In re Application of Neb. Pub. Power Dist.
Annotate this Case
Download PDF
Nebraska Advance Sheets
350
281 nebraska reports
In
re
Application of Nebraska Public Power District.
James Choquette et al., appellants,
v. Nebraska P ublic Power
District, appellee.
___ N.W.2d ___
Filed April 15, 2011.
No. S-10-707.
1. Nebraska Power Review Board: Appeal and Error. A decision of the Nebraska
Power Review Board will be affirmed if it is supported by the evidence and is not
arbitrary, capricious, unreasonable, or otherwise illegal.
2. Judgments: Statutes: Appeal and Error. Statutory interpretation is a matter of
law in connection with which an appellate court has an obligation to reach an
independent, correct conclusion irrespective of the determination made by the
trial court.
3. Nebraska Power Review Board: Electricity. The Nebraska Power Review
Board is required under Neb. Rev. Stat. § 70-1014 (Reissue 2009) to determine
whether the applicant before it can economically and feasibly supply the electric
service resulting from the proposed construction.
4. Nebraska Power Review Board: Administrative Law. The Nebraska Power
Review Board, as an administrative board, has no power or authority other than
that specifically conferred upon it by statute or by construction necessary to
accomplish the purpose of the act.
5. Administrative Law: Due Process. In administrative agency decisions, due proc
ess requires neutral and unbiased decisionmakers.
6. Administrative Law: Presumptions. Administrative decisionmakers serve with
a presumption of honesty.
7. Administrative Law: Due Process. Although due process requires disqualification when an administrative adjudicator has actually prejudged the precise facts
at issue, due process does not require the disqualification of one who has merely
been exposed to or investigated the facts at issue.
Appeal from the Power Review Board. Affirmed.
Adam D. Pavelka, of Sullivan, Shoemaker, Witt & Burns,
P.C., L.L.O., for appellants.
John C. McClure and Bonnie J. Hostetler, of Nebraska Public
Power District, and Kile W. Johnson and Cameron E. Guenzel,
of Johnson, Flodman, Guenzel & Widger, for appellee.
Heavican, C.J., Connolly, Gerrard, Stephan, McCormack,
and Miller-Lerman, JJ., and Cassel, Judge.
Nebraska Advance Sheets
in re application of neb. pub. power dist.
Cite as 281 Neb. 350
351
Miller-Lerman, J.
NATURE OF CASE
The Nebraska Public Power District (NPPD) filed an application with the Nebraska Power Review Board (PRB) requesting authorization to construct an electric transmission line.
A group of people who described themselves as residents
and owners of farms and ranches in close proximity to the
proposed line filed a protest and were permitted to intervene.
The PRB granted NPPD’s application. The protestors appeal.
We affirm.
STATEMENT OF FACTS
On March 3, 2010, NPPD filed application PRB-3617 with
the PRB, seeking authority to construct an approximately 53mile, 345-kilovolt transmission line in Kearney and Franklin
Counties, Nebraska. The construction would be part of a project to build a 225-mile transmission line from NPPD’s Axtell,
Nebraska, substation to Spearville, Kansas. The remainder
of the transmission line would be built in Kansas by another
company. NPPD asserted that the purpose of the project was
to relieve system congestion on the transmission grid in western Nebraska and western Kansas and that the project would
enable more efficient utilization of NPPD facilities and benefit
NPPD customers with low rates and enhanced system reliability. Construction of the project was planned to commence
in the winter of 2011 to 2012, to be completed by December
2012, and to cost approximately $78 million.
Several people who described themselves as residents and
owners of farms and ranches located in close proximity to the
proposed transmission line filed a protest and petition for intervention. The petition to intervene was granted. The protestors
asserted that the line would not serve the public convenience
and necessity of Nebraskans and that NPPD would not most
economically and feasibly supply electric service resulting
from the line. They asserted that the line would primarily benefit the interests of Kansas and that NPPD and its customers
would bear a disproportionate amount of the costs of the transmission line project.
Nebraska Advance Sheets
352
281 nebraska reports
The PRB held a hearing on NPPD’s application on May 14,
2010. NPPD presented the testimony of three witnesses who
were NPPD employees and offered numerous exhibits into
evidence. The protestors presented the testimony of two witnesses: one of the protestors and a consultant with knowledge
of engineering issues related to powerlines. The protestors
offered several exhibits into evidence.
Following the hearing, the PRB approved NPPD’s application. In an 18-page order dated June 14, 2010, with citations to
the record of the hearing, the PRB made the following findings:
Southern Power District, in whose service area the proposed
line would be located, had consented to approval of NPPD’s
application. After required consultations with the Nebraska
Game and Parks Commission and the U.S. Fish and Wildlife
Service, NPPD selected the easternmost of the alternate routes
it was considering for the location of the line, because that
route would pose the least threat to endangered species and
the species’ habitats. The Game and Parks Commission and the
U.S. Fish and Wildlife Service did not object to the selected
route but would have objected to the other proposed routes. It
was estimated that selecting the easternmost route to accommodate such concerns increased the cost of the project by at
least $14 million.
The PRB further found that with the installation of the
proposed transmission line, NPPD would have excess baseload generating capacity that it could sell and the proposed
transmission line would remove constraints preventing NPPD
from moving most or all of its excess power to the market. The
sale of excess power would reduce costs for NPPD ratepayers.
The proposed transmission line would also facilitate NPPD’s
ability to purchase electricity when needed. The increased
revenue from sales of excess power and the ability to purchase
electricity when needed were expected to offset the cost to
build the line. The PRB further found that the transmission
line would relieve congestion in western Nebraska and western
Kansas, relieve constraints by increasing transfer capability
and reducing loading on NPPD’s transmission system in central and eastern portions of Nebraska, and provide additional
reliability in NPPD’s transmission system for ratepayers in
Nebraska Advance Sheets
in re application of neb. pub. power dist.
Cite as 281 Neb. 350
353
western and south central Nebraska. The congestion that NPPD
would relieve by building the transmission line could not be
economically relieved by Omaha Public Power District or the
Lincoln Electric System.
The PRB finally found that although the proposed transmission line would provide benefits to Kansas interests, serving
those interests would not be the primary purpose of the line.
The PRB found little or no evidence that the proposed transmission line would cause electricity generated in Kansas wind
farms to be sold in Nebraska. In this regard, the PRB noted
that NPPD had its own wind generation resources and access
to areas in Nebraska with “good wind potential.”
The PRB addressed the protestors’ concerns about the route
of the transmission line. The protestors claimed that the route
was wasteful and chosen for the convenience of the Kansas
power company. The PRB relied on Lincoln Electric System v.
Terpsma, 207 Neb. 289, 298 N.W.2d 366 (1980), for the proposition that the utility rather than the PRB had the authority to
select a particular route and that the PRB’s authority was limited to either approving or disapproving the utility’s application. The PRB noted that NPPD selected the easternmost route
of the variations it had been considering because it posed the
least threat to endangered species and that if NPPD had chosen
one of the other routes, the PRB would have been constrained
to deny the application on the ground that the transmission line
threatened endangered species.
The PRB found:
[T]he evidence shows the proposed transmission line will
serve the public convenience and necessity[,]
. . . the evidence demonstrates that [NPPD] can most
economically and feasibly supply the electric service
resulting from the proposed transmission line[,]
[and] the evidence demonstrates that the proposed
transmission line will not unnecessarily duplicate other
facilities or operations.
The PRB therefore approved NPPD’s application designated as
PRB-3617.
The protestors appeal the PRB’s decision.
Nebraska Advance Sheets
354
281 nebraska reports
ASSIGNMENTS OF ERROR
The protestors claim, restated and summarized, that the PRB
erred when it approved NPPD’s application. The protestors also
claim that the PRB was biased and made findings in favor of
NPPD before the conclusion of the hearing.
STANDARDS OF REVIEW
[1] A decision of the PRB will be affirmed if it is supported
by the evidence and is not arbitrary, capricious, unreasonable,
or otherwise illegal. In re Application of City of North Platte,
257 Neb. 551, 599 N.W.2d 218 (1999).
[2] Statutory interpretation is a matter of law in connection
with which an appellate court has an obligation to reach an
independent, correct conclusion irrespective of the determination made by the trial court. State ex rel. Wagner v. Gilbane
Bldg. Co., 280 Neb. 223, 786 N.W.2d 330 (2010).
ANALYSIS
The PRB Did Not Err When It Found That NPPD Could Most
Economically and Feasibly Supply the Electric Service
Resulting From the Proposed Construction.
On appeal, the protestors assert that the PRB erred when it
approved NPPD’s application, because (1) NPPD’s evidence
failed to show “how the proposed transmission line compared
to other alternatives” and was the most economic and feasible
route, brief for appellants at 5, and (2) the PRB “took NPPD
at its word with regard to what was the most economic or
beneficial route” and failed to draw its own conclusion, id.
at 8. We conclude that the protestors’ first argument fails primarily because it is based on a misreading of the controlling
statute, Neb. Rev. Stat. § 70-1014 (Reissue 2009), and that
the second argument fails because it is based on a misunderstanding of the scope of the PRB’s authority with respect
to applications.
Section 70-1014 is central to our resolution of this appeal.
Section 70-1014 provides that before the PRB can approve an
application for construction of an electric generation facility
or transmission line, the PRB “shall find that the application will serve the public convenience and necessity, and that
Nebraska Advance Sheets
in re application of neb. pub. power dist.
Cite as 281 Neb. 350
355
the applicant can most economically and feasibly supply the
electric service resulting from the proposed construction or
acquisition, without unnecessary duplication of facilities or
operations.”
The PRB’s task in § 70-1014 furthers “the policy of this
state to avoid and eliminate conflict and competition between
public power districts [and other public utility entities] in
furnishing electric energy to retail and wholesale customers
[and] to avoid and eliminate the duplication of facilities and
resources which result therefrom.” Neb. Rev. Stat. § 70-1001
(Reissue 2009).
A final action of the PRB may be appealed to the appellate courts of this state. Neb. Rev. Stat. § 70-1016 (Reissue
2009). A decision of the PRB will be affirmed if it is supported
by the evidence and is not arbitrary, capricious, unreasonable, or otherwise illegal. In re Application of City of North
Platte, supra.
In connection with their insufficiency of the evidence argument, the protestors do not dispute the PRB’s finding that
NPPD’s evidence satisfied the first portion of § 70-1014 and
showed that the proposed transmission line “will serve the public convenience and necessity.” Instead, the protestors focus on
the second portion of § 70-1014 regarding whether “the applicant can most economically and feasibly supply the electric
service resulting from the proposed construction” and claim
that because NPPD’s evidence failed to establish this second
requirement, approval was not warranted. This argument misreads the statute and is without merit.
In making their insufficiency of the evidence argument, the
protestors focus on the word “most” in § 70-1014 and assert
that “most” is intended to describe the route identified in the
application. According to the protestors’ reading of § 70-1014,
the PRB is required to find that the proposed transmission line
is the “most” economic and feasible route and such determination can only be done after comparing the proposal to alternative routes. We reject this argument. We give the language of
§ 70-1014 its plain and ordinary meaning, see Ricks v. Vap, 280
Neb. 130, 784 N.W.2d 432 (2010), and a sensible construction,
Nebraska Advance Sheets
356
281 nebraska reports
see Walton v. Patil, 279 Neb. 974, 783 N.W.2d 438 (2010).
We conclude that “most” describes the word “applicant,” the
protestors misread § 70-1014, and the PRB correctly applied
§ 70-1014 to the facts of this case.
According to the plain language of § 70-1014, the PRB
must first find that the application will serve the public convenience and necessity and then determine if the applicant
can most economically and feasibly supply the resulting serv
ice. The word “most” qualifies the word “applicant,” not the
route in the application. Having found public convenience and
necessity, the inquiry then proceeds to focus on the applicant
and its ability to economically and feasibly provide the proposed service.
[3] We recognize that the comparative word “most” has its
greatest application where there are competing applicants. See,
e.g., City of Auburn v. Eastern Nebraska Public Power Dist.,
179 Neb. 439, 138 N.W.2d 629 (1965) (reviewing PRB’s decision with regard to two competing applicants, City of Auburn
and Eastern Nebraska Public Power District). We acknowledge
that in the absence of competing applicants, the comparative
word “most” in § 70-1014 is awkward. However, pursuant
to § 70-1014, the PRB must nevertheless complete its task
of evaluating an application regardless of whether competing
applications by competing applicants exist. Giving § 70-1014
a sensible reading, we reject the protestors’ argument that the
PRB was tasked with finding the “most” economic and feasible
route. Instead, the PRB was required under § 70-1014 to determine whether the applicant it had before it could economically
and feasibly supply the electric service resulting from the proposed construction which it had found would serve the public
convenience and necessity.
[4] Our reading of § 70-1014 is consistent with prior decisions of this court. In Lincoln Electric System v. Terpsma, 207
Neb. 289, 291-92, 298 N.W.2d 366, 368 (1980), we noted that
the PRB, as an administrative board, had “no power or authority other than that specifically conferred upon it by statute or
by construction necessary to accomplish the purpose of the
act.” And we concluded that the PRB had “no authority to
select a particular route other than that selected by the utility.”
Nebraska Advance Sheets
in re application of neb. pub. power dist.
Cite as 281 Neb. 350
357
Id. at 292, 298 N.W.2d at 368. We further stated that “[t]here
is nothing in the pertinent statutes to suggest that the [PRB]
has the power to determine that a transmission line shall be
built along a particular route.” Id. at 291, 298 N.W.2d at 368.
The protestors’ suggestion that the PRB affirmatively investigate other possible routes is contrary to the statute and the
case law.
With respect to the sufficiency of the evidence, the record
shows that Southern Power District, in whose service area the
proposed transmission line would be built, had consented to
approval of the application and stipulated that NPPD could
most economically and feasibly supply the service. There
was also evidence that general notice of the application had
been given through newspapers in the area and that specific
notice of the filing had been given to one other potential supplier, the city of Minden, Nebraska. No other potential supplier filed a protest or a competing application. We also note
that in its order, the PRB considered whether Omaha Public
Power District or Lincoln Electric System might be appropriate entities to build a transmission line to alleviate congestion
in the area and concluded that neither of those utilities was
sufficiently impacted by the congestion such that it would be
economical for either of them to construct a line. The PRB
noted that in contrast to these two entities, NPPD owned and
operated transmission lines in the surrounding area, had crews
in the area, and was directly impacted by the constraint. The
foregoing suggests that even in the absence of competing
applications, the PRB gave consideration to potential other
applicants and determined that NPPD could “most economically and feasibly supply the electric service resulting from the
proposed transmission line.”
As an additional argument, the protestors claim that “the
PRB simply took NPPD at its word with regard to what was
the most economic or beneficial route for the proposed transmission line” and failed to draw its own conclusion. Brief for
appellants at 8. The protestors further suggest that we adopt
standards from federal cases not repeated here to the effect
that an administrative agency must exercise its own judgment
and not cede deference to a private party on matters before the
Nebraska Advance Sheets
358
281 nebraska reports
agency. Given our statutes, these authorities are inapposite. We
reject these arguments.
As discussed above, the PRB did not have the authority to
substitute its selection of a route in lieu of NPPD’s proposal.
Lincoln Electric System v. Terpsma, supra. See § 70-1014.
Instead, the PRB was to determine whether NPPD could economically and feasibly supply the service, and after examination, the PRB determined that NPPD could. The protestors’
argument is without merit.
In accordance with our standard of review, we conclude
that there was evidence to support PRB’s decision to approve
NPPD’s application and that such decision was not arbitrary,
capricious, unreasonable, or otherwise illegal.
The Record Does Not Indicate Bias
on the Part of the PRB.
The protestors assert that the PRB decision should be reversed
because the PRB made findings in favor of NPPD before the
conclusion of the hearing. They assert that “certain members of
the PRB had already made their mind up about certain facts and
that they had already drawn conclusions regarding the application.” Brief for appellants at 8-9. They argue that the PRB’s
decision cannot be affirmed, because members of the PRB
showed “extreme bias” and “great deference and bias to NPPD
and NPPD’s initiatives, making the hearing inherently unfair”
for the protestors. Id. at 9. As examples of the PRB’s alleged
bias, the protestors refer us to one member’s questioning of the
protestors’ witness and another member’s expression of knowledge and opinion regarding wind energy. We find no merit to
this assignment of error.
[5-7] We have recognized that in administrative agency
decisions, due process requires neutral and unbiased decision
makers. See Barnett v. City of Scottsbluff, 268 Neb. 555, 684
N.W.2d 553 (2004). Factors which may indicate partiality
include a pecuniary interest in the outcome, a familial or
adversarial relationship with one of the parties, and a failure
to disclose a suspect relationship. See id. We have recognized
that administrative decisionmakers serve with a presumption
of honesty. See id. And “[a]lthough due process requires
Nebraska Advance Sheets
in re application of neb. pub. power dist.
Cite as 281 Neb. 350
359
disqualification when the administrative adjudicator has actually prejudged the precise facts at issue, due process does
not require the disqualification of one who has merely been
exposed to or investigated the facts at issue.” Central Platte
NRD v. State of Wyoming, 245 Neb. 439, 466, 513 N.W.2d
847, 865 (1994).
As an initial matter, the record does not show that the protestors sought to disqualify any decisionmakers. We do not
read the identified portions of the record as indicating that
members of the PRB either were biased, appeared to be biased,
or had prejudged the application. Instead, the questioning of
witnesses by the PRB indicated critical examination of testimony which included an opportunity for witnesses to provide
explanations for what might be considered weaknesses in the
protestors’ position. While the expression by PRB members of
knowledge or opinion regarding matters related to the application might not have been necessary to the hearing, it indicates
the knowledge of the power industry a PRB member would
necessarily develop rather than indicating bias on the part of
the PRB member. We find no basis in the record to support the
protestors’ assertion of bias.
CONCLUSION
We conclude that there was evidence to support PRB’s decision to approve NPPD’s application PRB-3617 and that such
decision was not arbitrary, capricious, unreasonable, or otherwise illegal. The record does not support the protestors’ claim
that the PRB was biased in NPPD’s favor. We therefore affirm
the decision of the PRB to grant NPPD’s application.
Affirmed.
Wright, J., not participating.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.