In re Application of Otter Tail Power Company for Authority to Increase Rates for Electric Service in Minnesota
Annotate this Case
The Supreme Court held that the Minnesota Public Utilities Commission (MPUC) lacks the authority to require Otter Tail Power Company to amend an existing transmission cost-recovery rider (TCRR) approved under Minn. Stat. 216B.16, subd. 7b(b) to include the costs and revenues associated with two high-voltage interstate transmission lines, known as the Big Stone Access Transmission Lines (Big Stone Lines).
In 2013, the MPUC approved Otter Tail's request for a TCRR for three transmission projects. In 2016, Otter Tail filed this general rate case with the MPUC seeking an annual-rate increase on its retail electricity sales to help offset company-wide investment costs and asserted that the costs and revenues associated with the Big Stone Lines should not be considered when setting the retail rates. The MPUC directed Otter Tail to amend the TCRR approved in 2013 to include the costs and revenues of the Big Stone Lines. The court of appeals reversed. The Supreme Court affirmed, holding that the MPUC does not have statutory authority to compel Otter Tail to include the Big Stone Lines in the TCRR.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.