or necessary; instead, separate evidence must be
offered that raises a fact issue regarding the reasonableness and necessity of the charges or
costs in question. See Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195,
200–01 (Tex. 2004); Dallas Ry. & Terminal Co. v. Gossett, 294 S.W.2d 377, 382–83 (Tex.
1956); O & B Farms, Inc. v. Black, 300 S.W.3d 418, 422–23 (Tex. App.—Houston [14th
Dist.] 2009, pet. denied); Dumler v. Quality Work By Davidson, No. 14-06-00536-CV,
2008 WL 89961, at *4 (Tex. App.—Houston [14th Dist.] Jan. 10, 2008, no pet.) (mem.
op.); Jackson v. Gutierrez, 77 S.W.3d 898, 904 (Tex. App.—Houston [14th Dist.] 2002, no
pet.); Allright, Inc. v. Lowe, 500 S.W.2d 190, 191–92 (Tex. Civ. App.—Houston [14th
4
Dist.] 1973, no writ); Ebby Halliday Real Estate, Inc. v. Murnan, 916 S.W.2d 585, 589
(Tex. App.—Fort Worth 1996, writ denied).
Sufficiency of Evidence Regarding Necessity of the Repairs
Regarding necessity, Hennen points to Krismer’s expert testimony.
Though
Krismer did testify regarding various construction defects in the house, Krismer did not
testify as to the amount of any alleged repair costs or damages. Nor did Krismer testify
that his remediation plan was reasonable or necessary. At trial, there was no direct
evidence that it would cost $651,230.72 to make the necessary repairs to the house. Nor
was there evidence that Villas’s breaches of contract in constructing the house resulted in
damages that would cost $651,230.72 to repair.
Instead, Hennen relied upon
Guerrra-Prats’s testimony that it would cost this amount in January 2007 to remediate the
mold using Krismer’s protocol and to then build back the parts of the house altered by the
remediation. After four years of water intrusion into the house with no effort to prevent or
mitigate this intrusion, Guerra-Prats estimated how much he would charge to remediate the
mold and restore the house after remediation. Even considering the evidence in the light
most favorable to the jury’s finding and indulging every reasonable inference that would
support it, the trial evidence would not enable reasonable and fair-minded people to find
that $651,230.72 was the cost of necessary repairs.
Sufficiency of Evidence that $651,230.72 was a Reasonable Cost for the Repairs
Regarding reasonableness, Krismer did not testify as to what it would cost to
implement his mold-remediation protocol.
Guerra-Prats’s testimony.
For this evidence, Hennen points to
In addition to testifying about his qualifications and
experience, Guerra-Prats testified as follows:
Guerra-Prats is a general contractor from Corpus Christi, Texas.
5
In January 2007, based on Krismer’s mold-remediation protocol, Guerra-Prats
provided Hennen with an estimate of the costs of implementing the protocol
(hereinafter, ―Remediation Work‖) and of building back the parts of the house
altered by the remediation (hereinafter, ―Build Back Work‖).
Guerra-Prats provided Hennen with bids to repair Hennen’s house as of January
2007. In Guerra-Prats’s bid for the Remediation Work, the cost to Hennen is
$246,992.96. In Guerra-Prats’s bid for the Build Back Work, the cost to Hennen is
$404,238.76. The total of these two bids or cost estimates is $651,230.72.
Guerra-Prats provided Hennen with detailed information reflecting the items of
parts and labor that form the basis for these bids or cost estimates.
The prices reflected in Guerra-Prats’s costs estimates were generated by a software
program that used Houston prices. Some of the costs came from subcontractors or
historical data or jobs that Guerra-Prats had done.
―Not every price is right, so we have to cross-reference and double check all our
pricing.‖
Between January 2007 and May 2008 (the time of trial), the costs for this type of
work increased across the board by ten to fifteen percent.
In coming up with the numbers for the bid for the Build Back Work, Guerra-Prats
did not get competitive bids from contractors in Seabrook, Texas.
Neither Guerra-Prats nor any other witness (1) provided the jury with an opinion
regarding the reasonable cost of the necessary repairs to Hennen’s house or (2) testified
that the pricing in the two bids or cost estimates provided by Guerra-Prats was reasonable.
Guerra-Prats’s testimony that some of these prices were generated by computer software
based on Houston prices does not address whether these prices were reasonable.
Guerra-Prats’s testimony that he cross-references and double-checks all of his prices is a
vague statement that does not specify any substantive standard that Guerra-Prats uses to set
his prices.
6
There was no direct evidence at trial that a reasonable cost to repair the house was
$651,230.72. Under binding precedent, Guerra-Prats’s testimony that he would charge
Hennen a total of $651,230.72 for the Remediation Work and the Build Back Work is
legally insufficient to support a finding that this amount is a reasonable cost to repair
Hennen’s house. 2 See Mustang Pipeline Co., 134 S.W.3d at 200–201; Dallas Ry. &
Terminal Co., 294 S.W.2d at 382–83; O & B Farms, Inc., 300 S.W.3d at 422–23; Dumler,
2008 WL 89961, at *4; Allright, Inc., 500 S.W.2d at 191–92. If Guerra-Prats had opined
that the amount in question was a reasonable and necessary cost to repair the house, this
testimony would have been sufficient to raise a fact issue. See Lowe, 500 S.W.2d at 192.
Though a fact issue can be raised even if no witness uses the word ―reasonable,‖ in the case
under review, this can only occur if, considering the evidence in the light most favorable to
the jury’s finding and indulging every reasonable inference that would support it, the
record contains evidence that would enable reasonable and fair-minded people to find
$651,230.72 was a reasonable and necessary cost to repair Hennen’s house. See City of
Keller, 168 S.W.3d at 827. Neither Hennen nor the majority point to any such evidence,
and a review of the record fails to reveal any.
The only case the majority cites regarding this issue is Hernandez v. Lautensack.
See 201 S.W.3d 771, 777 (Tex. App.—Fort Worth 2006, pet. denied). Presuming for the
sake of argument that this court should follow this opinion from a sister court of appeals,
the Hernandez case is not on point. In Hernandez, an expert witness testified as to how
much he would charge to replace the plaintiff’s roof, but no witness opined that this
amount was reasonable.
See id.
Nonetheless, the Hernandez court found legally
sufficient evidence that this amount was reasonable based on evidence that this amount
Even if the record contained evidence that Krismer’s mold-remediation protocol was necessary, this
evidence would not raise a fact issue as to whether Guerra-Prats’s bids or cost estimates were reasonable.
See Dallas Ry. & Terminal Co., 294 S.W.2d at 382–83 (holding that proof certain services are necessary
does not raise a fact issue as to the reasonable cost of these services).
2
7
was less than what the defendant himself would charge to replace the roof and
proportionately less than what a third-party contractor would charge to replace part of the
roof. See id. In the case under review, only Guerra-Prats testified concerning the amount
it would cost Hennen to have the repair work done; therefore, the Hernandez case is not on
point. See id.
Hennen has not paid any part of the $651,230.72, and Guerra-Prats’s testimony was
offered as a basis for a damage award in Hennen’s favor. In this context, the requirement
of independent evidence of the reasonableness of these charges is even more important to
prevent excessive damage awards based on unreasonably high price quotes. Nonetheless,
the majority effectively concludes that Guerra-Prats’s testimony that he would charge
$651,230.72 for the Remediation Work and Build Back Work is legally sufficient evidence
that this amount is reasonable.
This analysis conflicts with binding precedent that
requires additional evidence to raise a fact issue regarding reasonableness. See Mustang
Pipeline Co., 134 S.W.3d at 200–201; Dallas Ry. & Terminal Co., 294 S.W.2d at 382–83;
O & B Farms, Inc., 300 S.W.3d at 422–23; Dumler, 2008 WL 89961, at *4; Allright, Inc.,
500 S.W.2d at 191–92. This court should hold that the evidence is legally insufficient to
establish that $651,230.72 was a reasonable and necessary cost to repair the house.
Conclusion
For this court to affirm the trial court’s judgment awarding Hennen $651,230.72 in
damages, the trial record must contain legally sufficient evidence that this amount was a
reasonable and necessary cost to repair Hennen’s house. Under this court’s binding
precedent, if there were legally sufficient evidence that the Remediation Work and Build
Back Work were necessary to repair the house and if Guerra-Prats had provided the jury
with an opinion that the stated amount was a reasonable charge for this work, then the
evidence would be legally sufficient. But Guerra-Prats did not provide such an opinion,
and under the applicable standard of review the trial evidence would not enable reasonable
8
and fair-minded people to find that $651,230.72 was a reasonable and necessary cost to
repair Hennen’s house. Because the evidence is legally insufficient to support this jury
finding, Hennen may not recover damages based on repair costs, which were the only
damages awarded in the trial court’s judgment. Accordingly, this court should sustain the
Villas Parties’ second cross-issue and reverse the trial court’s judgment awarding damages
based on repair costs. Because the court instead affirms this part of the trial court’s
judgment, I respectfully dissent.
/s/
Kem Thompson Frost
Justice
Panel consists of Justices Anderson, Frost, and Seymore. (Anderson, J., majority).
9
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.