PENTECOSTAL ASSEMBLIES OF GOD CHURCH, v. ARCHER & GREINER

Annotate this Case
NOT FOR PUBLICATION WITHOUT THE
                      APPROVAL OF THE APPELLATE DIVISION
     This opinion shall not "constitute precedent or be binding upon any court."
      Although it is posted on the internet, this opinion is binding only on the
        parties in the case and its use in other cases is limited. R. 1:36-3.




                                       SUPERIOR COURT OF NEW JERSEY
                                       APPELLATE DIVISION
                                       DOCKET NO. A-5613-15T3

PENTECOSTAL ASSEMBLIES OF GOD
CHURCH, a non-profit religious
corporation,

        Plaintiff-Appellant,

v.

ARCHER & GREINER, and
ROBERT W. BUCKNAM, JR., ESQUIRE,

        Defendants/Third-Party
        Plaintiffs-Respondents,

v.

ESTATE OF NORMAN G. MORRELL, DECEASED,
and PANNA CONSTRUCTION CO.,

        Third-Party Defendants.


              Submitted December 12, 2017 – December January 10, 2018

              Before Judges Carroll and Leone.

              On appeal from Superior Court of New Jersey,
              Law Division, Atlantic County, Docket No. L-
              1531-14.

              Peter A. Ouda, LLC, attorneys for appellant
              (Peter A. Ouda, on the brief).
            Archer   &   Greiner,   PC,   attorneys   for
            respondents (Ellis I. Medoway, on the brief).

PER CURIAM

     Plaintiff Pentecostal Assemblies of God Church (PAG) appeals

from the July 14, 2016 summary judgment dismissal of its legal

malpractice action against defendants Archer & Greiner, PC and

Robert W. Bucknam, Jr.,1 Esquire.         The trial court found PAG's

claims were precluded by the doctrine of collateral estoppel.             We

affirm.

     The motion record reflects that PAG purchased vacant land in

Hammonton in 1997, for the purpose of constructing a church there.

PAG contracted with Aqua Terra, P.A. (Aqua Terra), an engineering

firm, to design a preliminary site plan to obtain a use variance

for the church construction.        PAG also retained defendants to

represent it in the site plan approval process.           Aqua Terra was

an existing client of Archer & Greiner, and recommended Bucknam

to PAG.    PAG obtained the use variance approval in 1998.

     On June 10, 1998, PAG entered into a second contract with

Aqua Terra to prepare a proposed preliminary and final site plan

for submission to various agencies, including the Hammonton Zoning

Board,    Atlantic   County   Planning   Board,   New   Jersey   Pinelands



1
  Defendant's name is misspelled in the caption and at various
points in the record as Robert W. Buckman, Jr.

                                    2                              A-5613-15T3
Commission, and the regional Soil Conservation District.          The

agreed price was $7000, which did not "includ[e] services normally

performed during the bidding, construction, and operational phases

of a project."    The contract further specified:

            The sole purpose for the preparation of the
            plans associated with this PROJECT is to
            secure development approval from certain
            governmental agencies as agreed between [PAG]
            and [Aqua Terra]. They are not intended to
            be used as formal contract documents.    Such
            use by anyone shall not be interpreted to
            imply any contractual relationship between
            that person and [Aqua Terra] for professional
            services involved in the construction of the
            improvements shown on these plans, unless
            there is a formal written agreement between
            that person and [Aqua Terra] to provide those
            services.

                 . . . .

            Any reuse without written verification or
            adaptation by [Aqua Terra] for the specific
            purpose intended will be at [PAG's] sole risk
            and without liability or legal exposure to
            [Aqua Terra] . . . and [PAG] shall indemnify
            and hold harmless [Aqua Terra] . . . from all
            claims, damages, losses and expenses including
            attorneys' fees arising out of or resulting
            therefrom.

At his deposition, PAG's pastor, Alberto Torres, agreed with

testimony previously given by Aqua Terra's representative that

Bucknam had no input with respect to the terms or language of the

contract.




                                  3                          A-5613-15T3
     After the approvals were obtained, PAG began construction of

the church in 2003, and completed it in 2004.                  PAG used Aqua

Terra's site plans as contract documents with the builder, Panna

Construction (Panna), to construct the improvements shown on the

plans.

     In March 2010, PAG began experiencing issues with water

infiltration in the church basement.              Consequently, in November

2010, PAG filed suit against Panna, the estate of the project

architect,     Norman    Morrell,    and   Aqua     Terra,    alleging     water

infiltration    and     structural   damages    arising      from   design    and

construction deficiencies in the church construction (the previous

action).

     PAG    subsequently     settled   its     claims   against     Panna     and

Morrell's    estate.      PAG   continued    to    assert    its    claims    for

professional negligence and breach of contract against Aqua Terra,

based on PAG's allegation that the engineer identified the seasonal

high ground water elevation (SHGWE) four feet below its actual

level.     Plaintiff contended that, when Aqua Terra's plans were

used in the construction phase, this misidentification caused the

building to be built below the SHGWE and rendered it subject to

flooding.

     In May 2013, the trial court granted summary judgment in

favor of Aqua Terra.        In a thirteen-page written opinion, Judge

                                       4                                 A-5613-15T3
James E. Isman first found that PAG's suit was barred by the

express terms of its contract with Aqua Terra:

                   In essence, [p]laintiff argues that by
              its unilateral misuse of the [p]erfected
              [s]ite [p]lans as construction contract
              documents, Aqua Terra had a duty to ensure
              that the [p]erfected [s]ite [p]lans contained
              the level of detail necessary to be used as
              construction    contract   documents    despite
              [PAG's] unwillingness to pay for those
              additional services. However . . . such an
              interpretation is clearly contrary to the
              clear language of the contract. . . .       The
              contract   specifically    and   unambiguously
              stated that additional engineering, design and
              construction details were required to generate
              construction contract documents. This [c]ourt
              cannot   overlook    the   fact   that    [PAG]
              intentionally and affirmatively elected not to
              pay for such additional services . . . . There
              is simply no theory of law under which [PAG]
              can establish that by [PAG's] unilateral
              misuse of the site plans, Aqua Terra undertook
              a duty to ensure that the plans contained the
              level of detail necessary to be used as
              construction documents, particularly given
              [PAG's] unwillingness to pay for those
              additional services.

    As a second basis for granting summary judgment, Judge Isman

found   PAG    could   not   establish       that   any   of   its   damages   were

proximately caused by Aqua Terra's professional negligence.                     The

judge elaborated:

              As argued by [Aqua Terra], [PAG's] own
              expert's   report   and   testimony   supports
              granting summary judgment in [Aqua Terra's]
              favor.    [PAG's] expert, Gregory S. Baker,
              P.E., has conceded that the basement has never
              experienced more than a few inches of water

                                         5                                A-5613-15T3
          on the basement floor. Notably, [PAG] has not
          alleged any damage from groundwater being four
          feet higher than that which they have
          experienced. Additionally, [PAG's] expert has
          opined that the flooding occurred because the
          architect, Norman G. Morrell (deceased),
          failed to specify that the basement floor and
          walls had to be waterproofed.     Furthermore,
          [PAG's] expert concedes that Aqua Terra's
          identification of the SHGWE being at the same
          elevation of the basement floor was sufficient
          notice to the architect, Norman Morrell, to
          require him to specify that the basement floor
          and walls be waterproofed.       However, Mr.
          Morrell failed to specify that the basement
          floor and walls be waterproofed. Furthermore,
          even [PAG's] expert opines that had the
          basement floor and walls been properly
          waterproofed and the perimeter drain properly
          located,   the   basement   would   not   have
          experienced any flooding. As such, [PAG] has
          failed to allege any damage that could have
          been proximately caused by Aqua Terra's
          failure to identify the SHGWE four feet
          higher.

     PAG commenced the present malpractice action on April 7,

2014, alleging defendants "should have known that [PAG] could not

proceed with construction based on the site plans of Aqua Terra,"

and that defendants "specifically advised [PAG] that it could

proceed with construction based on Aqua Terra's documents." During

discovery,   PAG   presented   a   four-page   report   from   its    expert

witness, an attorney, who distilled the malpractice claim into the

following:

          [The June 10, 1998] contract should have been
          discussed with the client PAG in detail so
          that [PAG] fully understood the risks of using

                                     6                               A-5613-15T3
         the documents beyond what was permitted in the
         . . . contract. . . .     In the exercise of
         reasonable care, [Archer & Greiner] should
         have advised PAG not to use the documents as
         construction documents and should have advised
         [PAG] further to make contact with Aqua Terra
         to ascertain the costs and timing to obtain
         documents that could be used as "formal
         contract documents."

    At the conclusion of discovery, defendants moved for summary

judgment, arguing that (1) PAG's claims were precluded by the

doctrine of collateral estoppel, and (2) PAG failed to produce an

expert engineering report to support its claim that Aqua Terra's

negligence led to the water infiltration in the church basement.

    Judge Noah Bronkesh dismissed the malpractice complaint,

finding the following:

         When all facts are viewed in the light most
         favorable   to   the  non—moving   party,   no
         questions of material fact remain.         The
         princip[le] of collateral estoppel precludes
         [relitigation] of the same issue.        [PAG]
         concedes [defendants'] statement of material
         facts, including that Judge Isman determined
         in the previous action that the engineer was
         entitled to summary judgment because [PAG]
         could not establish that any of the alleged
         damages caused by the water infiltration were
         proximately caused by the engineer. [PAG's]
         "Counterstatement of Material Facts" are
         unavailing because none of those facts touch
         upon Judge Isman's factual finding that the
         engineer was not the proximate cause for the
         water damage sustained by the Church's
         building. The proximate cause issue was fully
         and fairly litigated by [PAG] before Judge
         Isman and his decision bars the [relitigation]
         of that fact issue in this case. This [c]ourt

                               7                          A-5613-15T3
          finds that under the princip[le] of collateral
          estoppel, [d]efendants are entitled to summary
          judgment.

This appeal followed.

     When reviewing the grant of summary judgment, we analyze the

decision applying the "same standard as the motion judge."     Globe

Motor Co. v. Igdalev, 
225 N.J. 469, 479 (2016) (quoting Bhagat v.

Bhagat, 
217 N.J. 22, 38 (2014)).

          That standard mandates that summary judgment
          be granted "if the pleadings, depositions,
          answers to interrogatories and admissions on
          file, together with the affidavits, if any,
          show that there is no genuine issue as to any
          material fact challenged and that the moving
          party is entitled to a judgment or order as a
          matter of law."

          [Templo Fuente De Vida Corp. v. Nat'l Union
          Fire Ins. Co., 
224 N.J. 189, 199 (2016)
          (quoting R. 4:46-2(c)).]

     "To defeat a motion for summary judgment, the opponent must

'come forward with evidence' that creates a genuine issue of

material fact."   Cortez v. Gindhart, 
435 N.J. Super. 589, 605

(App. Div. 2014) (quoting Horizon Blue Cross Blue Shield of N.J.

v. State, 
425 N.J. Super. 1, 32 (App. Div. 2012)), certif. denied,


220 N.J. 269 (2015).    "[C]onclusory and self-serving assertions

by one of the parties are insufficient to overcome the motion."

Puder v. Buechel, 
183 N.J. 428, 440-41 (2005) (citations omitted).

"When no issue of fact exists, and only a question of law remains,


                                8                            A-5613-15T3
[we] [afford] no special deference to the legal determinations of

the trial court."   Templo Fuente De Vida, 
224 N.J. at 199 (citing

Manalapan Realty, L.P. v. Twp. Comm. of Manalapan, 
140 N.J. 366,

378 (1995)).

     To establish legal malpractice, PAG was

          required to show that competent, credible
          evidence existed to support each of the
          elements of that negligence action, i.e., "1)
          the   existence    of   an    attorney-client
          relationship creating a duty of care upon the
          attorney; 2) that the attorney breached the
          duty owed; 3) that the breach was the
          proximate cause of any damages sustained; and
          4) that actual damages were incurred."

          [Cortez, 
435 N.J. Super. at 598 (quoting
          Sommers v. McKinney, 
287 N.J. Super. 1, 9-10
          (App. Div. 1996)).]

     With respect to the third factor, "an attorney is only

responsible for a client's loss if that loss is proximately caused

by the attorney's legal malpractice[,]" that is, "the negligent

conduct is a substantial contributing factor in causing the loss."

2175 Lemoine Ave. Corp. v. Finco, Inc., 
272 N.J. Super. 478, 487

(App. Div. 1994).    Therefore, a plaintiff bears the burden of

showing, by a preponderance of the competent, credible evidence,

"what injuries were suffered as a proximate consequence of the

attorney's breach of duty." Id. at 488 (citing Lieberman v. Emp'rs

Ins. of Wausau, 
84 N.J. 325, 341 (1980)).      The burden is not

satisfied by mere "conjecture, surmise or suspicion."        Ibid.

                                 9                         A-5613-15T3
(quoting Long v. Landy, 
35 N.J. 44, 54 (1961)).       Ordinarily, the

measure of damages is what result the client would have obtained

in the absence of attorney negligence.     Garcia v. Kozlov, Seaton,

Romanini & Brooks, P.C., 
179 N.J. 343, 358 (2004).     Thus, to prove

such injury, "the client must demonstrate that he or she would

have prevailed, or would have won materially more . . . but for

the alleged substandard performance."     Lerner v. Laufer, 
359 N.J.

Super. 201, 221 (App. Div. 2003).

     "[C]ollateral   estoppel,    or   issue   preclusion,   bars   the

relitigation of an issue that has already been addressed in a

prior matter . . . ."   Bondi v. Citigroup, Inc., 
423 N.J. Super.
 377, 423 (App. Div. 2011).       That is, whereas res judicata, or

claim preclusion, bars relitigation of already adjudicated claims

between the same parties or their privies, collateral estoppel

"bars relitigation of issues in suits that arise from different

causes of action."    Selective Ins. Co. v. McAllister, 
327 N.J.

Super. 168, 173 (App. Div. 2000) (citing United Rental Equip. Co.

v. Aetna Life and Cas. Ins. Co., 
74 N.J. 92, 101 (1977)).

     Collateral estoppel requires a party to establish:

          (1) the issue to be precluded is identical to
          the issue decided in the prior proceeding; (2)
          the issue was actually litigated in the prior
          proceeding; (3) the court in the prior
          proceeding issued a final judgment on the
          merits; (4) the determination of the issue was
          essential to the prior judgment; and (5) the

                                 10                            A-5613-15T3
           party against whom the doctrine is asserted
           was a party to or in privity with a party to
           the earlier proceeding.

           [First Union Nat'l Bank v. Penn Salem Marina,
           Inc., 
190 N.J. 342, 352 (2007) (citing
           Hennessey v. Winslow Twp., 
183 N.J. 593, 599
           (2005)).]

      Here, in the previous action, PAG did not establish that any

professional negligence by Aqua Terra was the proximate cause of

its water damage because it was the architect who failed to specify

that the basement floor and walls be waterproofed.             PAG had a full

and fair opportunity to litigate that issue in the prior action,

and was unsuccessful in establishing Aqua Terra's liability for

the water infiltration.          We thus agree with Judge Bronkesh that

the   doctrine     of   collateral         estoppel   precluded    PAG      from

relitigating that issue in the malpractice action.             Consequently,

to the extent PAG alleged that defendants negligently failed to

review Aqua Terra's contract and documents, PAG was similarly

unable to establish that such failure caused PAG damage.                 Stated

differently,     because   the    architect's    negligence,    and   not   the

engineer's negligence, proximately caused PAG's water damage, PAG

cannot show it suffered loss as a consequence of defendants'




                                      11                              A-5613-15T3
alleged failure to properly advise PAG regarding the use of the

engineer's plans.2

      PAG contends the water damage was only one part of its damages

in the malpractice action.       PAG relies upon its legal expert to

establish that "the measure [of] damages would be all of the costs

and fees associated with the purchase of the property and all of

the   professional   fees   associated    with   the    approval    process."

However, the expert offered no basis for this opinion other than

defendants'    failure      to   prevent     the       engineer's     alleged

negligence.   However, in the prior action PAG failed to establish

any negligence by the engineer.          Hence, collateral estoppel was

properly applied to dismiss the malpractice action.

      Affirmed.




2
  Because we share the trial court's view that the doctrine of
collateral estoppel barred PAG's legal malpractice action, we need
not reach defendants' second argument that dismissal was also
proper due to PAC's failure to present an appropriate engineering
expert in the malpractice action.

                                   12                                 A-5613-15T3


Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.