ANDERSON v HOBBS

Annotate this Case
Download PDF
No. 81-97 IN THE SUPREME COURT OF THE STATE OF MONTANA 1981 LEN ANDERSON, d/b/a LEN ANDERSON CONSTRUCTION COMPANY, Plaintiff and Respondent, NORMAN D. HOBBS, individually and NORMAN D. HOBBS, d/b/a C. D. VENTURES, Defendant and Appellant. Appeal from: District Court of the Fifth Judicial District, In and for the County of Beaverhead. Honorable Frank Blair, Judge presiding. Counsel of Record: For Appellant: Harrison, Loendorf and Poston, Helena, Montana For Respondent: Drysdale, McLean, Screnar & Cok, Bozeman, Montana Submitted on briefs: August 27, 1981 Filed: gkc. - 'T [h!8;i Clerk Mr. Justice John Conway Harrison delivered the Opinion of the Court. This appeal arises from a contract for construction on appellant's nursing home in Dillon, Montana. The parties entered into the written agreement in January 1977, and the work was completed sometime in the late summer of 1977. Respondent filed a mechanics' lien against appellant's property on October 19, 1977. After trial without a jury, the District Court of the Fifth Judicial District upheld the lien and issued a judgment for $15,687.92 plus interest and attorney fees. This appeal followed. In December respondent, 1976, at the request of appellant, a general contractor doing business as Len Anderson Construction Co., a sole proprietorship, began work on Park View Acres in Dillon, Montana, a nursing home owned by appellant, Norman D. Hobbs, doing business as C. D. Ventures. In January 1977 the parties entered into a written contract whereby respondent would renovate the existing fifty-four-bed facility of Park View Acres and add a fiftyfour-bed wing to the building. The contract provided appel- lant would pay respondent all costs plus an eight percent contractor's fee. Costs included all costs necessarily incurred in the proper performance of work paid by the contractor; all wages paid for labor in the direct employ of the contractor; all salaries of contractor's employees; a portion of reasonable transportation, traveling and hotel expenses of the contractor, its officers and employees incurred in the discharge of their duties; the cost of all materials, supplies and equipment incorporated into the work; all payments made by the contractor to subcontractors for work performed according to subcontracts under this agreement; and costs, including transportation and maintenance, of all materials, supplies, equipment, temporary facilities and hand tools not owned by the workmen, which are consumed in the performance of the work, and the costs less salvage value on such items used but not consumed which remained property of the contractor. Respondent concluded construction on the project in the summer of 1977. On October 19, 1977, respondent filed a lien in the amount of $31,218.27. On the lien application respondent of stated his final day project was July 21, 1977. performance on the At trial respondent testified his last full-time work on the project was in the middle of August 1977. Respondent also introduced a "punch list" prepared by appellant's employees and dated September 23, 1977. Respondent argued the "punch list" established the last day September. respondent spent any time on the job was in The costs claimed by respondent were supported almost exclusively at trial by cancelled checks. The District Court found the lien was filed within the ninety-day period required by Montana statute. The court also found respondent's lien valid and enforceable and made the following determination of the amount owing: Costs for Anderson's out-of-pocket expenses. Defendant's payments to date for expenses. . . . . . .$150,362.72 ....... Due Plaintiff for costs. ....... Contractor's fee as a portion of 8% of contract and total costs on contract . Contractor's fee equals 8% of $366,977.56, for a total of. . . . .. . .. .... $ 139,633.00 10,729.72 .$ 10,729.72 .$366,977.56 ..... 29,358.28 Defendant's payment to date for contractor's fee. . . Due Plaintiff for contractor's fee . . . . . ............... Total due to Plaintiff by Defendant for costs Total due to Plaintiff by Defendant for fees. . TOTAL. . $ 16,758.28 ........ . . . . . . . TOTAL DUE TO 10,729.72 .$ 16,758.20 27,487.92 . . . . 8,000.00 . . . . . . . . . . . . . . . . LESS THE FOLLOWING OFFSETS: Liquidated damages. . . . . Lumber from personal stock. TOTALOFFSETS. 12,600.00 . . . . 3,800.00 . . . . . .$11,800.00 PLAINTIFF . . . . . . . . . $ 15,687.92 Four issues are before this Court: 1. Was the lien filed by respondent within the statutory ninety-day period? 2. Are there gross and substantial exaggerations in claims made which constitute fraud and void the filed lien? 3. Did the District Court err in failing to make certain deductions to the amount of the lien? 4. Did the District Court err in determining in the memorandum supporting its findings of fact and conclusions of law that Exhibit K was inadmissible as hearsay? To perfect a mechanics' lien it must be filed within ninety days after material or machinery is furnished or work or labor performed. argues there is no Section 7-3-511(1), MCA. credible evidence on the Appellant record to support the District Court's finding that the lien was filed within the statutory period. Respondent filed the lien on October 19, 1977, and on the lien stated the last work had been done on July 21, 1977. Appellant claims that the last work was performed by respondent on July 15, 1977, which was when the nursing home opened. At trial, respondent testified the date listed on the lien was incorrect and that, in fact, h i s l a s t f u l l t i m e o n t h e j o b was i n t h e m i d d l e o f A u g u s t and t h a t he r e t u r n e d i n S e p t e m b e r t o c o m p l e t e t h e p r o j e c t . Respondent a l s o s u b m i t t e d i n t o e v i d e n c e a "punch l i s t " p r e p a r e d by a p p e l l a n t ' s employee c o n t a i n i n g t h e d a t e S e p t e m b e r 23. The District Court found the lien had been filed w i t h i n t h e n i n e t y - d a y p e r i o d and s p e c i f i e d r e s p o n d e n t ' s work was c o m p l e t e d on A u g u s t 1 9 , 1 9 7 7 . The s t a n d a r d of t h i s C o u r t on r e v i e w i s w h e t h e r t h e D i s t r i c t C o u r t ' s f i n d i n g s and c o n c l u s i o n s a r e s u p p o r t e d by s u b s t a n t i a l c r e d i b l e evidence. Mont . , 6 1 1 P.2d evidence e x i s t s , 609, T o e c k e s v . Baker ( 1 9 8 0 ) , 37 S t . R e p . 948. If - substantial t h i s Court w i l l n o t o v e r t u r n t h e D i s t r i c t C o u r t . Schuman v . S t u d y Comm'n o f Y e l l o w s t o n e County ( 1 9 7 8 ) , 176 Mont. 3 1 3 , 578 P . 2 d 291. is It apparent from the record and the District C o u r t ' s f i n d i n g s t h a t t h e c o u r t gave c o n s i d e r a b l e weight t o r e s p o n d e n t ' s t e s t i m o n y a t t r i a l t h a t h i s l a s t f u l l - t i m e work on t h e p r o j e c t was i n mid-August In its supporting 1977. memorandum, t h e D i s t r i c t C o u r t c h o s e A u g u s t 1 9 , 1 9 7 7 , a s t h e final date. The r e c o r d makes no m e n t i o n o f d a t e i n August. that specific T h e r e f o r e , t h e f i n d i n g of August 19 c a n n o t T h i s C o u r t w i l l , however, g i v e c r e d e n c e t o t h e be a f f i r n e d . weight t h e D i s t r i c t Court obviously gave r e s p o n d e n t ' s t e s t i mony. "The c r e d i b i l i t y and w e i g h t g i v e n t h e w i t n e s s e s is n o t f o r t h i s Court t o determine. tion of special a trial judge consequence Hellickson v. sitting where the ... T h i s is a p r i m a r y func- without evidence a jury; is B a r r e t t M o b i l e Home T r a n s p o r t , it is of conflicting." Inc. (1973), 161 Mont. 455, 459, 507 P.2d 523, 525. Where the evidence indicates reasonable grounds for different conclusions, the findings of the District Court will not be disturbed. Morgen & Oswood Const. Co. v. Big Sky of Mont. (1976), 171 Mont. 268, 274, 557 P.2d 1017, 1021; Morrison v. City of Butte (1967), 150 Mont. 106, 112, 431 P.2d 79, 83. If respondent's last work on the project occurred any time in August or September, the filing of the lien was within the statutory ninety-day period. An exact date in August or September, however, is necessary for an accurate accounting of the $100-a-day offset allowed for late completion of the job. We therefore remand this matter for a hearing to establish the exact date in August or September on which respondent completed his full-time work on the job. The next issue before us is appellant's contention that respondent's claim contained such gross and substantial exaggerations as to constitute fraud and invalidate the lien. Fraud must be plead affirmatively to be relied on as a defense. Rule 8(c), M.R.Civ.P.; (1933), 94 Mont. 57, 20 P.2d 622. Ekestrand v. Wunder In the case before us fraud was not plead in either the original or the amended answer. Therefore, it cannot now be argued as a defense to the lien. Appellant also claims the District Court erred failing to make in reductions in the lien amount for three items. The first item appellant claims was erroneously allowed by the District Court is $2,558.60 of the $7,000 claimed paid to Simkins-Hallin. Respondent submitted a c a n c e l l e d check f o r $7,000 i n s u p p o r t of t h e S i m k i n s - H a l l i n claim. However, t h e s t a t e m e n t on S i m k i n s - H a l l i n I n v o i c e No. 6988 i n d i c a t e s t h a t o f t h e $7,000, a t e d t o respondent's job i n D i l l o n . is n o t substantial claim and that evidence the lien to $4,441.40 W therefore find there e support amount was a p p r o p r i - the should entire be $7,000 reduced by claims was $2,558.60. To evaluate erroneously the included item second by the appellant D i s t r i c t Court, consider the evidentiary issue before us. we m u s t f i r s t Appellant argues t h e r e i s a d i s c r e p a n c y b e t w e e n t h e amount r e s p o n d e n t c l a i m e d was p a i d t o M & M C o n c r e t e a n d t h e amount a c t u a l l y p a i d . I n s u p p o r t of t h a t argument a t t r i a l , a p p e l l a n t p r e sented for copy of i n t o evidence a t o t a l admission invoices of t i o n from M & account and a t h e D i l l o n j o b w i t h Anderson C o n s t r u c - M Concrete. The document was p r e p a r e d by t h e bookkeeper of M & M Co n c r e t e a t t h e d i r e c t i o n of t h e g e n e r a l manager and at the request of appellant's counsel. The a c c o u n t i n d i c a t e d a d i s c r e p a n c y b e t w e e n t h e amount r e c e i v e d by M & M C o n c r e t e on the job and the amount respondent c l a i m e d had been p a i d . R e s p o n d e n t o b j e c t e d on t h e b a s i s t h e o f f e r e d e v i d e n c e was hearsay and lacking proper foundation. The D i s t r i c t C o u r t o v e r r u l e d t h e o b j e c t i o n and a d m i t t e d t h e e v i d e n c e a s d e f e n d a n t ' s E x h i b i t K. At issued t h e conclusion of findings of s u p p o r t i n g memorandum. fact the and trial, t h e D i s t r i c t Court conclusions of law with a The memorandum s t a t e d E x h i b i t K had b e e n a d m i t t e d s u b j e c t t o r u l i n g a s t o i t s a d m i s s i b i l i t y on t h e f i n a l s u b m i s s i o n o f t h e c a s e and t h a t on f u r t h e r r e v i e w , the court found it inadmissible as hearsay. Appellant argues the District Court's af ter-the-fact ruling on the admissibility of Exhibit K was prejudicial because it precluded him from calling other witnesses or otherwise presenting proof. The transcript shows the court did not specifically reserve judgment regarding Exhibit K. was: The court's statement "Well, the objection is overruled and it will be admitted. " The court's later determination of Exhibit K as inadmissible was, however, correct. The document was a statement other than one made by the declarant while testifying at trial and was offered to prove the truth of the matter asserted. As such, it was hearsay. Rule 801(c), M0nt.R.Evi.d. Since the account statement was made, not in the ordinary course of business of M & M Concrete but at the request of appellant's counsel, it was not excepted from the hearsay rule and was inadmissible. Rule 803(6), Mont.R.Evid. While the District Court's final ruling on Exhibit K was correct, the manner in which it was reached was procedurally irregular and resulted in substantial prejudice to appellant. Had he been aware of the court's determination or its reservation of judgment during the trial, appellant could have presented and made available for cross-examination the witnesses who prepared the M & M Concrete account. To allow the District Court's exclusion of Exhibit K to stand in the face of such prejudice would be inherently unjust. We therefore remand this matter for reconsideration. The final item appellant claims was erroneously included in the lien is that amount claimed for respondent's personal wages as a carpenter. Appellant first argues that because there was no mention of the possibility of a personal claim in this agreement between the parties and respondent made no submission of such a charge to appellant prior to this suit, that respondent is not entitled to the claim. In support of this argument, appellant cites Article 10, Paragraph 10.1.6, of the parties1 contract which states as costs not to be reimbursed: "The cost of any item not specifically and expressly included in the items described in Article 9." Article 9, Paragraph 9.1.1, however, specifies that costs include "[wlages paid for labor in the direct employ of the contractor. . ." Since wages for labor are expressly included in the contract and there is no specific limitation on who performs the labor, the contract did not preclude Anderson from working on the project. Appellant also argues the hourly compensation the District Court allowed for Anderson's work was excessive and unsupported by credible evidence. The parties1 contract in Article 9 , Paragraph 9.1, allows for reimbursement of costs necessarily incurred in the proper performance of the work. It further provides that "[sluch costs shall be at rates not higher than the standard paid in the locality of the work except with prior consent . . ." At trial Anderson, a carpenter with twenty years1 exerience, testified he charged $18 an hour for his labor. Of that amount, $14 was for his work as a skilled carpenter and $4 for use of his tools. He testified the $14 amount was b a s e d on c o s t s in the area for h i s work. No other t e s t i m o n y was o f f e r e d by e i t h e r p a r t y r e g a r d i n g t h e v a l u e o f t h e work o f a c a r p e n t e r o f A n d e r s o n ' s s k i l l . Based on A n d e r s o n ' s unrebutted t r i c t C o u r t f o u n d t h a t t h e $14-an-hour c h a r g e was r e a s o n a b l e . The $4-an-hour testimony, the Dis- wage p o r t i o n o f t h e W agree. e charge f o r t h e use of Anderson's t o o l s i s a n o t h e r m a t t e r , however. While Anderson t e s t i f i e d a s t o w h a t t h e $4 was f o r , h e d i d n o t t e s t i f y o r p r o v i d e e v i d e n c e of any kind i n d i c a t i n g what w h e t h e r i t was r e a s o n a b l e . we are unable to uphold the f i g u r e was based on or W i t h o u t any s u p p o r t i n g e v i d e n c e the District Court's judgment a l l o w i n g $ 4 a n hour f o r t h e u s e o f t o o l s . W e costs. remand this matter for a reaccounting A t t h e same t i m e , w e s u g g e s t a r e v i e w o f of the the calcu- l a t i o n s i n t h e o r i g i n a l f i n d i n g s o f f a c t and c o n c l u s i o n s o f l a w , s i n c e t h e r e a p p e a r s t o be a n a r i t h m e t i c e r r o r computation of Anderson's out-of-pocket Justices expenses. in the Mr. Justice John C. Sheehy concurring: I concur in the foregoing, but I also think the lien filed in this case was timely under the facts. Justice

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.