Contract Steel Sales, Inc. v. FREEDOM CONST. CO.

Annotate this Case

353 S.E.2d 418 (1987)

CONTRACT STEEL SALES, INC. v. FREEDOM CONSTRUCTION COMPANY and E.I. Du Pont De Nemours and Company.

No. 8618SC599.

Court of Appeals of North Carolina.

March 3, 1987.

*419 Foster, Conner, Robson & Gumbiner P.A. by Eric C. Rowe and Richard D. Conner, Greensboro, for plaintiff-appellant.

Smith, Helms, Mulliss & Moore by Robert A. Wicker and Catherine C. Eagles, Greensboro, for defendants-appellees.

*420 JOHNSON, Judge.

It is not disputed that plaintiff is a first tier subcontractor within the meaning of G.S. 44A-17(2) or that Du Pont is an owner obligor as defined by G.S. 44A-17(3), by virtue of funds that were owed to Freedom, the general contractor.

The two primary questions argued on appeal are (1) whether plaintiff furnished materials at the site of improvement to Du Pont's real property as contemplated by G.S. 44A-18(1), and (2) whether plaintiff's letter, dated 6 December 1983, substantially complied with the requirement of notice as stated in G.S. 44A-19.

If plaintiff, as a first tier subcontractor, furnished materials at the site of improvement then the lien granted pursuant to G.S. 44A-18(1), was perfected upon plaintiff giving written notice, as required by G.S. 44A-19, to Du Pont. Upon Du Pont's receipt of the requisite written notice, Du Pont was under a duty, pursuant to G.S. 44A-20, to retain any funds subject to plaintiff's lien. Du Pont, pursuant to G.S. 44A-20(b), would be personally liable to plaintiff for any payments Du Pont made to Freedom after receipt of plaintiff's notice of claim of lien.

I

We first address the question of whether plaintiff, pursuant to a contract with Freedom, a general contractor, furnished materials at the site of improvement to Du Pont's real property. We hold that plaintiff furnished materials at the site of improvement to Du Pont's real property as called for by the contract between plaintiff and Freedom. We express no opinion on the main issues preserved for trial by jury, to wit: (1) whether plaintiff is entitled to recover against either defendant Du Pont or defendant Freedom pursuant to the subcontract between plaintiff and defendant Freedom, and (2) whether the steel fabricated pursuant to the subcontract was defective or properly rejected by defendants.

The statute, G.S. 44A-18(1), by which plaintiff seeks to assert its lien, states the following:

(1) A first tier subcontractor who furnished labor or materials at the site of improvement shall be entitled to a lien upon funds which are owed to the contractor with whom the first tier subcontractor dealt and which arise out of the improvement on which the first tier subcontractor worked or furnished materials.

G.S. 44A-18(1).

In Raleigh Paint and Wallpaper Co. v. Peacock & Associates, Inc., 38 N.C.App. 144, 247 S.E.2d 728 (1978), disc. rev. denied, 296 N.C. 415, 251 S.E.2d 470 (1979), this Court held that G.S. 44A-8 did not require a lien claimant who contracted with an owner to personally deliver materials to the site of improvement. Recently, this Court followed the example set in Raleigh Paint, supra, and made an exhaustive inquiry to determine whether the General Assembly intended that G.S. 44A-18 require a subcontractor to personally deliver materials to the site of improvement. See generally, Queensboro Steel Corp. v. East Coast Machine & Iron Works, Inc., 82 N.C.App. 182, 346 S.E.2d 248 (1986). In Queensboro Steel Corp., supra, this Court held the following:

We now hold there is no such requirement under G.S. sec. 44A-18. If a third tier subcontractor delivers to a second tier subcontractor with the intent that the materials ultimately be delivered at the site, and the materials are actually delivered at the site, the third tier subcontractor has a lien on the funds owed to the second tier subcontractor for those materials.

Queensboro Steel Corp., supra, at 191, 346 S.E.2d at 254 (emphasis supplied). Although the holding in Queensboro Steel Corp., supra, is not dispositive of the case sub judice this Court did review relevant case law, legislative history, and legal commentary from which we may draw guidance.

*421 This Court in Queensboro Steel Corp., supra, noted the following: "[t]he term `furnish' is used in almost every State's mechanics' lien statute. Annot., 32 A.L.R. 4th 1130, 1135 (1984). It is a `key concept,' sometimes `imposing a less stringent requirment.' "Id. Queensboro Steel Corp., supra, at 186, 346 S.E.2d at 251. The meaning of furnish as construed by this Court is to supply, provide or equip. Id. at 185-86, 346 S.E.2d at 250. This Court in Queensboro Steel Corp., supra, noted the following pertinent observation:

In contrast to the State rules discussed in Annot., 32 A.L.R. 4th 1130, 1164-68, Secs. 11-13 (1984) and Annot., 39 A.L. R.2d 394, 435-49, Secs. 11-16 (1955), North Carolina's current mechanics' and materialmen's lien statutes apparently do not require actual incorporation of materials into the improvement, even when the materials are furnished to a subcontractor. See Urban & Miles, supra, at 303-04, 354-55. But see Fulp & Linville v. Kernersville Light and Power Company, 157 N.C. 154, 72 S.E. 869 (1911) (interpreting an older statute that has since been repealed). In some states, proof of actual use is required when the materials are delivered to a contractor or subcontractor rather than directly to the owner. This protects the owner against liens based on materials that are never actually delivered and of which the owner has no notice. This function is served in our State, at least in part, by the requirement that the materials be delivered at the site, whether by the lien claimant or by another party.

Queensboro Steel, supra, at 190, 346 S.E.2d at 253. We hereby adopt the reasoning in Queensboro Steel, supra, and hold that materials are furnished within the meaning of G.S. 44A-18 if pursuant to a subcontract a subcontractor delivers materials to the site of improvement to real property.

Bearing the foregoing in mind we now turn to the trial court's pertinent findings of fact to determine if they support a conclusion of law that plaintiff did not furnish materials to the site of improvement.

The trial court's conclusion of law number 2 that "Contract Steel is not entitled to a lien on the funds or on the real property owned by Du Pont" indicates that the court concluded that plaintiff had not furnished materials at the site of improvement.

The trial court, sitting as the trier of fact, in pertinent part, made the following findings of fact:

4. In August and September, 1983, Contract Steel delivered reinforcing Steel to the jobsite. Some of these items, consisting of wire mesh and rebar, were incorporated into the improvement, and Contract Steel was paid $1,600. On September 6 and 15, angle frames, regalvanized angle frames and galvanized field bolts were delivered to the jobsite. On September 22, 1983, one load of galvanized structural steel was delivered to the jobsite. The total amount of the structural and fabricated miscellaneous steel at the jobsite on September 22, as a result of the deliveries on September 6, 15 and 22, was approximately 14 tons. 5. On September 28, 1983, the approximately 14 tons of steel was inspected at the site by a quality assurance inspector for du Pont. Du Pont's inspector then inspected the remaining 9 tons of steel under the subcontract at the galvanizing plant in Aberdeen, North Carolina. The approximately 14 tons of steel were not accepted by Freedom and were refused for alleged defects. The approximately 14 tons of steel and the approximately 9 tons of steel were returned to Contract Steel's plant in Staley, North Carolina, for reworking. Staley North Carolina, is located more than 80 miles from the jobsite. In connection with inspection of the steel, Du Pont's quality assurance inspector traveled to Staley, North Carolina. 6. On November 7, 1983, approximately 14 tons of structural and fabricated miscellanous steel were delivered to the jobsite. On November 8, 1983, the remaining approximately 9 tons of steel under the contract were taken from the galvanizing plant to the jobsite. On November 8, 1983, Du Pont and Freedom *422 refused to accept the steel and so notified Contract Steel.

(Emphasis supplied).

Three things are clear from the trial court's findings set forth hereinabove. First, plaintiff delivered the amount of material that was required by the subcontract. Second, Du Pont employed inspectors who knew that the material had been delivered to the job site. And third, some of the material furnished by plaintiff was actually incorporated into the MMF Process Building. The trial court's findings establish that plaintiff, pursuant to a subcontract with Freedom, furnished materials to the site of improvement to the real property improved. Therefore, pursuant to G.S. 44A-18, plaintiff was entitled to a lien upon funds owed by Du Pont to Freedom. This was true "whether or not amounts are due and whether or not performance or delivery is complete." G.S. 44A-18(5). Plaintiff's lien was perfected "upon giving of notice in writing to the obligor as hereinafter provided and shall be effective upon the receipt thereof by such obligor." G.S. 44A-18(6).

II

Our second line of inquiry is whether plaintiff, a first tier subcontractor, substantially complied with the requirements of G.S. 44A-19 for giving adequate notice of a claim of lien. We hold that plaintiff substantially complied with G.S. 44A-19.

In pertinent part G.S. 44A-19 states the following:

44A-19. Notice to obligor. (a) Notice of a claim of lien shall set forth: (1) The name and address of the person claiming the lien, (2) A general description of the real property improved, (3) The name and address of the person with whom the lien claimant contracted to improve real property, (4) The name and address of each person against or through whom subrogation rights are claimed, (5) A general description of the contract and the person against whose interest the lien is claimed, and (6) The amount claimed by the lien claimant under this contract. (b) All notices of claims of liens by first, second or third tier subcontractors must be given using a form substantially as follows: NOTICE OF CLAIM OF LIEN BY FIRST, SECOND OR THIRD TIER SUBCONTRACTOR To: 1. ..................., owner of property involved. (Name and address) 2. ..................., general contractor. (Name and address) 3. ..................., first tier subcontractor against or through whom subrogation (Name and address) is claimed if any 4. ..................., second tier subcontractor against or through whom (Name and address) subrogation is claimed, if any General description of real property where labor performed or material furnished: .................................................................................. .................................................................................. .................................................................................. General description of undersigned lien claimant's contract including the names of the parties thereto: ............................................................. .................................................................................. .................................................................................. The amount of lien claimed pursuant to the above described contract: $.......... The undersigned lien claimant gives this notice of claim of lien pursuant to North Carolina law and claims all rights of subrogation to which he is entitled under Part 2 of Article 2 of Chapter 44A of the General Statutes of North Carolina. *423 Dated............................. .............................,Lien Claimant ........................................... (Address)

The 6 December 1986 letter by which plaintiff claims to have notified Du Pont that plaintiff was claiming a lien states the following:

Dupont Company P.O. Drawer Z Fayetteville, N.C. 28302 Re: Dupont Co. MMF Process Building Fayetteville, N.C. Gentlemen: Pursuant to our agreement with Freedom Construction Co. 315 S. Moore St. Sanford, N.C. to furnish structural, fabricated miscellaneous steel and reinforcing steel for the Dupont Co. MMF Process Building, Fayetteville, N.C. we have on November 7, 1983 actually furnished to the job site all structural steel. The amount of $50,008.91 remaing [sic] due and owing to us and Freedom Construction Co. has in our opinion, wrongfully refused payment. Please take notice that we hereby claim a lien in any and all funds owing from you to Freedom Const. to the extent of $50,008.91 and claim and reserve all of our rights under Chapter 44A of the North Carolina General Statute. On receipt of this notice of claim of lien please confirm to us in writing that such funds have been withheld from Freedom Const. Co. While we deem this action unfortunate in view of our desire to maintain our working relationship with you, we are taking this action in a timely manner to protect our legal right, and hope that a prompt settlement will be made. You will find attached a copy of our letter to Freedom Const. Co. Very truly yours, CONTRACT STEEL SALES, INC. Philip A. Hutson President Encl. cc: Freedom Const. Co.

In support of its conclusion of law that the letter set forth, hereinabove, did not substantially comply with the notice requirements of G.S. 44A-19, the trial court made the following findings of fact:

12. The letter (a) is not labeled as a `Notice of Claim of Lien,' (b) is not separated into paragraphs numbered 1 through 4, (c) does not indicate on the signature line that it is being signed by a `Lien claimant,' and (d) does not list the address of the lien claimant at the end of the letter, although the letter was sent on stationary of Contract Steel, whose address and telephone number appear on the letterhead. 13. The letter was sent to `Du Pont Company, P.O. Drawer Z, Fayetteville, North Carolina, 28302,' and refers to the real property as `the Du Pont Co., MMF Process Building, Fayetteville, N.C.'

The trial court's findings of fact, with the exception of finding of fact number 13, pertain to the form of plaintiff's notice of a claim of lien and not its substance. Finding of fact 12(a) is directly attributable to the form's caption as set forth in G.S. 44A-19. Plaintiff's letter clearly stated that Du Pont was to "take notice that we hereby claim a lien." Moreover, the exact statutory language was utilized in paragraph five as follows: "On receipt of this notice of claim of lien please confirm to us in writing that such funds have been withheld from Freedom Const. Co." (Emphasis supplied). Although, as the trial court found as fact, plaintiff's notice of a claim of lien "is not separated into paragraphs numbered 1 through 4," we do not deem this deviation to be fatally deficient. Plaintiff's notice of a claim of lien informed Du *424 Pont that plaintiff was thereby claiming a lien and said notice was signed by Philip A. Hutson in his capacity as president of the corporate plaintiff. Therefore, we deem that it was sufficiently indicated by plaintiff's notice of a claim of lien that said notice was signed by a lien claimant. The trial court also found that although plaintiff's address appeared on its business stationary the letter "does not list the address of the lien claimant at the end of the letter." We hold that this finding does not warrant a conclusion of law that plaintiff's notice did not substantially comply with G.S. 44A-19.

Defendants argue and the trial court agreed that plaintiff failed to substantially comply with G.S. 44A-19(a)(3) by not setting forth a general description of the real property improved. Plaintiff's letter describes the subject real property as follows: "Dupont Co. MMF Process Building, Fayetteville, N.C." We conclude that the foregoing description substantially complies with G.S. 44A-19(a)(3) by serving the purpose of giving Du Pont, the owner of the real property involved, sufficient notice of the real property being improved. Du Pont argues that the subject real property is actually located more than sixteen (16) miles away from Fayetteville, North Carolina. Therefore, defendants argue, "[a]lthough the plant has a Fayetteville, North Carolina post office or mailing address, the mailing address is not what is required by the statute." We find this argument unpersuasive. The purpose of G.S. 44A-19 is to provide the obligor with notice. Defendants do not seriously dispute the fact that there has never been any question about what real property plaintiff referred to in its notice of claim of lien. Moreover, we note that Du Pont had actual notice of the real property referred to by plaintiff by virtue of Du Pont's employees inspecting the steel furnished by plaintiff at the site of improvement.

We reject Du Pont's invitation to analogize the case sub judice to cases where a contractor may actually file a lien against real property instead of against funds owed by the obligor. See Mebane Lumber Co. v. Avery & Bullock Builders, Inc., 270 N.C. 337, 154 S.E.2d 665 (1967). See also Neal v. Whisnant, 266 N.C. 89, 145 S.E.2d 379 (1965), Lowery v. Haithcock, 239 N.C. 67, 79 S.E.2d 204 (1953). The notice of claim of lien filed by plaintiff is for the purpose of giving the owner obligor notice. The notice is not intended to protect innocent third parties and does not affect the title to the real property being improved. Plaintiff's notice of claim of lien fulfilled the purpose of G.S. 44A-19. Du Pont's employees even referred to the location of site of improvement as the "Fayetteville work site." There was only one building at the "Fayetteville work site" designated as the "MMF Process Building."

In conclusion we hold that the trial court's findings do not support its conclusion of law that plaintiff's "letter dated December 6, 1983, does not substantially comply with the requirements of G.S. 44A-19, and does not constitute a valid notice of claim of lien." To the contrary, plaintiff's letter, set forth, hereinabove, does as a matter of law substantially comply with the notice requirements set forth in G.S. 44A-19.

Because plaintiff was entitled to a lien and perfected that lien, the judgment must be reversed. Therefore, the cause is remanded so that a trial may be had on those issues that were stipulated to by the parties as preserved for a trial by jury.

Reversed and remanded.

ARNOLD and EAGLES, JJ., concur.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.