MILJEVICH CORP V NORTH COUNTRY BANK & TRUST
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
MILJEVICH CORPORATION,
UNPUBLISHED
August 16, 2007
Plaintiff-Appellee/Cross-Appellant,
v
No. 268356
Ontonagon Circuit Court
LC No. 04-000094-CK
NORTH COUNTRY BANK & TRUST,
Defendant-Appellant/CrossAppellee.
Before: Whitbeck, C.J., and Talbot and Zahra, JJ.
PER CURIAM.
In this breach of contract action, defendant appeals as of right, and plaintiff cross-appeals
as of right, a judgment entered in favor of plaintiff following a bench trial. We reverse and
remand for entry of a judgment of no cause of action in favor of defendant.
On December 21, 1998, Eli Miljevich, the president of plaintiff Miljevich Corporation,
executed a $1,464,650 business loan agreement with defendant North Country Bank and Trust.
The loan note provided that the interest rate on the loan was “[o]ne and one-half percent (1
1/2%) per annum above the ‘prime’ rate as published from time-to-time by the Bank as its ‘prime
rate.’” Eli died in October 1999. His wife, Kathleen Miljevich, became plaintiff’s president. In
December 1999, Kathleen met with the bank officer who negotiated the terms of the loan with
Eli, in part, in an effort to obtain a lower interest rate on the loan to reduce the monthly
payments. At that time, Kathleen did not know what the interest rate was on the loan. At the
meeting, the bank officer did not tell Kathleen what the interest rate was. Following the meeting,
defendant’s employees repeatedly failed to respond to Kathleen’s inquiries regarding the
applicable interest rate. In September 2003, plaintiff refinanced the loan and paid, in full, the
amount owing to defendant. Thereafter, plaintiff initiated this action against defendant, alleging
that defendant breached the terms of the loan agreement by failing to publish its internal prime
rate (“NCB prime”), failing to inform plaintiff about what NCB prime was, and by overcharging
interest on the loan.
Following a bench trial, the trial court found that the parties’ agreement was
unambiguous, yet incomplete. The court reasoned that, because defendant failed to publish NCB
prime, as provided in the note, defendant could not apply NCB prime to the loan. The parties’
agreement did not mention any other interest rate. Thus, the trial court applied what it
determined to be a “reasonable” interest rate to the loan: Wall Street Journal prime (“WSJ
-1-
prime”) plus 1 1/2 percent. WSJ prime was lower than NCB prime. The trial court awarded a
judgment to plaintiff in the amount of $140,326.78, which included $113,567.22 in damages for
the overpayment of interest, $6,291.56 in judgment interest, $380 in costs, and $20,088 in case
evaluation sanctions pursuant to MCR 2.403. This appeal followed.
Plaintiff and defendant contend that the trial court erred in applying an interest rate of
WSJ prime plus 1 1/2 percent to the loan. Defendant contends, on appeal, that the trial court
should have applied an interest rate of NCB prime plus 1 1/2 percent to the loan, as provided in
the loan note. Plaintiff contends, on cross-appeal, that the trial court should have applied an
interest rate of 1 1/2 percent to the loan.
Following a bench trial, we review a trial court’s factual findings for clear error and its
conclusions of law de novo. Glen Lake-Crystal River Watershed Riparians v Glen Lake Ass’n,
264 Mich App 523, 531; 695 NW2d 508 (2004). A finding is clearly erroneous when, although
there is evidence to support the finding, the reviewing court on the entire record is left with a
definite and firm conviction that a mistake has been made. Id. “Moreover, questions involving
the proper interpretation of a contract or the legal effect of a contractual clause are also reviewed
de novo.” Rory v Continental Ins Co, 473 Mich 457, 464; 703 NW2d 23 (2005).
“The primary goal in the construction or interpretation of any contract is to honor the
intent of the parties.” Klapp v United Ins Group Agency, Inc, 468 Mich 459, 473; 663 NW2d
447 (2003) (citation omitted). “To do so, this Court reads the agreement as a whole and attempts
to apply the plain language of the contract itself.” Old Kent Bank v Sobczak, 243 Mich App 57,
63; 620 NW2d 663 (2000). “[C]ourts must give effect to every word, phrase, and clause in a
contract and avoid an interpretation that would render any part of the contract surplusage or
nugatory.” Klapp, supra at 468. “An unambiguous contract must be enforced according to its
terms.” DaimlerChrysler Corp v G-Tech Professional Staffing, Inc, 260 Mich App 183, 185;
678 NW2d 647 (2003).
Defendant concedes that it did not publish the NCB prime rate, as provided in the note.
Trial testimony established that information regarding NCB prime was not disseminated to the
public in the newspaper, on television, or on the radio. NCB prime was not documented on a
placard in defendant’s branch offices. Defendant’s customers did not have access to the
computer system where the changes in NCB prime were logged. The only way for a customer to
learn of the NCB prime rate was to go to the bank and speak to a lender. Defendant’s failure to
publish NCB prime constituted a breach of the parties’ agreement. When performance of a
contractual obligation is due, . . . “anything short of full performance is a breach, even if the
party who does not fully perform was not at fault and even if the defect in his performance was
not substantial.” Woody v Tamer, 158 Mich App 764, 772; 405 NW2d 213 (1987), quoting
Restatement Contracts, 2d, § 235, Comment b, p 212.
Nevertheless, defendant’s breach did not preclude defendant from charging interest on
the loan at the rate of NCB prime plus 1 1/2 percent. Based on the plain language of the parties’
contract, we are satisfied that the parties intended that the applicable interest rate would be NCB
prime plus 1 1/2 percent. Neither the term loan agreement nor the loan note mentions any
interest rate other than NCB prime plus 1 1/2 percent. Nothing in the parties’ agreement
suggests that the parties intended any other interest rate to apply to the loan, even in the event
that defendant failed to publish the NCB prime rate. “Too much regard is not to be had to the
-2-
proper and exact signification of words and sentences, so as to prevent the simple intention of the
parties from taking effect.” Hustina v Grand Trunk Western R Co, 303 Mich 581, 586-587; 6
NW2d 902 (1942). See also Stark v Budwarker, Inc, 25 Mich App 305, 314; 181 NW2d 298
(1970).
Thus, the trial court erred in applying an interest rate of WSJ prime plus 1 1/2 percent to
the loan. Under some circumstances where a contract is incomplete, “the law supplies the
missing details by construction.” Muci v State Farm Mut Automobile Ins Co, 267 Mich App
431, 440-441; 705 NW2d 151 (2005) (citation omitted). However, contrary to the trial court’s
finding, the parties’ agreement was not incomplete. The agreement provided the applicable
interest rate. Moreover, “courts will presume reasonable terms unless the parties express a
contrary intention.” Kojaian v Ernst, 177 Mich App 727, 731; 442 NW2d 286 (1989) (emphasis
added). The note in this case expressly provided that the interest rate was NCB prime plus 1 1/2
percent. Thus, there was no basis for the trial court to apply what it determined to be a
“reasonable” interest rate to the loan. “When a court abrogates unambiguous contractual
provisions based on its own independent assessment of ‘reasonableness,’ the court undermines
the parties’ freedom of contract.” Rory, supra at 468-469.
[U]nless a contract provision violates law or one of the traditional
defenses to the enforceability of a contract applies, a court must construe and
apply unambiguous contract provisions as written. We reiterate that the judiciary
is without authority to modify unambiguous contracts or rebalance the contractual
equities struck by the contracting parties because fundamental principles of
contract law preclude such subjective post hoc judicial determinations of
“reasonableness” as a basis upon which courts may refuse to enforce
unambiguous contractual provisions. [Id. at 461.]
In refusing to apply NCB prime plus 1 1/2 percent to the loan, the trial court failed to apply the
plain language of the contract itself and, thereby, failed to honor the intent of the parties. Id. at
468; DaimlerChrysler Corp, supra at 185.
We reject plaintiff’s contention that, because defendant failed to publish the NCB prime
rate, the only interest rate that defendant could have applied to the loan was 1 1/2 percent. We
agree with the trial court that defendant’s failure to publish the NCB prime rate was not the same
as defendant publishing a prime rate of zero percent, which would have resulted in an interest
rate of 1 1/2 percent under the terms of the note. Further, applying an interest rate of 1 1/2
percent to the loan would not only be contrary to the parties’ intent, as expressed in the plain
language of their agreement, but would, in effect, punish defendant for breaching the contract.
“[T]he goal in contract law is not to punish the breaching party, but to make the nonbreaching
party whole.” Corl v Huron Castings, Inc, 450 Mich 620, 625-626; 544 NW2d 278 (1996).
Defendant next contends that plaintiff failed to prove that it suffered any damages as a
result of defendant’s breach of the agreement. Therefore, the trial court erred in awarding
plaintiff a money judgment.
“In an action based on contract, the parties are entitled to the benefit of the bargain as set
forth in the agreement.” Ferguson v Pioneer State Mut Ins Co, 273 Mich App 47, 54; 731
NW2d 94 (2006). “The remedy for breach of contract is to place the nonbreaching party in as
-3-
good a position as if the contract had been fully performed.” Corl, supra at 625. “[T]he
damages recoverable for breach of contract are those that arise naturally from the breach or those
that were in the contemplation of the parties at the time the contract was made.” Kewin v
Massachusetts Mut Life Ins Co, 409 Mich 401, 414; 295 NW2d 50 (1980). “The party asserting
a breach of contract has the burden of proving its damages with reasonable certainty, and may
recover only those damages that are the direct, natural, and proximate result of the breach.” Alan
Custom Homes, Inc v Krol, 256 Mich App 505, 512; 667 NW2d 379 (2003).
Plaintiff alleges that it suffered damages because it “was overcharged interest.”
However, the evidence does not support plaintiff’s assertion. Plaintiff’s own expert witness
testified that the interest that plaintiff paid on the loan was consistent with NCB prime plus 1 1/2
percent, the interest rate that the parties intended to apply to the loan. Nothing in the record
indicates that defendant charged plaintiff an interest rate higher than NCB prime plus 1 1/2
percent during the loan repayment period. Because plaintiff negotiated an interest rate of NCB
prime plus 1 1/2 percent, and paid an interest rate of NCB prime plus 1 1/2 percent, plaintiff
received the benefit of the bargain as set forth in the parties’ agreement. Ferguson, supra at 54.
In other words, plaintiff was not entitled to any damages because defendant’s breach of the
contract was, as to plaintiff, damnum absque injuria, or “damage without injury.” Michigan
Dep’t of Transportation v Tomkins, 270 Mich App 153, 161; 715 NW2d 363 (2006). Had
defendant published the NCB prime rate “from time-to-time,” as provided in the note, the actual
interest rate that plaintiff paid on the loan would not have changed. Defendant’s act of
publishing the NCB prime rate would not have changed the manner in which the interest was
calculated on the loan, and would not have changed any of the terms of the loan. Thus, the trial
court erred in determining that plaintiff suffered any measurable damages as a result of
defendant’s breach of the agreement. See Crawford v Cicotte, 186 Mich 269; 152 NW 1065
(1915).
Plaintiff asserts that, “had the Defendant published it’s internal prime rate, the Plaintiff
very well would have refinanced it’s [sic] loan sooner than it did.” However, plaintiff failed to
present any evidence to support this assertion. These alleged damages are purely speculative in
nature. “A plaintiff asserting a cause of action has the burden of proving damages with
reasonable certainty, and damages predicated on speculation and conjecture are not recoverable.”
Health Call of Detroit v Atrium Home & Health Care Services, Inc, 268 Mich App 83, 96; 706
NW2d 843 (2005). “[D]amages which are purely speculative in character, and dependent on so
many contingencies that they cannot be traced with reasonable certainty to the breach of the
contract, are not allowable.” Valley Die Cast Corp v A C W Inc, 25 Mich App 321, 338-339; 181
NW2d 303 (1970) (citation omitted). Thus, plaintiff failed to establish that it suffered any
damages as a result of defendant’s breach.
Plaintiff contends, on cross-appeal, that the interest it paid on the loan was unlawful and,
thus, it is entitled to return of all of the interest that it paid to defendant. Plaintiff’s argument is
based on the following provision in the note:
In no event shall the interest rate exceed the maximum rate allowed by
law; any interest payment which would for any reason be deemed unlawful under
applicable law shall be applied to principal.
-4-
Plaintiff’s argument is without merit. This provision was drafted to address a
circumstance where a contract or note charges a usurious interest rate. A contract or promissory
note charges a usurious interest rate where it charges interest at a rate that exceeds the interest
allowed under the applicable law. See Washburn v Michailoff, 240 Mich App 669, 674; 613
NW2d 405 (2000). “[W]hen a lender seeks to enforce a usurious contract, the borrower is
entitled to have any previously paid interest applied against the outstanding principal.” Id. at
674. The note in this case did not charge a usurious interest rate; the interest rate did not exceed
the maximum rate allowed by law. See MCL 438.61; MCL 450.1275. Thus, there was no basis
for plaintiff to assert that the interest rate that it agreed to pay was unlawful. Plaintiff was bound
to pay the interest rate promised in writing and cannot raise the defense of usury to argue that the
interest should have been applied to principal and, therefore, it is entitled to a return of all of the
interest. See Kleanthous v First of Chelsea Corp, 201 Mich App 440, 441-442; 507 NW2d 2
(1993). Thus, plaintiff failed to establish that it was entitled to any relief on its breach of
contract claim.
We reverse the judgment entered in favor of plaintiff and remand this matter to the trial
court for entry of a judgment of no cause of action in favor of defendant. We do not retain
jurisdiction.
/s/ William C. Whitbeck
/s/ Michael J. Talbot
/s/ Brian K. Zahra
-5-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.