Sosa v 46th St. Dev. LLC

Annotate this Case
Sosa v 46th St. Dev. LLC 2012 NY Slip Op 08642 Decided on December 13, 2012 Appellate Division, First Department Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.

Decided on December 13, 2012
Mazzarelli, J.P., Catterson, Moskowitz, Manzanet-Daniels, Román, JJ.
8056 112660/09

[*1]Enrique Sosa, Plaintiff,

v

46th Street Development LLC, et al., Defendants-Appellants, Five Star Electrical Corp., Defendant-Respondent.




Goldberg Segalla LLP, Garden City (Brian W. McElhenny of
counsel), for appellants.
Peisner Girsh Schaefer & Sfouggatakis, New York (Allen H.
Gueldenzopf of counsel), for respondent.

Order, Supreme Court, New York County (Eileen A. Rakower, J.), entered December 23, 2011, which, to the extent appealed from as limited by the briefs, denied the motion of defendant Plaza Construction Corporation (Plaza) for conditional summary judgment on its cross claim seeking contractual indemnification from defendant Five Star Electrical Corp. (Five Star), affirmed, without costs.

Defendant 46 Street Development LLC (owner) hired Plaza to manage the construction of a 42-story residential building owned by the former. Plaza hired Five Star as the electrical subcontractor. Pursuant to the contract between Plaza and the owner, Plaza was solely responsible for "coordinating the construction of all portions of the work," and had broad and specific responsibilities relating to site safety. Indeed, Plaza hired an outside safety coordinator, Total Safety Consulting, to ensure that all proper safety precautions were taken on the site. The contract between Plaza and Five Star contained an indemnification and hold harmless clause, which provided that Five Star would indemnify and hold Plaza harmless for damages which "ar[i]se out of or are connected with or ... claimed to arise out of or be connected with ... performance of [w]ork by [Five Star]."

Plaintiff Enrique Sosa was an employee of non party Port Morris Tile Corporation, the tile contractor. He alleges that at about 7:15 a.m. on December 13, 2007, while engaged in tiling work in a bathroom in an apartment on the 10th floor, he sustained injuries from an electric shock after coming into contact with an exposed, hanging electric wire. When the accident occurred, Con Edison was already in the process of transforming the power supply in the building from "temporary" to "permanent." The temporary supply was made available to contractors while the superstructure of the building was being erected. Robert Marrone, who was Plaza's superintendent at the project in the year leading up to the accident, testified that power was gradually switched to permanent as the building rose and individual apartments became ready to be finished. However, even after sections of the building went to permanent power supply, that [*2]power would remain off unless a contractor specifically requested that power be supplied to the apartments. To connect the power in those apartments, Five Star was required to activate breakers at central panels which controlled power to three floors. It also had to activate breakers in the individual apartments where the requesting contractor desired to work. Plaza generally coordinated with Five Star when individual contractors needed power in an apartment.

A few days before the accident in question, Port Morris requested that the permanent power supply in the apartments be activated in two specific areas, including at the outlets providing electricity for washing machines. Port Morris planned to plug tile-cutting saws into those outlets. Five Star accommodated the request by activating breakers at the central panels and at the necessary areas in the apartments. It also went to each individual apartment to "safe off" the relevant outlets, which involved insulating the wires at those outlets to prevent the workers from sustaining electrical shocks. Chris Cote, Five Star's foreman, testified at his deposition that on the night before the accident he saw workers from contractors other than Port Morris working in apartments and using permanent electricity. The only way these workers could have accessed the electricity was to activate breakers in those apartments. However, these workers were not permitted to do so without direct authorization from Five Star. Cote reported what he saw to Plaza. This was not the first time that Cote noticed other contractors circumventing Five Star to draw more power for their work. In fact, he testified, it happened more frequently in the beginning stages of the project. The subject incident occurred toward the end of the project.

Two of Five Star's workers gave testimony that was consistent with Cote's to the extent they stated that it was not unheard of for other contractors, after the permanent power supply had been activated, to energize electric power in individual apartments without Five Star's knowledge or permission. One of the workers, Ralph Lopez, testified that from the time the permanent power supply was activated at the site, he was aware of incidents where other trades would activate breakers inside apartments without Five Star's knowledge. Bridgette Kennedy, who had been working at the job for a few weeks before the accident, testified that the problem occurred on a daily basis. She further averred that the problem was not uncommon in the industry. Finally, Kennedy testified that the issue was discussed at safety meetings run by Plaza through its contractor, Total Safety Consulting.

Plaza's superintendent on the project, William Rogers, testified that it was "possible" that there was a problem during the construction of the building with contractors activating electricity in apartments without proper authorization. He further testified that it was "possible" that the issue came up during safety meetings.

Plaza cross-claimed against Five Star for, inter alia, contractual indemnification. It then moved for conditional summary judgment on that claim. Conceding that any evidence of active negligence on its part would render the indemnification clause unenforceable, Plaza argued that "[t]he fact that a construction manager runs safety meetings, inspects the site, supervises and coordinates the work of the trades etc. is not the basis for a claim of active negligence."

In opposition, Five Star did not contest that the indemnification provision covered the subject accident. However, relying on testimony from Five Star's witnesses that there was a problem at the construction site with unauthorized activation of permanent power, it asserted that, pursuant to General Obligations Law § 5-322.1, an issue of fact existed regarding enforceability of the indemnification provision.

In a ruling from the bench, the court denied the motion. It stated that "to the extent that [*3]Plaza was coordinating the different trades within the unit, whether or not there was knowledge of them turning the circuit breakers on is a question of fact. One of [Five] Star's workers says they kept finding the circuit breakers switched on when they should have been switched off, and this is a question for the jury."

As trite as such recitations have become, this is a case that deserves a brief reiteration of the by now well-settled constraints imposed on any court considering a summary judgment motion. "On a motion for summary judgment, facts must be viewed in the light most favorable to the non-moving party. Summary judgment is a drastic remedy, to be granted only where the moving party has tendered sufficient evidence to demonstrate the absence of any material issues of fact and then only if, upon the moving party's meeting of this burden, the non-moving party fails to establish the existence of material issues of fact which require a trial of the action" (Vega v Restani Constr. Corp., 18 NY3d 499, 503 [2012] [internal quotation marks omitted]). Courts may not resolve summary judgment motions by making credibility determinations, as those are exclusively within the province of the trier of fact (see Sanchez v Finke, 288 AD2d 122, 123 [1st Dept 2001]).

Applying these principles, the burden was on Plaza to demonstrate, beyond a material issue of fact, that it bore no responsibility for plaintiff's accident. Because this was an accident on a construction site, it had to show that it did not exercise any authority over the means and methods of plaintiff's work, or that, to the extent the accident arose out of a dangerous condition on the premises, it was not liable for the condition (see Cappabianca v Skanska USA Bldg. Inc., 99 AD3d 139, 148 [1st Dept 2012]). It does not appear to be in dispute that this accident falls into the latter category. Thus, Plaza was required to establish that it did not create the condition or have actual or constructive notice of its existence prior to the accident in sufficient time to take corrective measures (see Mitchell v New York Univ., 12 AD3d 200, 201 [1st Dept 2004]).

It appears from the testimony, especially that of Lopez and Kennedy, that there was some history during the project of contractors activating the electricity in individual apartments without having first received the proper authorization. Further, and significantly, Kennedy testified that the issue came up at safety meetings run by Plaza. This suggests that Plaza was concerned about the practice and considered it a possible threat to the safety of workers such as plaintiff. No one from Plaza refuted the testimony of Lopez and Kennedy. To the contrary, its superintendent Rogers stated that it was "possible" that this occurred. Under these circumstances, and giving every benefit of the doubt to Five Star as the non-moving party, we find that an issue of fact exists as to whether Plaza had the requisite notice of a dangerous condition in sufficient time to do something about it. Accordingly, summary judgment was properly denied (see Barraco v First Lenox Terrace Assoc., 25 AD3d 427, 429 [1st Dept 2006]).

In opining that there are no issues of fact whether Plaza was negligent, the dissent misapprehends the record. First, it states that Cote "testified that there was no ongoing problem with other subcontractors turning on electrical power before the plaintiff's accident". In fact, however, Cote testified that, even in the early stages of construction, contractors were "trying to bypass Five Star Electric to get more power for their work." Including Lopez and Kennnedy, the two other Five Star workers who testified, there were three witnesses who consistently testified that in the weeks prior to the accident, there was an issue with unauthorized activations of electricity.

The dissent further reads the record incorrectly when it states that Kennedy "could not remember when she worked at the project." At first she could not, when she asked to describe in [*4]absolute terms her time energizing outlets in individual apartments. However, when asked to state the period of time in terms of weeks or months, she answered, "Probably a couple of weeks." Again, this Court is not permitted to make credibility determinations and as such this testimony cannot be rejected out of hand. Further, contrary to the dissent's comment that Lopez could not say when contractors accessed electricity "with reference to the plaintiff's accident," Lopez's testimony that the problem existed was in response to a question asking if it happened "[f]rom the time the power was provided to the apartment panels and was permanent." Because Marrone testified that power was switched gradually from temporary to permanent, beginning on the lowest floors and proceeding to the higher floors, and the accident occurred on the 10th floor, an inference can be drawn that Lopez was describing a problem which began some time before the accident.

Finally, the dissent ignores Kennedy's testimony that the issue of other contractors activating electricity in individual apartments was discussed at Plaza's safety meetings. If we assume this to be true, as we must, it would evince specific awareness of the problem and an acknowledgment by Plaza that it considered it to be a significant safety concern. Accordingly, the cases cited by the dissent where the defendant only had a general awareness of a dangerous condition are completely inapposite.

Five Star has pointed to concrete evidence in the record to suggest that Plaza had notice of a dangerous condition on the construction site in sufficient time to remedy it. Accordingly, because a material issue of fact exists whether Plaza's negligence voids Five Star's contractual obligation to indemnify Plaza against plaintiff's claims, the motion court properly denied Plaza summary judgment on its cross claim against Five Star. All concur except Catterson, J. who dissents in a memorandum as follows:
CATTERSON, J. (dissenting)

I must respectfully dissent. In my opinion, codefendant subcontractor Five Star Electrical Corp. (hereinafter referred to as "Five Star") fails to raise an issue of fact as to whether defendant Plaza Construction Corp. was actively negligent in bringing about the plaintiff's injury which was caused by a live, exposed wire while he was tiling a bathroom. Five Star contends, inter alia, that general contractor Plaza had constructive notice of a dangerous condition at the building site where other trades were allegedly turning on electrical power without authorization. In my view, the testimony upon which Five Star relies simply does not support its contention.

As set forth in greater detail below, at best the testimony of two Five Star electricians and its foreman establishes only that Plaza may have had a general awareness of a potentially hazardous condition, which precedent deems is an insufficient basis for constructive notice. Moreover, the testimony of the Five Star foreman as to a telephone call he made to Plaza regarding a situation where other tradesmen had turned on circuit breakers in some apartments also fails to raise an issue of fact as to notice. Given the timing of the call on the night before the [*5]plaintiff's accident, there is no evidence of record that Plaza could have taken any concrete steps to remedy the situation before the plaintiff's accident at 7.15 a.m. the following morning. Therefore, in my view, Plaza is entitled to contractual indemnification from Five Star, and I would grant its motion for summary judgment.

Defendant 46th Street Development LLC hired Plaza to manage the construction of a 42-story residential building. Plaza's contractual responsibility included "coordinating the construction of all portions of the work" among the trade subcontractors at the site. Plaza hired Five Star for the electrical work and nonparty Port Morris Tile Corp. for the tile work. The plaintiff, an employee of Port Morris Tile, alleges that at about 7:15 a.m. on December 13, 2007, he sustained injuries from an electric shock after touching an exposed, live electric wire while tiling a bathroom in one of the apartments in the building.

The plaintiff brought this action against, inter alia, Plaza and Five Star alleging violations of Labor Law §§ 200, 240, and 241. Plaza cross-claimed against Five Star for contractual indemnification based on a very broad indemnification and "hold harmless" provision, which stated that Five Star would indemnify and hold Plaza harmless for damages that "arise out of or are connected with [...] performance of [w]ork by the subcontractor."

At the conclusion of discovery, Plaza moved for summary judgment on its indemnity claim against Five Star on the ground that the plaintiff's accident arose out of Five Star's work. Plaza argued that the plaintiff was injured after he touched live electrical wires that the plaintiff claimed were not taped or capped to prevent shocks. Plaza contended that the broad indemnity clause applied whether Five Star was negligent or not.

Five Star did not dispute that the plaintiff's accident arose out of or was connected to Five Star's electrical work. Rather, Five Star argued that New York General Obligations Law § 5-322.1 precludes full contractual indemnification on the ground that Plaza was actively negligent. Specifically, Five Star contended that there was evidence that Plaza had notice that other subcontractors were improperly turning on circuit breakers and that Plaza failed to "coordinate the trades" at the project. The motion court agreed and denied Plaza's motion.

The majority affirms, finding that there is "concrete evidence in the record to suggest that Plaza had notice of a dangerous condition on the construction site in sufficient time to remedy it." For the reasons set forth below, I disagree. New York General Obligations Law § 5-322.1(1) states that "[an] ... agreement ... in connection with ... a contract or agreement relative to the construction ... of a building ... purporting to indemnify or hold harmless the promisee against liability for damage arising out of bodily injury to persons ... caused by or resulting from the negligence of the promisee ... whether such negligence be in whole or in part, is against public policy and is void and unenforceable."
Thus, a subcontractor seeking to avoid enforcement of an indemnity agreement has the burden of proving that the indemnitee general contractor was "negligent to some degree." Brown v. Two Exch. Plaza Partners, 146 A.D.2d 129, 539 N.Y.S.2d 889 (1st Dept. 1989), aff'd 76 N.Y.2d 172, 556 N.Y.S.2d 991, 556 N.E.2d 430 (1990). Conversely, summary judgment may be granted to a contractor on its contractual indemnity claim against a subcontractor when there is no possibility that the contractor will be found actively negligent. See Warnett v A.J. Pegno Constr. Corp., 1 AD3d 207, 767 N.Y.S.2d 107 (1st Dept. 2003); see also Itri Brick & Concrete Corp. v. Aetna Cas. & Sur. Co., 89 N.Y.2d 786, 658 N.Y.S.2d 903, 680 N.E.2d 1200 (1997) (absent a finding of negligence on an indemnitee's behalf, an indemnity agreement would not run afoul of GOL [*6]5—322.1).

A general contractor may be held liable for negligence when it has actual or constructive notice of a dangerous condition and fails to take corrective action. See Mitchell v New York Univ., 12 AD3d 200, 200-201, 784 N.Y.S.2d 104, 106 (1st Dept. 2004). A defendant has constructive notice of a hazardous condition when a defect is visible and apparent and exists for a sufficient length of time prior to the accident to permit the defendant's employees to discover and remedy it. Gordon v. American Museum of Natural History, 67 N.Y.2d 836, 837-838, 501 N.Y.S.2d 646, 647, 492 N.E.2d 774, 775 (1986).

Here, Five Star contends that Plaza was negligent because it failed to "keep the hands of the other trades out of the electricians' work." Five Star further contends that Plaza had constructive notice of this "recurring hazardous condition," and failed to address it in a timely and reasonable manner. In support of this argument, Five Star relies primarily on the testimony of two electricians who were responsible for capping or taping the wires as well as the testimony of its foreman.

Five Star's general foreman testified that two or three days before the plaintiff's accident, he was asked to "energize" or provide permanent power to apartments on the first 11 floors of the building. He directed two electricians to put wire nuts or tape on the wires and turn on the power to the apartments. He instructed them to then turn on the circuit breakers for "the washer unit so the tile guy would have power to the washer outlet and operate his saw, and the lighting circuit, so they had light to perform their work." All other circuit breakers, including those in the bathrooms, were to be left off.

The foreman further testified that there was no ongoing problem with other subcontractors turning on electrical power before the plaintiff's accident. However, he acknowledged that on the night before the accident, he observed that some workers in some of the apartments had turned on electrical circuits without permission. He testified that he told those workers they could not do so, and that he reported the incident to Plaza. However, he did not identify the workers or the apartments.

The two electricians testified that they capped and taped the wires and activated the two circuits in each apartment as instructed. Both of them also testified as to seeing other tradesmen improperly turning on electrical power in certain apartments. However, neither electrician could identify the location of the apartments.

One electrician testified that she saw "other trades touching electrical breakers ... [a]lmost every day ... from the time [she] started." However, she could not remember when she worked at the project. The second electrician testified that some of the trades went into the panel to turn breakers on "once in a while."However, he could not say when this occurred with reference to the plaintiff's accident. Hence the testimony of the first electrician is inconsistent with that of the second, and the testimony of both electricians is inconsistent with that of the Five Star foreman.

More significantly, the vagueness of the testimony precludes any conclusion that a triable issue of fact exists as to Plaza's constructive notice. At best, the testimony imputes to Plaza only a general awareness of a potentially dangerous condition and it is well settled that a "general awareness" that a dangerous condition may be present is legally insufficient to constitute constructive notice of the particular condition that caused a plaintiff's accident. Piacquadio v. Recine Realty Corp., 84 N.Y.2d 967, 969, 622 N.Y.S.2d 493, 494, 646 N.E.2d 795, 796 (1994). Thus, vague testimony, which cannot establish the length of time a hazardous condition has existed, is insufficient to raise a triable issue of fact as to constructive notice. See e.g. [*7]Kobiashvilli v. Hill, 34 AD3d 747, 747-748, 828 N.Y.S.2d 68, 69 (2d Dept. 2006) ("appellant established its entitlement to judgment as a matter of law by submitting proof that the length of time for which the [defect] existed was unknown")(internal quotation marks omitted); Reilly v. Newireen Assoc., 303 A.D.2d 214, 756 N.Y.S.2d 192 (1st Dept. 2003), lv. denied 100 N.Y.2d 508, 764 N.Y.S.2d 235, 795 N.E.2d 1244 (2003) (testimony that a hoist broke down "periodically" or "twice a week" was too vague and unspecific to state a viable claim for negligent maintenance).

Nor, in my view, does Five Star raise an issue of fact as to notice by relying on its foreman's testimony as to his phone call to Plaza on the night before the accident. Actual notice "must call attention to the specific defect or hazardous condition and its specific location, sufficient for corrective action to be taken." Mitchell, 12 AD3d at 201, 784 N.Y.S.2d at 106 (emphasis added). Here, the foreman could not identify the workers who allegedly were turning on electrical power without authorization; nor could he identify the apartments, or the floors on which they were located.

Even assuming arguendo that the foreman's telephone phone call was sufficiently specific to provide Plaza with actual notice, there is no evidence that there was time for Plaza to take any concrete steps to remedy the hazardous condition. The only evidence concerning a remedy was testimony that after the accident locks were installed on each apartment's electric panel to ensure that only Five Star would have access to the circuit breakers. Not only did Five Star's foreman admit that this was not the standard practice in the industry, but Plaza, who was allegedly notified the night before the plaintiff's accident, could not have had time to have locks installed on every apartment panel in the 42-story building when work began at 7 the following morning and the plaintiff was injured at 7:15 a.m.

THIS CONSTITUTES THE DECISION AND ORDER
OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

ENTERED: DECEMBER 13, 2012

CLERK

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.