MICHIGAN PIPE & VALVE-LANSING INC V HEBELER ENTERPRISES INC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
MICHIGAN PIPE & VALVE-LANSING, INC.,
UNPUBLISHED
March 22, 2011
Plaintiff/Counter-DefendantAppellee/ Cross-Appellant,
v
HEBELER ENTERPRISES, INC., WINDY
PINES VIEW, L.L.C., WILLIAM B. CHUNKO,
HEATHER M. CHUNKO, and CLINTON
COUNTY TREASURER,
No. 294530
Clinton Circuit Court
LC No. 08-010384-CZ
Defendants/Cross-Defendants,
and
FIRSTBANK-ST. JOHNS,
Defendant/Cross-DefendantAppellant/Cross-Appellee,
and
GRAND RIVER INFRASTRUCTURE, INC.,
Defendant/Counter-Plaintiff/CrossPlaintiff/Third-Party PlaintiffAppellee,
and
BRUCE HEBELER,
Third-Party Defendant.
Before: SHAPIRO, P.J., and HOEKSTRA and TALBOT, JJ.
PER CURIAM.
Appellant Firstbank-St. Johns (Firstbank) appeals as of right the judgment of foreclosure.
Specifically, Firstbank appeals the trial court’s order granting summary disposition under MCR
2.116(C)(10) to appellees Michigan Pipe & Valve-Lansing, Inc. (MPV) and Grand River
-1-
Infrastructure, Inc. (GRI) on MPV’s and GRI’s claim that their construction liens had priority
over its mortgage. MPV cross appeals the trial court’s order that its construction lien could not
include any sums representing a service charge. We affirm in part and reverse in part.
I. BASIC FACTS AND PROCEDURAL HISTORY
Windy Pines View, LLC (Windy Pines) is the owner of property in St. Johns, Michigan.
Windy Pines intended to develop the property into a 77-unit residential subdivision. To secure
financing for the project, Windy Pines granted a mortgage on the property to Firstbank.
Firstbank recorded the mortgage on February 10, 2005.
Two days earlier, on February 8, 2005, F&W Well Drilling, Inc. drilled a 245-foot deep
well on the property. A plastic casing was placed in the well from 140-feet below grade to onefoot above grade. The well, which was used to obtain a water sample from the aquifer below the
property, was capped after Windy Pines decided that the subdivision would be serviced by the
Bingham Township municipal water supply.
In 2007, Windy Pines contracted with Hebeler Enterprises, Inc. (Hebeler) to build the
“[i]nfrastructure and roads.” Hebeler purchased pipe and other materials from MPV and GRI.
Hebeler’s contract with GRI contained the following provision:
The undersigned agrees to pay GRI’s credit price for all amounts unpaid
after 30 days from invoice date. Under the credit price terms, time price
differential charges will accrue on all such amounts at the rate of 1.5% per month
(18% per annum). Accordingly, it is agreed that the timeliness of payment for the
goods and/or service provided is an integral part of the price of those goods and/or
services and is thus an integral part of this agreement.
MPV’s contract contained a somewhat similar provision: “For open credit sales, terms of
payment are NET 30 DAYS from invoice date. A service charge of 1-1/2% per month or any
lesser charge reflecting the maximum amount legally permissible will be added to all past due
accounts.”
Although it was paid in full by Windy Pines, Hebeler failed to pay MPV and GRI the
total amounts due under the contracts. Consequently, GRI filed a claim of lien against the
property in February 2008 and MPV filed a claim of lien in May 2008.
Thereafter, this litigation was commenced to foreclose on the liens. The parties filed
cross-motions for partial summary disposition under MCR 2.116(C)(10). Relevant to this
appeal, the issues were whether the well drilled days prior to the recording of Firstbank’s
mortgage constituted an “actual physical improvement” under MCL 570.1103(1) and whether
MPV could recover service charges as provided in its contract with Hebeler.
The trial court held that the drilling of the well on February 8, 2005, was an “actual
physical improvement” to the property and, therefore, pursuant to MCL 570.1119(1), the liens of
MPV and GRI had priority over Firstbank’s mortgage. The trial court found that the amount of
GRI’s lien was $46,459.24, plus sums representing the time-price differential charges of 1.5
-2-
percent per month. It found that the amount of MPV’s lien was $153,639.68 and did not include
any amounts for the 1.5 percent per month “service charge.”
II. STANDARDS OF REVIEW AND RULES OF STATUTORY INTERPRETATION
We review de novo a trial court’s decision on a motion for summary disposition. Maiden
v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). Summary disposition is proper under
MCR 2.116(C)(10) if “there is no genuine issue as to any material fact, and the moving party is
entitled to judgment or partial judgment as a matter of law.”
We also review de novo questions of statutory interpretation. Bates v Gilbert, 479 Mich
451, 455; 736 NW2d 566 (2007). The goal of statutory interpretation is to give effect to the
intent of the Legislature. Kuznar v Raksha Corp, 481 Mich 169, 176; 750 NW2d 121 (2008). If
the language of the statute is unambiguous, the Legislature is presumed to have intended the
meaning plainly expressed, and judicial construction is not permitted. Paris Meadows, LLC v
City of Kentwood, 287 Mich App 136, 141; 783 NW2d 133 (2010). An unambiguous statute
must be enforced as written. Klida v Braman, 278 Mich App 60, 64; 748 NW2d 244 (2008).
“[A] court may read nothing into an unambiguous statute that is not within the manifest intent of
the Legislature as derived from the words of the statute itself.” Roberts v Mecosta Co Gen Hosp,
466 Mich 57, 63; 642 NW2d 663 (2002). When a statute defines a given term, that definition
controls. Kuznar, 481 Mich at 176.
III. ACTUAL PHYSICAL IMPROVEMENT
On appeal, Firstbank argues that the trial court erred in holding that the well was an
“actual physical improvement.” We disagree.
MPV and GRI filed their lien claims under the Construction Lien Act (CLA), MCL
570.1101 et seq. MCL 570.1119(3) addresses the priority of construction liens:
A construction lien arising under this act shall take priority over all other
interests, liens, or encumbrances which may attach to the building, structure, or
improvement, or upon the real property on which the building, structure, or
improvement is erected when the other interests, liens, or encumbrances are
recorded subsequent to the first actual physical improvement.
The date of the “first actual physical improvement” is the date that construction liens attach to
the property for determining priority among competing liens and encumbrances. M D Marinich,
Inc v Mich Nat’l Bank, 193 Mich App 447, 454; 484 NW2d 738 (1992). The CLA defines
“actual physical improvement” as
the actual physical change in, or alteration of, real property as a result of labor
provided, pursuant to a contract, by a contractor, subcontractor, or laborer which
is readily visible and of a kind that would alert a person upon reasonable
inspection of the existence of an improvement. Actual physical improvement
does not include that labor which is provided in preparation for that change or
alteration, such as surveying, soil boring and testing, architectural or engineering
planning, or the preparation of other plans or drawings of any kind or nature.
-3-
Actual physical improvement does not include supplies delivered to or stored at
the real property. [MCL 570.1103(1).]
Firstbank advances two arguments in support of its claim that the well in this case is not
an actual physical improvement. Initially, it argues that the well does not met the definition of
an “actual physical improvement” because the well did not add any value to the property. In
support of this argument, it cites Barron’s Law Dictionary for the proposition that improvements
to real property are generally thought to increase the value of the property.
Firstbank’s reliance on a dictionary definition is unavailing because the CLA definition
of “actual physical improvement” controls. Kuznar, 481 Mich at 176. Further, nothing in the
unambiguous definition of “actual physical improvement,” MCL 570.1103(1), requires that the
improvement add value to the real property. We may not read such a requirement into the
definition. Roberts, 466 Mich at 63. Accordingly, we reject Firstbank’s argument that the well
was not an “actual physical improvement” because the well did not add value to the property.
Next, Firstbank asserts that the well falls within the exception of MCL 500.1103(1) for
“labor which is provided in preparation for that change or alteration . . . .” In doing so, Firstbank
does not suggest that the well was not an “actual physical change in . . . real property . . . which
[was] readily visible and of a kind that would alert a person upon reasonable inspection of the
existence of an improvement,” MCL 570.1103(1). But it does maintain that the exception
provided for in the definition encompasses what it calls the “due diligence process.” Under this
interpretation, Firstbank argues that the well was only a test well and therefore not an “actual
physical improvement.”
As defined in MCL 570.1103(1), an “actual physical improvement” does not “include
that labor which is provided in preparation for that change or alteration, such as surveying, soil
boring and testing, architectural or engineering planning, or the preparation of other plans or
drawings of any kind or nature.” Id. We do not dispute that these acts may suggest that the
definition in effect recognizes a “due diligence process” that involves the specific procedures
stated in the definition of “actual physical improvement.” Nor does the plain language of the
statute, which states “such as,” suggest that the list is exhaustive. However, none of the
procedures stated in the definition equates to the digging of a well, or any other act, which makes
a “readily visible” “physical change” to the property. To the contrary, the acts identified in the
statute are all of a nature that none of them will leave a permanent presence on the property.
Consequently, we find Firstbank’s assertion that the exception encompasses all acts done in the
“due diligence process” is not supported by the plain and unambiguous language of MCL
570.1103(1).
Because Firstbank’s mortgage was recorded subsequent to the digging of the well, which
was the “first actual physical improvement” to the property, the construction liens of MPV and
GRI had priority over Firstbank’s mortgage. MCL 570.1119(3). Accordingly, the trial court did
not err in granting priority to the liens of MPV and GRI.
IV. SERVICE CHARGE
-4-
On cross appeal, MPV argues that the trial court erred in holding that its construction lien
could not include any amounts for the “service charge” that was specified in its contract with
Hebeler. We agree.
MCL 570.1107(1) provides:
Each contractor, subcontractor, supplier, or laborer who provides an
improvement to real property has a construction lien upon the interest of the
owner or lessee who contracted for the improvement to the real property . . . . A
construction lien acquired pursuant to this act shall not exceed the amount of the
lien claimant’s contract less payments made on the contract.
Pursuant to the plain language of the statute, the amount of the lien is determined by the terms of
the contract. Erb Lumber Co v Homeowner Constr Lien Recovery Fund, 206 Mich App 716,
722; 522 NW2d 917 (1994). Here, the terms of MPV’s contract with Hebeler provided that a
“service change” of 1.5 percent per month would be added to all past due amounts.
The trial court relied on Erb Lumber Co, 206 Mich App 716, to conclude that MPV could
not include in its lien an amount representing the service charge. In Erb Lumber Co, the
supplier’s contract provided that payment for materials must be made within 150 days of
delivery and, if not, a time-price differential charge of two percent per month would be added
until the total was fully paid. The Homeowner Construction Lien Recovery Fund agreed to pay
the entire amount of the supplier’s lien except for the time-price differential charges. It argued
that the time-price differential was a finance charge and could not be considered part of the
contract. This Court disagreed. Id. at 721. It reasoned:
[P]laintiff here relies on the terms of the contract to establish its costs. By
including a time-price differential, plaintiff essentially set differing costs for the
materials depending on when they were paid for after delivery. . . . [S]ince the
contract terms established the cost of the materials, and profit and overhead were
included, plaintiff is entitled to recover the time-price differential as well.
Furthermore, the statute here clearly contemplates that recovery is based on the
value of the contract less amounts already paid. [Id.]
According to the trial court, because “there is a difference between [a] time price differential and
a periodic interest rate,” Erb Lumber Co did not permit MPV to secure payment of the service
charge with its lien claim. We agree that a time-price differential is different than an interest
payment or a service charge. A time-price differential relates the cost of an item to the method
of payment. See Grand Blanc Cement Prod v Ins Co of North America, 225 Mich App 138, 149
n 3; 571 NW2d 221 (1997) (“A time-price differential charge is the difference between the cash
and credit price, the latter being higher.”).1 However, based on MCL 570.1107(7), we conclude
1
Black’s Law Dictionary (7th ed) provides similar definitions: “1. A figure representing the
difference between the current cash price of an item and the total cost of purchasing it on credit.
-5-
that any distinction between a time-price differential and a service change, when contained in the
contract, is a distinction without a difference for purposes of MCL 570.1107(1).
MCL 570.1107(7) provides:
After the effective date of the amendatory act that added this subsection, a
construction lien of a subcontractor or supplier for an improvement to a
residential structure shall only include an amount for interest, including, but not
limited to, a time-price differential or a finance charge, if the amount is in
accordance with the terms of the contract between the subcontractor or supplier
and the contractor or subcontractor and does not include any interest that accrues
after 90 days after the claim of lien is recorded.
Subsection (7) was added to the CLA in 2006. See 2006 PA 497.2 According to Legislative
Analyses, the Legislature added subsection (7) to help ensure the solvency of the Home Owner
Construction Lien Recovery Fund. See Senate Legislative Analyses, SB 405, SB 459, January 8,
2007, and November 21, 2006. The analyses explained that payments from the Fund were more
than had been anticipated—due, in part, from interest added to amounts owed by contractors—
and to ensure that the Fund remained solvent, interest paid from the Fund should be limited. Id.
Thus, MCL 570.1107(7) limited the amount of “interest” that could be included in a lien filed
against a residential structure: the amount of “interest” may not include “any interest” that
accrues after 90 days of the claim of lien being recorded.
The parties agree that because MPV did not provide supplies for an improvement to a
“residential structure,”3 MCL 570.1107(7) does not apply to the present case. However, because
“statutory provisions are not to be read in isolation; rather, context matters, and thus statutory
provisions are to be read as a whole,” Robinson v Lansing, 486 Mich 1, 15; 782 NW2d 171
(2010) (emphasis deleted), subsection (7) of MCL 570.1107 aids in the interpretation of
subsection (1).
MCL 570.1107(7) provides that a lien against a residential structure may include an
amount for “interest,” so long as (1) the amount is in accordance with the terms of the contract
and (2) the amount does not include any interest that accrues 90 days after the claim of lien is
recorded. The “interest” that may be included in the lien is that “including, but not limited to, a
time-price differential or a finance charge[.]” “The word ‘includes’ can be used as a term of
enlargement or limitation[.]” Thorn v Mercy Mem Hosp Corp, 281 Mich App 644, 650; 761
2. The difference between a seller’s price for immediate cash payment and a different price
when payment is made later or in installments.”
2
It took effect on January 3, 2007.
3
A “residential structure” is defined by the CLA as “an individual residential condominium unit
or a residential building containing not more than 2 residential units, the land on which it is or
will be located, and all appurtenances, in which the owner or lessee contracting for the
improvement is residing or will reside upon completion of the improvement.” MCL
570.1106(3).
-6-
NW2d 414 (2008) (quotation omitted). It is clear from the context in which it is used in MCL
570.1107(7)—“including, but not limited to”—that the word “including” in subsection (7) is a
term of enlargement. Thus, the specific types of “interest” that are listed in subsection (7), timeprice differentials and finance charges, are specific examples of “interest” that may be included
in the claim of lien, and not an exhaustive list. See id. at 651.
We conclude that the service charge contained in MPV’s contract with Hebeler would
fall within the scope of the “amount of interest” that could be included in a lien under MCL
570.1107(7). Interest is “[t]he compensation fixed by agreement or allowed by law for the use or
detention of money, or for the loss of money by one who is entitled to its use; esp., the amount
owed to a lender in return for the use of borrowed money.” Black’s Law Dictionary (7th ed). A
service charge, as pertinent to this case, is “[t]he sum . . . of all charges payable by the buyer and
imposed by the seller as an incident to the extension of credit.” Id. Thus, like a time-price
differential and a finance charge, which is “[a]n additional payment, usu. in the form of interest,
paid by a retail buyer for the privilege of purchasing goods or services in installments,” id., a
service fee is an amount owed in return for the privilege of purchasing goods or services with
credit.
Pursuant to MCL 570.1107(1), the amount of a construction lien is determined by the
terms of the contract. Erb Lumber Co, 206 Mich App at 722. MCL 570.1107(7) places an
additional limitation on the amount of a lien on a residential structure: any “amount of interest,”
which is in accordance with the contract terms, may not include interest that accrues more than
90 days after the claim of lien was filed. An unharmonious result would be reached if “interest”
that is permitted under MCR 570.1107(7) to be included in a construction lien claim against a
residential structure could not be included in all other construction lien claims, especially where
subsection (7) was enacted to limit the lien amounts against residential structures. Accordingly,
reading MCL 570.1107(1) and (7) together to produce a harmonious result, we hold that the
“amount of the lien claimant’s contract” includes all “interest” charges that are contemplated by
the contract. Because the service charge of 1.5 percent per month on all past due amounts is an
“interest” charge that was contemplated in MPV’s contract with Hebeler,” MPV was entitled to a
lien that included a sum representing the service charge. The trial court erred in holding to the
contrary. We reverse that portion of the order regarding motions for partial summary disposition
and the judgment of foreclosure that precluded MPV from including in its lien a sum
representing the service charge.
Affirmed in part, reversed in part.
/s/ Douglas B. Shapiro
/s/ Joel P. Hoekstra
/s/ Michael J. Talbot
-7-