In re Application of City of Neligh
Annotate this CaseThe Supreme Court reversed the decision of the Nebraska Power Review Board (Board) transferring two newly annexed territories from the Elkhorn Rural Public Power District (ERPPD) to the City of Neligh’s electrical service area and assessing the economic impact at $490,445.90. At issue on appeal was what compensation was owed to ERPPD for reintegration costs under Neb. Rev. Stat. 70-1010(2)(b). The Court held that the Board’s actions were arbitrary, capricious, and unreasonable because the Board erred in failing to award compensation for reintegration costs under section 70-1010(2)(b) to ERPPD for the lost substation unit.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.