In re Block Island Power Co. Petition for Declaratory Judgment
Annotate this Case
The Supreme Court affirmed the decision of the Public Utilities Commission (PUC) denying the petition for a declaratory judgment filed by Block Island Power Company (BIPCo), holding that there were no grounds to overturn the PUC's decision.
In 2009, the legislature enacted R.I. Gen. Laws 39-26.1-7 (the enabling act) authorizing the Town of New Shoreham Project. In 2017, BIPCo sought a declaratory judgment declaring that the enabling act required the costs for BIPCo's interconnection facilities and backup transformer to be socialized across all electric ratepayers in the state, not just those in the Town. The PUC issued a judgment against BIPCo. The Supreme Court affirmed, holding that the PUC's reading and application of the statute was without error.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.