Noble House, Inc. v. W & W Plumbing & Heating, Inc.

Annotate this Case
Download PDF
IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI NO. 2002-CA-02060-COA NOBLE HOUSE, INC. AND FRANCIS J. RANSOM D/B/A RANSOM CONSTRUCTION COMPANY APPELLANTS v. W & W PLUMBING & HEATING, INC. DATE OF TRIAL COURT JUDGMENT: TRIAL JUDGE: COURT FROM WHICH APPEALED: ATTORNEYS FOR APPELLANTS: ATTORNEY FOR APPELLEE: NATURE OF THE CASE: TRIAL COURT DISPOSITION: DISPOSITION: MOTION FOR REHEARING FILED: CERTIORARI FILED: MANDATE ISSUED: APPELLEE 10/28/2002 HON. FORREST A. JOHNSON, JR. ADAMS COUNTY CIRCUIT COURT BRUCE M. KUEHNLE STEVEN H. SMITH TIM DAVID BLALOCK CIVIL - CONTRACT MOTION TO AMEND JUDGMENT DENIED AFFIRMED - 08/31/2004 BEFORE KING, C.J., BRIDGES, P.J., AND CHANDLER, J. CHANDLER, J., FOR THE COURT: ¶1. This appeal arises from an October 28, 2002 order of the Adams County Circuit Court denying a motion by Noble House, Inc. and Francis J. Ransom, d/b/a Ransom Construction Company, Inc., to alter or amend a judgment entered on October 4, 2002. At issue is a so-called “agreed judgment of dismissal” devised by Noble House and Ransom, which, without notice, unilaterally precluded the subcontractor, W & W Plumbing & Heating, Inc., from sharing in funds interpled with the court pursuant to Rule 22 of the Mississippi Rules of Civil Procedure. Noble House and Ransom challenge the circuit judge’s hand-written provision in the October 28 order for W & W Plumbing, which had been named as an interpleader defendant when litigation began in 1997. Finding that the circuit judge did not abuse his discretion in refusing to grant the motion to alter or amend the judgment, we affirm the decision of the court below. FACTS ¶2. On April 27, 1994, Francis J. Ransom, d/b/a Ransom Construction Company, entered into a contract with Noble House, Inc. and the Adams County Board of Supervisors for the construction of a multi-family, low-income housing project in Natchez, Mississippi, under the aegis of the Home Investment Partnership Program of the United States Department of Housing and Urban Development. Under the terms of the contract, construction of the apartments was scheduled for completion within 240 days of the contract date. However, because of various collateral legal proceedings not related to the case sub judice, work was stopped between November 1994 and August 1995. Consequently, the apartments were not ready for occupancy until November 1996. ¶3. As a result of the work stoppage, the original subcontractor Ransom had hired to install the plumbing, heating and air conditioning systems refused to perform. Ransom substituted W & W Plumbing & Heating as the alternative subcontractor, which bid $55,964.32 to correct work previously done and to complete the project. Invoices submitted by W & W Plumbing to Ransom indicate that the contractor paid the first draft of $30,589.05 on September 3, 1996. Two subsequent drafts of $14,287.51, due on October 1, 1996, and $10,817.76, due on December 1, 1996, were not paid. ¶4. During the course of construction, Noble House made periodic installment payments to Ransom. On October 16, 1996, with the apartments nearly ready for occupancy, Noble House notified Ransom in writing that its contract was terminated because of Ransom's alleged failure to complete the limited work remaining in a timely and workman-like manner. Noble House thus withheld its final payment of $72,356 to the contractor. Ransom, in turn, did not pay W & W 2 Plumbing the final $25,105.27 it was owed for completing the plumbing, heating and air conditioning work.1 ¶5. On February 1, 1997, Noble House filed a complaint in the Adams County Circuit Court against Ransom and W & W Plumbing. Noble House charged that Ransom had breached its contract by failing to complete the project in a timely and workman-like manner. Noble House averred that it had not made the final payment of $72,356 to Ransom because of economic losses caused by the construction delays. Noble House further stated in its complaint that Ransom owed the plumbing contractor $25,105.27. Therefore, Noble House sought to interplead a total of $72,356 and named W & W Plumbing as an interpleader defendant for purposes of the escrowed funds. ¶6. W & W Plumbing filed its response to the complaint on February 26, 1997. Ransom filed a response and counter-claim against Noble House on March 13, 1997, seeking recovery for additional project expenses incurred by the stop work order. Ransom further alleged that the original contract was rescinded by the stop work order and never revived, either orally or in writing. ¶7. W & W Plumbing filed a motion for partial summary judgment on March 27, 1997. W & W Plumbing asserted that it was undisputed that it had properly completed the work as agreed and was entitled to payment in the amount of $31,877.29, which included accrued interest. Since the pleadings filed by Noble House and Ransom agreed that W & W Plumbing was entitled to $25,105.27 due and payable from December 1, 1996, the subcontractor asked the court to declare that there was no issue of material fact and to pay the amount due from the interpled funds. Noble House responded that proof of the amount due had not been placed in evidence. Accordingly, the circuit judge found that granting relief would be premature and denied the motion on April 30, 1997. 1 By letter dated September 23, 1996, Ransom represented to Noble House that all debts related to the construction had been paid and no claims had been asserted against the contractor. The debt owed to W & W Plumbing arose after this time. 3 ¶8. Ransom amended its counterclaim against Noble House on July 8, 1998, seeking payment of the money owed to W & W Plumbing, the $72,356 allegedly still owed for completing the construction, and further, compensation for business lost because of bonding problems arising from the litigation. Noble House likewise amended its complaint against Ransom, joining Cumberland Surety & Performance Co., Inc., which had provided Ransom’s performance bond. ¶9. On June 1, 2000, W & W Plumbing filed an amended response to the initial complaint. Contrary to all parties’ earlier position that the plumbing company was a subcontractor, W & W Plumbing asserted that because time had been of the essence in completing the project, it had acted as an independent contractor for both Ransom and Noble House. W & W Plumbing alleged that it had reported directly to Noble House, which had supervised the work and guaranteed payment. Because of the disputes and delays encountered during the course of construction, W & W Plumbing further claimed that it had refused to enter into a contract and all work had been done on an hourly basis. Noble House denied the allegations made in the amended response, subsequently filing a motion for partial summary judgment in August 17, 2000, seeking dismissal of any claims W & W Plumbing might have against it or the interpled funds. ¶10. Ransom then filed its motion for summary judgment on October 4, 2000. Ransom, for the first time, asserted that the work performed by W & W Plumbing had been done pursuant to an open account arrangement. Ransom therefore argued that any claim W & W Plumbing might have against it was time-barred by the three-year statute of limitations on open accounts prescribed by Mississippi Code Annotated Section 15-1-29 (Rev. 2003). ¶11. Noble House’s motion for summary judgment was denied on October 23, 2000. The circuit judge found that no independent claim by W & W Plumbing existed against Noble House which would be a proper subject for summary judgment. The judge expressly refused to rule on the validity or invalidity of any claims against the interpled funds, stating that the issue should be 4 bifurcated and held in abeyance until the claims between Ransom and Noble House were resolved. In his November 2, 2000 order, the circuit judge reiterated that W & W Plumbing had basis for a claim against Noble House, and had not asserted any counterclaims against the owner or crossclaims against Ransom and remained only an interpleader defendant, with claims solely to the interpled funds. ¶12. In its amended response, W & W Plumbing noted that Noble House had failed to deposit the full $72,356 it sought to interplead in the original complaint. Ransom subsequently filed a motion to require Noble House to deposit the remaining $51,167.32 in the escrow account, which was denied by the circuit judge on January 31, 2002. Thus, the full amount was never deposited with the court. ¶13. Partial summary judgment for W & W Plumbing was granted on August 13, 2002. The circuit judge found that the work done by W & W Plumbing was specifically requested by both Noble House and Ransom and that it was completed according to the specifications of both parties. The amount claimed by W & W Plumbing, the judge determined, was undisputed. The circuit judge further ruled that while W & W Plumbing could bring no claims against Noble House, it was entitled to payment from the funds interpled with the court. ¶14. On October 3, 2002, Noble House and Ransom advised the circuit judge that they had reached a settlement whereby the parties would dismiss all claims against each other. The order presented to the court directed the circuit clerk to divide the interpled funds evenly between Noble House and Ransom. The circuit court entered the agreed judgment of dismissal on October 4, 2002, after amending it to provide for payment of funds to Noble House and Ransom “[a]fter first paying the sum of $25,105.27 to W & W Plumbing and Heating, Inc.” ¶15. Noble House and Ransom filed their motion to alter or amend the agreed judgment on October 24, 2002. They reasserted their claim that W & W Plumbing was not entitled to the funds 5 originally interpled on its behalf. Moreover, they argued that the circuit judge’s orders exceeded his authority and contravened their intentions. ¶16. A hearing was held to show cause why the funds should not be paid out as ordered by the court. As a result of those proceedings, the circuit judge entered an order on October 28, 2002, finding that the October 4, 2002 agreed judgment of dismissal should stand, as amended by the judge, and denying the motion to alter or amend. In the order, the circuit judge further found that W & W Plumbing had been made a party defendant in an interpleader action initiated by Noble House, recognized by the court as an interpleader defendant and found to have a claim solely to the interpled funds. He emphasized that the agreed judgment of dismissal made no mention of W & W Plumbing as an interpleader defendant and that the attorney for W & W Plumbing neither had agreed to the disposition of funds set forth in the judgment of dismissal nor been informed that it would be presented to the court. The interpleader funds were ordered to remain on deposit with the circuit clerk pending this appeal. LAW AND ANALYSIS I. WHETHER THE CIRCUIT COURT ABUSED ITS DISCRETION IN ENTERING ORDERS GRANTING PARTIAL SUMMARY JUDGMENT TO W & W PLUMBING, AMENDING AND ENTERING THE AGREED ORDER OF DISMISSAL AND DENYING THE RULE 60 MOTION FILED BY NOBLE HOUSE AND RANSOM A. The Order Granting Partial Summary Judgment ¶17. The circuit court entered an order on August 13, 2002, granting partial summary judgment for W & W Plumbing. As part of their first assignment of error, Noble House and Ransom mention in passing that the circuit judge erred in granting partial summary judgment for W & W Plumbing. However, as discussed below, the circuit court correctly found that although W & W Plumbing was not entitled to bring a claim directly against Noble House, the property owner and stakeholder in this interpleader action, it was entitled to payment from the funds interpled with the court. 6 B. The Agreed Order of Dismissal and Rule 60(b)(6) Motion ¶18. On October 3, 2002, the circuit judge entered an agreed judgment of dismissal, presented to the court by Noble House and Ransom. Noble House and Ransom advised the judge that they had reached a settlement in the case, sought the dismissal of all claims and counterclaims with prejudice, and would split the interpled funds evenly between them. W & W Plumbing was neither advised by the other parties of the agreement between them nor that it had been unilaterally cut off from the funds which had been interpled, ostensibly on its behalf, nearly six years earlier. The circuit judge, therefore, modified the final paragraph of the order, which originally provided that the interpled funds and all interest which had accrued thereon, be divided evenly between Noble House and Ransom, by inserting a handwritten provision that such division take place only “after first paying the sum of $25,105.27 to W & W Plumbing and Heating, Inc.” ¶19. Noble House and Ransom filed a motion to alter or amend the agreed judgment of dismissal on October 24, 2002, contending that the circuit judge abused his discretion in amending the judgment because W & W Plumbing was not entitled to the interpled funds. They asserted that because the subcontractor had failed to make a valid claim to the funds by filing a counterclaim against Noble House or a cross-claim against Ransom or by timely filing a stop notice pursuant to Mississippi Code Annotated section 85-7-181 (Rev. 1999) and had no contractual relationship with Noble House, it was precluded from recovery. Accordingly, Noble House and Ransom argued that the circuit judge’s modification of their agreed order completely abrogated the terms and conditions to which the two parties had agreed.2 ¶20. At the show cause hearing, the circuit judge explained: 2 It is not clear from the record what role, if any, Cumberland Surety & Performance Co., Inc. played in the settlement between Ransom and Noble House and in the agreed dismissal. 7 Essentially what the Court is ruling is that once the funds were interpled into court, Noble House and Ransom had every right to settle all their claims, but they had no right to unilaterally provide for the disposition of the interpled funds, particularly given the rulings previously made by the Court and W.W.’s clear status as an interpled defendant to these funds. The circuit judge further reminded the parties that “Noble House and Ransom had every right to settle their claims and competing interests between themselves, but you cannot be an Indian giver with interpled funds.” ¶21. Although the motion was filed by Noble House and Ransom pursuant to Rules 59 and 60 of the Mississippi Rules of Civil Procedure, it must be treated as a Rule 60(b)(6) motion because it was not filed within ten days of the final judgment as required by Rule 59. Fultz v. Doss, 507 So. 2d 891, 893 (Miss. 1987). The Mississippi Supreme Court has stated that "[r]elief under Rule 60(b)(6) is reserved for extraordinary and compelling circumstances," and further, that the Rule is a "grand reservoir of equitable power to do justice in a particular case." M.A.S. v. Mississippi Dept. of Human Services, 842 So. 2d 527, 530 (¶ 12) (Miss. 2003), quoting Briney v. United States Fid. & Guar. Co., 714 So. 2d 962, 966 (Miss. 1998). In the case sub judice, the circuit judge, as he explained at the show cause hearing, acted to correct an extraordinary situation. ¶22. "Rule 60(b) is not an escape hatch for litigants who had procedural opportunities afforded under other rules and who without cause failed to pursue those procedural remedies." City of Jackson v. Jackson Oaks Ltd. P'ship, 792 So. 2d 983, 986 (Miss. 2001). The case was initiated by Noble House, albeit represented by different counsel and overseen by a different judge, as an interpleader action pursuant to Rule 22 of the Mississippi Rules of Civil Procedure. Throughout six years of litigation, W & W Plumbing remained as a defendant solely for purposes of the interpleader funds, the total amount of which was never paid into the court by Noble House. Neither the contract issues between Noble House and Ransom nor the interpleader action were ever pursued to the extent 8 of resolution. Both Noble House and Ransom failed to pursue the procedural remedies initiated by Noble House to resolve the differences between them. "Further, Rule 60(b) motions should be denied where they are merely an attempt to relitigate the case." Stringfellow v. Stringfellow, 451 So. 2d 219, 221 (Miss. 1984). Given the peculiar twists and turns this case took over six years, the agreement between Noble House and Ransom, without notice to W & W Plumbing, together with the Rule 60(b)(6) motion challenging the circuit judge’s amendment of the “agreed judgment of dismissal,” may well be construed as an attempt to relitigate the case. ¶23. A trial judge's denial of a motion seeking relief under Rule 60(b)(6) is subject to review under an abuse of discretion standard. Telephone Man, Inc. v. Hinds County, 791 So. 2d 208, 210 (Miss. 2001); Moore v. Jacobs, 752 So. 2d 1013, 1015 (Miss. 1999). Among the factors a trial judge must consider when ruling on a 60(b)(6) motion are whether the movants have had a fair chance to state their claims, whether it would be inequitable to grant the relief sought as well as any other factors which are “relevant to the justice of the judgment under attack.” Briney v. United States Fidelity & Guaranty Co., 714 So. 2d 962, 968 (Miss. 1998). Given the particular circumstances of this case, the circuit judge did not abuse his discretion in amending the agreed order to provide the relief originally intended for W & W Plumbing or in denying the Rule 60(b)(6) motion. ¶24. Noble House and Ransom argue, however, that W & W Plumbing is not entitled to the interpled funds because the subcontractor did not proactively assert a claim to the funds. They contend that it first was necessary for W & W Plumbing either to file a stop notice pursuant to Mississippi Code Annotated section 85-7-181 (Rev. 1999) or a construction lien or enforcement of a construction lien as authorized by Mississippi Code Annotated sections 85-7-131 (Rev. 1999) and 85-7-141 (Rev. 1999), or further, to seek recovery against Ransom, the contractor, before it could claim a share in funds deposited with the court through the Rule 22 interpleader action. However, following the statutory notice filing procedures is required only when a subcontractor seeks to 9 pursue a statutory remedy against a property owner; it is not a pre-requisite to eligibility for funds interpled pursuant to a Rule 22 action. 1. Rule 22 Interpleader ¶25. Rule 22(a) of the Mississippi Rules of Civil Procedure provides for an interpleader action as follows: Persons having claims against the plaintiff may be joined as defendants and required to interplead when their claims are such that the plaintiff is or may be exposed to double or multiple liability. It is not ground for objection to the joinder that the claims of the several claimants or the titles on which their claims depend do not have a common origin or are not identical but are adverse to and independent of one another, or that the plaintiff avers that he is not liable in whole or in part to any or all of the claimants. A defendant exposed to similar liability may obtain such interpleader by way of cross-claim or counterclaim. The provisions of this rule supplement and do not in any way limit the joinder of parties permitted in Rule 20. The action may be used “to protect the claimants by bringing them together in one action and reaching an equitable division of a limited fund.” M.R.C.P. 22 cmt. ¶26. As we explained in Chic Creations of Bonita Lakes Mall v. Doleac Electric Co., 791 So. 2d 254, 257 (¶ 10) (Miss. Ct. App. 2000), “[t]he Rule 22 interpleader action provides only the procedural vehicle to assert claims to the specific funds. The rule by itself cannot be the basis for a pro-rata distribution. In order for the subcontractors to assert a valid claim to this fund they must do more than show that they are owed money by the contractor. They must demonstrate how they are entitled to a portion of this particular fund . . . .” W & W Plumbing was brought into this litigation by Noble House, which specifically interpled into court funds admittedly owed to the subcontractor, while Noble House, the owner, and Ransom, the contractor, attempted to settle the contract issues that had arisen between them. Noble House’s “filing of this interpleader action sufficiently demonstrated that it was willing to pay whomever the trial court determined had a valid claim to the interpled funds.” Amerihost Dev., Inc. v. Bromanco, Inc., 786 So. 2d 362, 367 (¶ 24) (Miss. 2001). We note, moreover, that Noble House actually deposited with the court only that 10 amount agreed by the parties to be due W & W Plumbing; it was never required to interplead the entire sum specified in the original pleadings. ¶27. The comment to Rule 22 acknowledges that generally, “claimants will have asserted their claims to the interpleader fund in their answer to the stakeholder’s complaint. If an order of interpleader is entered, each claimant must then traverse the claims of the other claimants, thus joining the issue. Alternatively, if the issues are already clearly defined in the claimants’ initial pleadings, further pleadings may be unnecessary.” M.R.C.P. 22 cmt. (emphasis added). The complaint of Noble House, the stakeholder, together with the original responses to the complaint filed by the claimants, Ransom and W & W Plumbing, clearly articulated the issues. From the pleadings, it is evident that both Noble House and Random knew and acknowledged that W & W Plumbing had not been paid for the work it had completed on the Noble House project, and that the subcontractor was owed $25,105.27. Invoices to Ransom from W & W Plumbing provide further evidence of the unpaid balance. Because the amount owed to W & W Plumbing did not exceed the funds interpled, W & W would have no further claim against Noble House. Humble Oil & Refining Co. v. Rankin, 207 Miss. 402, 411, 42 So. 2d 414, 416 (1949). ¶28. W & W Plumbing did, however, promptly file a motion for summary judgment, in essence, seeking a declaration of its interest in the interpleader funds. The Comment to Rule 22 provides that “[s]ummary judgment may be granted in favor of any one of the claimants against any other, even before the former serves an answer to the latter’s pleading, a procedure generally appropriate under Rule 56(b).”3 M.R.C.P. 22 cmt. Since the initial pleadings clearly defined the issues, further pleadings were unnecessary. Thus, entitlement to funds placed in escrow pursuant to a Rule 22 3 Interpleader is an equitable action. “[W]hen equity takes jurisdiction of a matter for one purpose it will administer complete relief as to every portion or feature of the controversy and, so far as practicable, quiet the whole of the issues.” Humble Oil, 207 Miss. at 412, 42 So. 2d at 417, quoting Griffith’s Mississippi Chancery Practice § 101. 11 interpleader action may be determined on the basis of the pleadings or any other outside evidence introduced. It need not be predicated upon satisfaction of statutory notice procedures. 2. The § 85-7-181 “Stop Notice” Action ¶29. Noble House and Ransom assert, however, that W & W Plumbing is not entitled to share in the interpleader funds because it did not timely file a “stop notice” with Noble House pursuant to Mississippi Code Annotated section 85-7-181 (Rev. 1999). “Only those with a direct contractual relation with the owner’s contractor can file an effective stop notice, and then only to require the retention of funds owed by the owner to the contractor.” Chic Creations, 791 So. 2d at 258 (¶ 14). In the initial pleadings and throughout the first three years of these proceedings, the parties and the court recognized W & W Plumbing as a subcontractor. As a subcontractor, W.W. Plumbing was eligible to seek the protection offered by the statute. ¶30. Filing a “stop notice” with the owner is a pre-requisite to pursuing the subcontractor’s statutory remedy outlined in § 85-7-181. Once a subcontractor who has not received payment for his work by a contractor provides the property owner with written notice, he is entitled to payment from the owner up to the amount the owner is indebted to the general contractor as of the date the notice is served. Miss. Code Ann. § 85-7-181 (Rev. 1999). Having failed to file a stop notice with Noble House after the drafts still owing were not paid by Ransom, W & W Plumbing stands only as a general creditor of Ransom, the contractor, with no right of recovery directly against Noble House, the owner. Corrugated Indus., Inc. v. Chattanooga Gas Co., 317 So. 2d 43, 47 (Miss. 1975). Indeed, the circuit judge correctly found that W & W Plumbing’s only relief lay with the funds ostensibly interpled on its behalf, and not in any action against either Noble House or Ransom. 3. The §§ 85-7-131 and 85-7-141 Mechanic's Lien ¶31. In its amended response filed in June, 2000, W & W Plumbing asserted for the first time that it had worked as an independent contractor for both Noble House and Ransom, operating directly 12 under the supervision of Noble House. Noble House denied this assertion. Indeed, in his order granting summary judgment for W & W Plumbing, the circuit judge found that W & W Plumbing had worked for both Noble House and Ransom, but did not label the plumber either as a subcontractor or a general contractor. Noble House and Ransom, nevertheless, suggest that W & W Plumbing should have asserted its claim by filing a mechanic’s lien pursuant to § 85-7-131 and by pursuing an action thereunder pursuant to § 85-7-141. Contractors are entitled to a lien against the property if they are not paid for their services and materials. Chic Creations, 791 So. 2d at 259 (¶ 20). Section 85-7-131 allows only "architects, engineers, surveyors, laborers, and materialmen and/or contractors" to secure a lien against the owner's property for services rendered and improvements constructed. Cummings v. Davis, 751 So. 2d 1055, 1058 (¶14) (Miss. Ct. App. 1999). The remedy does not extend to subcontractors, who, according to the statutory scheme, must pursue a separate remedy under § 85-7-181. Chic Creations, 791 So. 2d at 259 (¶ 20). At the time a lien could have been filed and throughout most of these proceedings, W & W Plumbing held itself out as a subcontractor and thus, was not entitled to the remedy provided to contractors pursuant to §§ 85-7-131 and 85-7-141. ¶32. Assuming arguendo that W & W may be characterized as something other than a subcontractor and could have afforded itself protection with a mechanic’s lien, we note that there is no evidence in the record that Ransom, the contractor, filed a lien against Noble House pursuant to § 85-7-131 for the $72,356 allegedly it was due upon completion of the project. If we were to extend the logic of Noble House’s and Ransom’s argument against W & W Plumbing’s entitlement to the interpleader funds to Ransom, we would have to find that Ransom, too, was just a creditor of Noble House without the priority of a lienholder and thus, on an equal footing with W & W Plumbing. Moreover, it appears from the record that the only liens filed throughout the course of 13 litigation were those filed by Noble House’s former attorneys against any proceeds the project owner might recover. II. WHETHER ANY AND ALL CLAIMS BY W & W PLUMBING AGAINST RANSOM AND NOBLE HOUSE WERE TIME-BARRED ¶33. Noble House and Ransom further contend that any cause of action against them or claim to the interpled funds is time-barred. They suggest that because the statutes of limitations have run on the remedies W & W Plumbing might have pursued, it is not entitled to share in the interpleader funds. The passage of time is not fatal to W & W Plumbing’s entitlement to the interpled funds. Pursuing statutory remedies is not a prerequisite to a Rule 22 interpleader action. Indeed, W & W Plumbing is in the same position as Ransom, which from the record, similarly does not appear to have timely availed itself of any statutory remedies. Moreover, since the inception of this litigation, Noble House has maintained, and the decisions of the circuit judges have consistently stated, that W & W Plumbing has no claim against Noble House, itself. Noble House cannot now argue that any action against it is time-barred. There is no merit to the assignment of error. CONCLUSION ¶34. An interpleader action, the Comment to Rule 22 suggests, “can be employed to reach an early and effective determination of a disputed question with a consequent saving of trouble and expense for the parties.” Despite the circuit judge’s efforts “to reach an early and effective determination of a disputed question,” trouble and expense for the parties mounted during the six years of litigation, culminating with the circuit court’s challenging the propriety of the parties’ attorneys’ actions in unilaterally denying W & W Plumbing’s entitlement to the funds interpled to the court on its behalf. The circuit judge correctly found that W & W Plumbing was entitled to recover only against the interpleader funds and not against Noble House and Ransom. Entitlement to those funds was a finding for the court to make, not the parties. Thus, the circuit judge did not 14 abuse his discretion in granting partial summary judgment for W & W Plumbing, amending the agreed judgment of dismissal to protect the rights of the parties which were already adjudicated and denying the motion to alter or amend the judgment. Accordingly, we affirm the judgment of the circuit court. ¶35. THE JUDGMENT OF THE CIRCUIT COURT OF ADAMS COUNTY IS AFFIRMED. ALL COSTS OF THIS APPEAL ARE ASSESSED TO THE APPELLANTS. KING, C.J., BRIDGES, P.J., LEE, MYERS, GRIFFIS AND BARNES, JJ., CONCUR. IRVING DISSENTS WITH SEPARATE WRITTEN OPINION. IRVING, J., DISSENTING: ¶36. The majority affirms the judgment of the trial court granting partial summary judgment to W & W Plumbing and Heating, Inc. and awarding W & W the sum of $25,105.27 from funds interpled into court by Noble House, Inc. I am of the opinion that the majority has overlooked some glaring errors committed by the trial court and as a result has arrived at an erroneous decision. Consequently, I dissent. I would reverse and render the judgment in favor of W & W. ¶37. This matter began with Noble House filing an interpleader action. Francis J. Ransom d/b/a Ransom Construction Company, and W & W Plumbing and Heating , Inc. were made defendants. In its complaint, Noble alleged (1) that it entered into a contract with Ransom for construction of a low-income multi-unit dwelling at a cost of $407,689 under the Home Investment Partnership Program in conjunction with the Adams County Board of Supervisors, (2) that as a condition of the subject construction contract, Ransom obtained a performance and surety bond from Cumberland Surety Insurance Company, Inc.,4 (3) that Ransom had materially breached the contract resulting in 4 Later, Noble amended its complaint to make Cumberland a defendant. In its amended complaint, Noble alleged that Ransom and Cumberland were jointly liable to it as a result of Cumberland's being the surety on Noble's performance bond. 15 considerable damage to Noble, (4) that W & W served as Ransom's plumbing subcontractor on the project and that Ransom owed W & W a balance of approximately $25,105.27 for plumbing work performed on the project, (5) and that a final payment in the amount of $72,356 was to be made upon completion of the project but because of the damages and economic loss caused by Ransom's breach, Noble had withheld payment of the final installment. In the prayer of its complaint, Noble asked that a judgment be entered "in its favor against Ransom in an amount to be determined at trial, equal to its economic loss and damages resulting from Ransom's breach of the subject construction contract." Noble further requested that the court "enter an order directing the Chancery Clerk of Adams County, as the present custodian of the final payment, to pay such funds into the registry of [the] court to be held in an interest bearing account during the pendency of [the] litigation." ¶38. Noble never alleged that W & W was entitled to any of the interpled funds, just that Ransom owed money to W & W. ¶39. W & W answered Noble's complaint and admitted that it was Noble's subcontractor on the project and that Noble owed it $25,105.27 for work performed. W & W asked to be paid out of the monies withheld and that it be dismissed from the action, leaving the remaining parties to litigate their differences. It is significant that while W & W stated that it was owed the money as alleged in Noble's complaint, it did not make any claim against either Noble or Ransom. It simply alleged that it had performed all the work in a workmanlike manner required of it under its subcontract. ¶40. Ransom answered Noble's complaint and admitted that W & W was a subcontractor on the project. Ransom did not specifically deny that he owed W & W $25,105.27 as alleged in paragraph eleven of Noble's complaint. However, he did deny generally that he owed W & W for plumbing work as alleged in paragraph eighteen of Noble's complaint. Finally, Ransom alleged that he was entitled to the entire $72,356, and in his counterclaim, which was also filed with his answer, Ransom 16 demanded an additional $31,877.29 from Noble which he alleged was due him as a result of Noble's breach of the contract. ¶41. In W & W's motion for partial summary judgment, it alleged: All parties hereto, both in the complaint of Noble House, Inc. and the separate answer of Francis J. Ransom d/b/a Ransom Construction Company, set forth and allege that this defendant, W & W Plumbing & Heating, Inc., has completed the terms of his [sic] contract, the basis of the monies interpled into this court pursuant to M.R.C.P. 22. Further, both parties by the same pleadings, specifically set forth and agree that this defendant is entitled to the sum of $25,105.27, being due and payable from December 1, 1996. That no other set of facts involve this defendant as a party to this action. . . . [t]hat there is no genuine issue of material fact on the issue of paying this defendant the sum of $25,105.27, plus accrued interest and dismissing it as a party to this action, as a matter of law. ¶42. On April 15, 1997, Noble responded to W & W's motion for partial summary judgment in pertinent part as follows: [T]here exist genuine issues of material fact which preclude summary judgment in W & W's favor. Specifically, and contrary to W & W's assertions, the sum total allegedly owed to W & W is not undisputed. Although NHI [Noble House, Inc.] has set forth in its pleadings that certain monies are due W & W for work done on the subject housing project, the figure relied upon was furnished to NHI by W & W and its attorney, without prove [sic] or substantiation of the same. Hence, NHI has alleged that "approximately" $25,105.27 is due W & W. This figure is subject to proof by W & W, as well as proof by NHI and Ransom, as to the accuracy of the same and whether any reductions or setoffs apply. ¶43. On April 22, 2000, Noble, with new attorneys, filed another response to W & W's motion for partial summary judgment. In that response, Noble again admitted that Ransom owed money to W & W for plumbing work done on the project but denied that W & W was entitled to any of the interpled fund. Noble specifically alleged that W & W had "no legal or factual basis that would entitle it to even assert, much less prevail, on its assertion that it is somehow entitle [sic] to receive any amount or portion of the funds previously interpled or any other sum or amount paid or unpaid." ¶44. On November 2, 2000, the trial court entered an order in which it ordered and adjudged (1) that W & W had no claim against Noble and had not asserted any counterclaim against Noble other 17 than to the interpled funds, (2) that W & W had not asserted any cross-claim against Ransom Construction Company other than to the interpled funds, and (3) that W & W would be allowed to remain as a non-participating interpleader defendant throughout the duration and conclusion of the action, with a claim to the interpled funds, "for the reasons stated in the record." Presumably, those reasons were that W & W had been made a party defendant by Noble and that Noble had alleged that W & W was owed money by Ransom as a result of work that W & W had performed for Ransom on the project. In an earlier order, the trial court had ordered that the issue of the interpled monies should be bifurcated and held in abeyance until the primary issue between Noble and Ransom had been adjudicated. ¶45. On August 13, 2002, the trial court granted partial summary judgment to W & W, finding that "upon the evidence heard in open court," there was no genuine issue of fact that W & W was due the monies contracted for as the subcontract was properly completed. More specifically, the trial court found: (1) that the work done by W & W was specifically requested by both parties, Francis J. Ransom d/b/a Ransom Construction Company and Noble House, Inc., and that all services sought were done and completed according to the specifications of both parties and the amount claimed, i.e., $25,105.27 is undisputed, (2) that [W & W was] not entitled to a claim against Noble House, Inc., [but that it was] entitled to payment from the sum interpled with the Court for which this issue was joined and for which it was made a party. Additionally, the trial court found that W & W was entitled to payment of $25,105.27 from the interpled funds. ¶46. Sometime after the trial court granted summary judgment to W & W, Noble and Ransom presented an agreed judgment of dismissal to the trial court in which they agreed that the case should be dismissed with the interpled funds divided equally between them and disbursed accordingly. The trial judge, sua sponte, modified the agreed judgment to reflect that W & W be paid $25,105.27 and the remainder of the interpled funds be disbursed equally between Noble and Ransom. The agreed 18 judgment as modified sua sponte by the trial court was executed on October 3, 2002, and entered on October 4. ¶47. At some point after October 4, Noble and Ransom filed a letter with the clerk of the court advising that they would be appealing the court's October 3 order and requesting that the funds not be disbursed. The court was apprised of the letter and as a result, entered an order on October 17 in which the court stated that it would hold a hearing on October 28 to allow the remaining parties to show cause why the interpled funds should not be disbursed in accordance with the court's order of October 3. ¶48. On October 24, Noble and Ransom, apparently in response to the court's October 17 order, filed a joint motion seeking relief from the court's October 3 order. They alleged that neither NHI nor Ransom agreed to the terms and conditions which the court placed on the agreed judgment of dismissal previously provided to the court and that the court was without factual or legal authority to modify the agreed judgment of dismissal submitted by them. They further argued that the court's modification of the agreed judgment completely abrogated the terms and conditions of the agreed judgment and that as a result there was no longer an agreement between the parties. Additionally, Noble and Ransom alleged that "at no time since W & W Plumbing purportedly performed work on the construction project for Ransom, has it filed any sort of stop notice, statutory stop notice, claim, lawsuit or other type of action against Noble House, Inc." They further argued that W & W had no contractual relationship with Noble which would cause it to be entitled to any of the funds. ¶49. On October 28, the trial court entered an order in which it found that the "court's order for disposition of the interpleaded funds should stand" and that the October 28 order "shall constitute the final order or judgment in this case, and that any applicable time periods for appeal shall commence to run upon the filing" of the October 28 order. 19 ¶50. Neither the trial court nor the majority offers any basis for finding that W & W was entitled to be paid out of the interpled funds other than the fact that W & W was made an interpleader defendant and had performed work on the project. It appears to me that both the trial court and the majority have confused W & W's right to be paid, with its right to be paid from the interpled funds. No right accrued to W & W to be paid from the interpled funds simply because it had done work on the project and had not been paid for it. Indeed, it seems the majority recognized as much when it quoted from our decision in Chic Creations of Bonita Lakes Mall v. Doleac Electric Co., 791 So. 2d 254, 257 (¶10) (Miss. Ct. App. 2000), "[t]he Rule 22 interpleader action provides only the procedural vehicle to assert claims to the specific funds. The rule by itself cannot be the basis for a pro-rata distribution. In order for the subcontractors to assert a valid claim to this fund they must do more than show that they are owed money by the contractor. They must demonstrate how they are entitled to a portion of this particular fund. . . ." ¶51. Having recognized the appropriate law, the majority then proceeds to ignore it. Therefore, I find no need to further address the rationale offered by the majority for its erroneous decision, for the opinion, in my humble judgment, misses the point. ¶52. Without a doubt, W & W had a remedy, but the question is whether its remedy was to be paid out of the interpled funds even if it had not followed the proper procedure to allow it to reach those funds. On the facts before us, that answer is a resounding no. In the balance of this opinion, I will attempt to explain why I believe the judgment of the trial court and the decision of the majority are misguided. ¶53. Ransom posted a performance bond in connection with his contract with Noble. Noble and the Board of Supervisors of Adams County were the obligees under the performance bond. ¶54. Mississippi Code Annotated section 85-7-185 (1972) provides: 20 When any contractor or subcontractor entering into a formal contract with any person, firm or corporation, for the construction of any building or work or the doing of any repairs, shall enter into a bond with such person, firm or corporation guaranteeing the faithful performance of such contract and containing such provisions and penalties as the parties thereto may insert therein, such bond shall also be subject to the additional obligations that such contractor or subcontractor, shall promptly make payments to all persons furnishing labor or material under said contract; and in the event such bond does not contain any such provisions for the payment of the claims of persons furnishing labor or material under said contract, such bond shall nevertheless inure to the benefit of such person furnishing labor or material under said contract, the same as if such stipulation had been incorporated in said bond, and any such person who has furnished labor or materials used therein; for which payment has not been made, shall have the right to intervene and be made a party to any action instituted on such bond, and to have his rights adjudicated in such action and judgment rendered thereon, subject, however, to the priority of the rights or claim for damages or otherwise, of the obligee. . . . (emphasis added). ¶55. Once the bond was posted, all funds due Ransom under the construction contract were released from liens or attachments of laborers and materialmen. Dickson v. United States Fidelity & Guaranty Co., 150 Miss. 864, 878, 117 So. 245, 246 (1928). ¶56. As stated, this case started with Noble filing an interpleader action in which it named W & W as a defendant. Initially, Cumberland, the surety of Ransom's performance bond, was not a party to the litigation. Prior to Cumberland being made a party defendant, W & W had no legal basis whatsoever to any portion of the interpled funds. Its sole recourse at that time would have been to institute an action against Ransom and Cumberland, forcing Cumberland to make good on its obligation as surety in compliance with the requirements of section 85-7-185. ¶57. When Noble brought Cumberland into the case, W & W had the right under section 85-7-185 to intervene and have its rights adjudicated. Miss. Code Ann. § 85-7-185 (1972). Since W & W was already in the case when Cumberland was made a party defendant, there was no need for a motion to intervene on the part of W & W. However, W & W was required to initiate at that time a crossclaim against Ransom and Cumberland in order to have its rights adjudicated as permitted by the 21 statute. W & W never did so. I have throughly searched the record and find that W & W never filed any sort of claim against Ransom or Cumberland. The record does reveal that W & W was given an opportunity by the trial judge to do so, but W & W declined, choosing instead to file only an amended response to Noble's complaint. ¶58. Since W & W failed to follow the statute which provided the remedy for it to have its rights adjudicated, I find that the trial court erred in adjudicating W & W rights to the interpled funds. But, even if W & W's response and amended response could be considered an assertion of a cross-claim against Ransom and Cumberland, and they certainly cannot, the trial court still committed reversible error in ordering that W & W's claim for $25,105.27 enjoyed priority status over Noble's claim. Again, section 85-7-185 makes it clear that W & W could not have priority over the obligee, for the rights of any materialmen or laborer, who intervenes in a suit brought against the surety on the bond of a contractor, are subject to the priority of the rights or claim for damages or otherwise, of the obligee. Miss. Code Ann. § 85-7-185 (1972). ¶59. I also find that the trial court erred in modifying the agreed judgment submitted to it by Noble and Ransom. For sure, the trial court was not obligated to sign the order as presented, but since it was an agreed judgment containing the terms and conditions upon which the parties were basing the resolution of their dispute, the court's only alternative would have been to submit the court-modified agreed judgment to the parties for their acceptance or rejection. If rejected, the court's only option would have been to set the matter down for hearing and resolution on the merits, requiring Noble to go forward and present its case. ¶60. For the reasons presented, I would reverse and render rather than reverse and remand because W & W was given a fair opportunity to have its claim to the interpled funds properly adjudicated in accordance with the provisions of section 85-7-185. It failed to present its claim. It now must bear the consequences of its decision. 22

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.