FLANDERS INDUSTRIES INC V STATE OF MICHIGAN
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
FLANDERS INDUSTRIES, INC., d/b/a LLOYD
FLANDERS INDUSTRIES, INC.,
UNPUBLISHED
November 18, 2003
Plaintiff-Appellant,
v
STATE OF MICHIGAN, DEPARTMENT OF
ENVIRONMENTAL QUALITY, and RUSSELL
J. HARDING,
No. 240789
Court of Claims
LC No. 01-018002-CM
Defendants-Appellees.
Before: Smolenski, P.J., and Murphy and Wilder, JJ.
PER CURIAM.
Pursuant to an administrative order issued on September 17, 1992 (1992 Order), by the
Department of Natural Resources (DNR) (now the Department of Environmental Quality
“DEQ”)1, plaintiff incurred significant costs in cleaning up the contamination of paint sludge at
its facility, on the shores of Lake Michigan, and in the bottomlands of Lake Michigan. After
plaintiff’s satisfactory completion of the remedial action plan in January 2001, plaintiff
unsuccessfully petitioned the DEQ for reimbursement of the response activity costs it incurred in
relation to the contaminated submerged bottomlands, accepting liability regarding the other
areas. In accordance with MCL 324.20119(5), plaintiff filed this action alleging that it was not
liable for the response activity costs pertaining to the submerged bottomlands (count I) and that it
was entitled to reimbursement of its costs expended before the 1992 Order was entered (count
II). The court granted defendants’ motion for summary disposition on count I, pursuant to MCR
2.116(C)(10), and on count II, pursuant to MCR 2.116(C)(8). Plaintiff appeals as of right. We
affirm.
A trial court's decision to grant or deny summary disposition is reviewed de novo by this
Court. MacDonald v PKT, Inc, 464 Mich 322, 332; 628 NW2d 33 (2001). “A motion for
summary disposition pursuant to MCR 2.116(C)(10) tests the factual support of a claim. The
motion should be granted if the evidence demonstrates that no genuine issue of material fact
1
MCL 324.99903, effective October 1, 1995.
-1-
exists, and that the moving party is entitled to judgment as a matter of law.” Id.; citations
omitted. Statutory interpretation is a question of law that is also reviewed de novo on appeal.
Eggleston v Bio-Medical Applications of Detroit, Inc, 468 Mich 29, 32; 658 NW2d 139 (2003).
Plaintiff asserts that it is not liable under MCL 299.612(1), which provides:
Notwithstanding any other provision or rule of law and subject only to the
defenses set forth in sections 12a and 12b, if there is a release or threatened
release from a facility that causes the incurrence of response activity costs, the
following persons shall be liable under this section:
(a) The owner or operator of the facility.
(b) The owner or operator of the facility at the time of disposal of a hazardous
substance.
(c) The owner or operator of the facility since the time of disposal of a hazardous
substance not included in subdivision (a) or (b).
(d) A person that by contract, agreement, or otherwise arranged for disposal or
treatment, or arranged with a transporter for transport for disposal or treatment, of
a hazardous substance owned or possessed by the person, by any other person, at
the facility owned or operated by another person and containing the hazardous
substance.
(e) A person that accepts or accepted any hazardous substance for transport to the
facility selected by that person.
Any person that falls into one of these categories is considered a potentially responsible party
(PRP) and is jointly and severally liable; liability is strict. Port Huron v Amoco Oil Co, Inc, 229
Mich App 616, 622; 583 NW2d 215 (1998).
The primary goal of judicial interpretation of statutes is to ascertain and give effect to the
intent of the Legislature. Gladych v New Family Homes, Inc, 468 Mich 594, 597; 664 NW2d
705 (2003). Nothing will be read into a clear statute that is not within the manifest intention of
the Legislature as derived from the language of the statute itself. Roberts v Mecosta Co Gen
Hosp, 466 Mich 57, 63; 642 NW2d 663 (2002). If the language of a statute is clear, no further
analysis is necessary or allowed. Eggleston, supra at 32.
Plaintiff’s argument is two-fold: (1) the statute requires that an owner or operator is
liable only if there was a release during the time of its ownership; and (2) since no releases
occurred during plaintiff’s ownership of the facility, it cannot be held liable for the release that
occurred during Heywood-Wakefield’s ownership because plaintiff is not Heywood-Wakefield’s
successor. Regarding plaintiff’s first argument, that in order to be held liable the release must
have occurred during its ownership, we agree in part. But our partial concurrence does not
afford plaintiff any relief.
-2-
MCL 229.612 is a strict liability statute that imposes liability on five categories of
persons “if there is a release … that causes the incurrence of response activity costs . . . .”2 Port
Huron, supra at 622. The statute does not provide a timeframe of when the release had to occur.
Reading the statute as a whole, we believe that the specific timing of the release is irrelevant in
establishing liability as a PRP under MCL 299.612. The statute only indicates that a release
must occur that causes the need for response activities, the cost of which falls on the persons
listed in subsection (1). Therefore, the key is the incurrence of response activity costs, not the
timing of the release. In this case, as long as plaintiff is found to be the owner of the facility, it is
a PRP who is liable for the cleanup costs. This conclusion is supported by the MERA’s
definition of a facility, which includes any area “where a hazardous substance has been released
. . . .” MCL 299.603(m); emphasis added.
This conclusion is also supported by the Legislature’s decision to structure such a
comprehensive strict liability scheme that includes past and present owners/operators and
provides for limited enumerated defenses. Because the MERA was “patterned after” and was
similar in intent to the federal Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA), 42 USC 9601 et seq., it is appropriate to look to federal case law
interpreting CERCLA. Flanders, supra at 21. As a federal district court stated succinctly in
Lincoln Properties, Ltd v Higgins, 823 F Supp 1528, 1536-1537 (ED Cal, 1992),
An owner or operator of a facility, from which there has been a release, is
subject to the Act, unless one of the narrowly stated defenses applies. Once
liability is found, a court may apportion the cleanup costs to reflect relative
responsibility. . . .
CERCLA is a strict liability statute with few defenses. One of its primary
purposes is to encourage cleanup. It envisions that sometimes the cleanup must
be paid for by those least responsible because those who are most responsible lack
funds or cannot be found. It tempers its severity with an apportionment principle
and with limited defenses that are rarely available. [Citations omitted.]
2
Before 1995, the statutes at issue were collectively known as the Michigan Environmental
Response Act (“MERA”), MCL 299.601 et seq. Pursuant to 1994 PA 451, effective March 30,
1995, the Natural Resources and Environmental Protection Act (“NREPA”), MCL 324.1 et seq.,
was enacted. The MERA was repealed and its statutes were recodified in Part 201 of NREPA.
The provision under the MERA that delineated liability under the act, MCL 299.612, was
substantively changed in the NREPA provision, MCL 324.20126, pursuant to 1995 PA 71,
which was effective June 5, 1995. However, NREPA provided that the MERA provisions in
effect on May 1, 1995, would control in any case where an administrative order was issued
pursuant to [MCL 299.610f] on or before this date. MCL 324.20102a(1)(b). Therefore, all
statutory references, unless otherwise noted, refer to the MERA provisions.
-3-
Thus, if plaintiff was truly only liable by virtue of it being the current owner of the facility, then
it could have invoked such a defense under MCL 299.612a as an innocent purchaser.3 To that
end, the timing of the release would be relevant. But plaintiff never raised this defense.4
Plaintiff contends that this Court’s previous decision in Flanders Industries, Inc v State of
Michigan, 203 Mich App 15; 512 NW2d 328 (1993), sanctions its interpretation of the statute as
requiring a “current” release. We find no support in Flanders for plaintiff’s contention. Any
discussion related to “releases” was in relation to plaintiff’s injunctive relief request. MCL
299.615 provides that a private citizen can bring an action against the owner/operator for
injunctive relief. In discussing the many proper grounds for dismissing this claim,5 the Flanders
Court noted that no releases were imminent. This was important because without the prospect of
future releases, there was no activity to enjoin. The Flanders Court did not decide that a
“current” release had to occur in order to hold a current owner liable as a PRP.
Plaintiff also cites In re Acushnet River & New Bedford Harbor, 722 F Supp 893 (D
Mass, 1989), in support of its contention that it cannot be liable if no releases occurred during its
ownership of the facility. Plaintiff’s reliance is misplaced. In In re Acushnet River, the federal
government brought a recovery of response costs action against several PRPs. As to one PRP,
the court held that summary disposition was not proper on the issue of whether the government
had incurred response costs within the meaning of 42 USC 9607 because it had not established
that the response costs they incurred were caused by a release from the facility while the PRP
owned it. Id. at 900. The critical distinction is that in In re Acushnet River, the other PRPs were
also defendants in the case, and thus, the percentage of response costs had to be allocated among
the PRPs, which necessarily required a fault inquiry. The government was not seeking to hold
only one PRP jointly and severally liable.
Plaintiff asserts that it is not liable for the cleanup costs of the submerged bottomlands
because it does not own the bottomlands and it did not cause the contamination there. But
neither of these factors is material in this case. Causation is irrelevant because liability under the
MERA is strict. Port Huron, supra at 622. And whether plaintiff actually holds title to the
submerged bottomlands is immaterial because it is undisputed that plaintiff is the current owner
of the facility from where the contaminants originated. MCL 299.612(1)(a).
Plaintiff attempts to bifurcate its responsibility by asserting that the uplands and
bottomlands constitute two separate and distinct facilities, and because it does not “own” the
3
The other defenses provided for in MCL 299.612a are not applicable in this case.
4
We note that plaintiff raised this defense in the prior related action, Flanders, supra at 23 n 4,
but failed to raise it in this separate cause of action for reimbursement of the cleanup costs.
5
The Flanders Court affirmed dismissal of this claim, finding that plaintiff had no standing to
bring the action because MCL 299.615 provides for a cause of action to be brought only by a
private citizen whose “health or enjoyment of the environment” may be adversely affected by the
release. Flanders, supra at 32-34.
-4-
submerged bottomlands “facility,” it is not liable as an owner under MCL 299.612.6 Given the
Legislature’s express intent to hold each responsible party liable for its own response activity
costs, we conclude that the MERA does not support such an interpretation; one that would allow
a person to avoid liability under MCL 299.612 simply because the released contaminants
traveled outside their titled property. To the contrary, the MERA’s definition of owner indicates
that plaintiff cannot avoid liability on a “lack of ownership” defense. An owner is one who owns
a facility. MCL 299.603(u). But an owner does not include a person who can prove:
(A) The release was caused solely by a third party, who is not an employee or
agent of the person, or whose action was not associated with a contractual
relationship with the person.
(B) The hazardous substance was not deposited, stored, or disposed of on that
person's property.
(C) The person at the time of transfer of the property discloses any knowledge or
information concerning the general nature and extent of the release as required in
section 10c. [MCL 299.603(u)(iii).7]
Here, it is undisputed that the paint sludge was deposited, stored, and disposed of on the property
that plaintiff undisputedly owns. Notably, the exception does not provide that the release has to
occur on the person’s property.
The MERA defines “facility” as “any area, place, or property where a hazardous
substance has been released, deposited, stored, disposed of, or otherwise comes to be located.”
MCL 299.603(m); emphasis added. This definition is broad enough to encompass the
submerged bottomlands, especially when read in conjunction with the MERA’s definition of
“release.” Release is a broad definition that includes disposal, but also includes passive
movement such as leaking, emitting, escaping, and leaching. MCL 299.603(x); Bob’s Beverage,
Inc v Acme, Inc, 264 F3d 692, 696-697 (CA 6, 2001) (interpreting release and disposal under
CERCLA). Because the contaminates originated from the facility that plaintiff owns, the court
correctly concluded that, for purposes of plaintiff’s liability under the MERA, the affected areas
constituted a single facility. Therefore, plaintiff is liable as a PRP for the cleanup costs of the
submerged bottomlands and hence, is not entitled to reimbursement of response activity costs
incurred pursuant to the 1992 Order. The court properly granted defendants’ motion for
summary disposition regarding count I.
Plaintiff also argues that City Mgt Corp v US Chemical Co, Inc, 43 F3d 244 (CA 6,
1994), supports its contention that it would be liable for the cleanup of the submerged
6
Plaintiff contends that it does not own any of the submerged bottomlands. Defendants assert
that plaintiff’s deed covered at least a portion of the submerged bottomlands, apparently
conceding that there is a portion plaintiff does not own.
7
The statute provides other definitions of those who are not “owners,” but none are applicable to
this case.
-5-
bottomlands of the lake only if it was Heywood-Wakefield’s successor. However, City Mgt is
distinguishable. In that case, the defendant US Chemical (USC) was in the business of solvent
reclamation. Some of these solvents were disposed of at its facility and others were transported
to off-site landfills, including the one at issue, Metamora Landfill. Id. at 246-247. In 1990, the
plaintiff bought USC’s facility and expressly assumed USC’s liability for the contamination at
the facility, which the plaintiff had discovered through its own investigations before executing
the purchase agreement. During negotiations, USC was notified that it was a potentially
responsible party for contamination at the Metamora Landfill. USC did not disclose this fact to
the plaintiff. Id. at 247-248. When a group of the other defendants sought to impose liability on
the plaintiff, plaintiff filed suit for a declaratory judgment of no liability. The Sixth Circuit held
that the plaintiff was not liable for the cleanup of the Metamora Landfill as a successor
corporation. Id. at 253.
There are two critical distinctions between City Mgt and this case. First, USC did not
own the landfill and thus, could not be held liable under 42 USC 9607(a) as an owner or
operator. UCS’s liability was as a “generator” of hazardous waste under 42 USC 9607(a)(3).
Second, the facility where the contamination occurred was the landfill. Therefore, the plaintiff
could only be held liable if it was determined to be a successor corporation of USC. In this case,
because the release occurred at plaintiff’s facility, it can be held liable under MCL 299.612(1)(a)
as a current owner of the facility. The issue of successorship is irrelevant.
Plaintiff further asserts that Flanders, supra, acknowledged that plaintiff’s liability
depended on its status as a successor corporation to Heywood-Wakefield. Plaintiff misinterprets
the Court’s analysis. The Flanders Court affirmed the dismissal of plaintiff’s first claim, which
sought a declaratory judgment of no liability, on the ground that the circuit court had no
jurisdiction to hear the case because the DNR had not yet instituted a cost recovery action.
Flanders, supra at 22. The Court noted that if the DNR instituted such an action, “plaintiff will
have ample opportunity to present the defenses outlined in its complaint,” which included an
assertion that plaintiff was not Heywood-Wakefield’s successor. Id. at 22-23 n 4. Plaintiff had
argued that one of the reasons it was not liable was because it did not own the contaminated
bottomlands. In addressing this contention, the Court stated that current ownership of the
bottomlands was irrelevant for two reasons: (1) plaintiff owned the land where the contaminates
were originally released from and thus, the bottomlands were part of the facility as defined in
MCL 299.603(u); and (2) under a successor argument, plaintiff could be liable under MCL
299.612(1)(b), which assigns liability to the owner at the time the hazardous substance was
disposed of. The Flanders Court did not address MCL 299.612(1)(a), which assigned liability to
a person merely because it was the current owner of the facility, because it was not raised in
plaintiff’s complaint in that case. We conclude that Flanders cannot be read as sanctioning
plaintiff’s assertion that it can only be held liable under MCL 299.612 if it is found to be
Heywood-Wakefield’s successor.
Plaintiff argues that even if it is determined to be liable, it should be given the
opportunity on remand to limit its liability by establishing that the harm was divisible and caused
by Heywood-Wakefield. Because plaintiff is a PRP under MCL 299.612, and thus not entitled to
reimbursement from the state under MCL 324.20119(5), plaintiff had two avenues for recovering
the portion of its total expended clean up costs that related to the submerged bottomlands.
Plaintiff could have institute a cost recovery action under either MCL 299.612 or MCL
-6-
299.612c. See Centerior Service Co v Acme Scrap Iron & Metal Corp, 153 F3d 344, 347 (CA 6,
1998). As the Sixth Circuit explained, interpreting the corresponding CERCLA provisions, 42
USC 9607 and 42 USC 9613 respectively,
Any party may seek response costs regardless of its status as a liable or potentially
liable party. Whether that party may seek joint and several cost recovery, or is
limited to an action for contribution governed by § 113(f), however, depends on
the nature of the cause of action pleaded.
Cost recovery actions by parties not responsible for site contaminations
are joint and several cost recovery actions governed exclusively by § 107(a).
Claims by PRPs, however, seeking costs from other PRPs are necessarily actions
for contribution, and are therefore governed by the mechanisms set forth in §
113(f). [Id. at 350.]
In this case, plaintiff’s cause of action cannot be construed as a cost recovery action for
joint and several response costs under MCL 299.612 for two reasons. One, we have already
concluded that plaintiff is liable as a PRP and plaintiff has conceded its liability regarding
contamination of the uplands and filled bottomlands. Second, in order to establish a prima facie
case under MCL 299.612, plaintiff must prove:
(1) the site is a "facility"; (2) a release or threatened release of hazardous
substance has occurred; (3) the release has caused the plaintiff to incur "necessary
costs of response"; and (4) the defendant falls within one of the four categories of
PRPs. [Id. at 347-348.]
Plaintiff cannot establish the fourth element because Heywood-Wakefield is not a defendant in
this case.
Plaintiff’s assertion that the harm is divisible and that the costs for cleaning up the
submerged bottomlands should be borne by Heywood-Wakefield is properly characterized as
contribution claim under MCL 299.612c. But plaintiff’s liability cannot be limited under this
provision either. While plaintiff’s failure to allege a contribution claim under MCL 299.612c in
its complaint8 is not fatal,9 its failure to join Heywood-Wakefield in this suit is. Even if plaintiff
had alleged a contribution claim in its complaint, Heywood-Wakefield is not a party to this suit.
A contribution claim seeks reimbursement from other PRPs for the cost expended by the plaintiff
over and above its pro rata share. “[T]he burden is placed on the plaintiff to establish the
8
In its prior related suit, plaintiff did assert a claim for contribution against the state, the
dismissal of which was affirmed by this Court in Flanders, supra, “because § 612c(3) allows
contribution actions only against ‘person[s] who [are] or may be liable.’” Id. at 31. The
Flanders Court determined that the state could not be liable under MCL 299.612. Id. at 29-30.
9
A MCL 299.612c action for contribution is an action under MCL 299.612 to the extent that it
seeks recovery for costs referred to in MCL 299.612. Centerior Service, supra at 353, citing Sun
Co, Inc v Browning-Ferris, Inc, 124 F3d 1187, 1191 (CA 10, 1997).
-7-
defendant’s equitable share of response costs.” Id. at 348; emphasis added. That the party from
whom contribution is sought must be a party to the action is implicit in the statutory language.
MCL 299.612c(3) and (4) (these provisions outline the procedure for allocating response activity
costs among PRPs). Therefore, plaintiff is not entitled to a remand in order to present its
argument regarding divisibility of harm.
Lastly, plaintiff argues that the court erred in dismissing count II of its complaint
pursuant to MCR 2.116(C)(8). In count II of its complaint, plaintiff claimed that it was entitled
to reimbursement for response costs incurred before the 1992 Order was entered. Plaintiff
alleged that denial of such costs violated its due process rights and unjustly enriched the state,
challenging the statute’s constitutionality in that MCL 324.20119(5) only provides for recovery
of post-order costs.
This Court reviews de novo a trial court's grant of summary disposition for failure to state
a claim. MacDonald, supra at 332. When reviewing a trial court's grant of summary disposition
for failure to state a claim on which relief can be granted, an appellate court assumes all factual
allegations in the nonmoving party's pleadings are true, Maiden v Rozwood, 461 Mich 109, 199;
597 NW2d 817 (1999), and determines whether there is a legally sufficient basis for the claim,
MacDonald, supra at 332.
As plaintiff concedes, reimbursement for recovery costs under MCL 324.20119(5) is
limited to those costs incurred “pursuant to the relevant order.” Thus, according to the plain
language of the statute, plaintiff is not entitled to reimbursement for costs incurred before the
1992 Order was entered. But plaintiff contends that this scheme is unconstitutional as violative
of due process. “[A] statutory scheme violates due process if ‘the penalties for disobedience are
by fines so enormous and imprisonment so severe as to intimidate [an affected party] from
resorting to the courts to test the validity of the legislation.’” Solid State Circuits, Inc v USEPA,
812 F2d 383, 390 (CA8, 1987), quoting Ex Parte Young, 209 US 123, 147; 28 S Ct 441; 52 L Ed
714 (1908).10 Here, there are no penalties for not voluntarily initiating response activities.
Plaintiff could have allowed the DNR to clean up the site and then defended its nonliability
position if the state instituted a cost recovery action.
Furthermore, to implicate due process concerns there necessarily must be some action by
the state that affects plaintiff’s liberty or property interests. See Landon Holdings, Inc v Grattan
Twp, 257 Mich App 154, 173; 667 NW2d 93 (2003) (substantive due process ensures that the
state does not deprive a person of liberty or property by an arbitrary exercise of power); Hanlon,
supra at 723 (procedural due process requirements limit state actions by requiring safeguards in
proceedings such as notice of the nature of the proceedings, an opportunity to be heard in a
meaningful time and manner, and an impartial decision-maker). The DNR requested that
plaintiff engage in clean up efforts, but did not require it to do so until the 1992 Order was
entered. Therefore, we conclude that there can be no violation of due process for costs
10
Due process is defined and interpreted similarly in both Michigan’s and the federal
constitution. Hanlon v Civil Service Comm, 253 Mich App 710, 722; 660 NW2d 74 (2002).
-8-
voluntarily incurred before an administrative order that compels a PRP to engage in response
activities has been entered.
In regards to plaintiff’s unjust enrichment theory, we also find this argument meritless. If
plaintiff could recover pre-1992 Order costs, presumably reimbursement would be according to
the standard set for reimbursement of post-order costs; they must be reasonable and necessary.
MCL 324.20119(5). We find that the costs at issue were not “reasonable and necessary” because
they were duplicative of the state’s efforts and were not legally required. See Louisiana-Pacific
Corp v Breazer Materials & Services, 982 F2d 1436, 1447-1448 (CA 10, 1992); US v Iron
Mountain Mines, Inc, 987 F Supp 1263, 1272 (ED Cal, 1997); US v Hardage, 750 F Supp 1460,
1511-1517 (WD Okla, 1990). Also, to the extent that any of plaintiff’s actions were not
duplicative, we find that plaintiff suffered no inequity as a result of the retention of any benefit
by the state. Belle Isle Grill Corp v Detroit, 256 Mich App 463, 478; 666 NW2d 271 (2003)
(elements of unjust enrichment claim are receipt of a benefit by the defendant and an inequity
resulting to the plaintiff because of the retention of the benefit by the defendant). Accordingly,
the trial court properly granted defendants’ motion for summary disposition regarding plaintiff’s
count II.
Affirmed.
/s/ Michael R. Smolenski
/s/ William B. Murphy
/s/ Kurtis T. Wilder
-9-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.