Korte Construction Co. v. State, Board of Regents
Annotate this Case
In this opinion, the Supreme Court clarified that the existence of a bond pursuant to Nev. Rev. Stat. 108.2415 precluded a contractor's ability to maintain a claim for unjust enrichment against the property owner because the subject of the dispute was governed by an express, written contract.
University entered into an agreement with Lessee providing that University would purchase certain real property and lease it to Lessee, whereby Lessee would fund and construct student housing and other establishments. Lessee subsequently entered into a construction contract with Contractor. When a dispute arose between Contractor and Lessee, Contractor recorded a mechanics' lien against the property and filed a complaint against several defendants, including a claim against University for unjust enrichment. The district court granted summary judgment in favor of University. The Supreme Court affirmed, holding that the bond provided an adequate remedy at law and that the unjust enrichment claim was improper.
Sign up for free summaries delivered directly to your inbox. Learn More › You already receive new opinion summaries from Supreme Court of Nevada. Did you know we offer summary newsletters for even more practice areas and jurisdictions? Explore them here.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.