PCL CIVIL CONSTRUCTORS INC V DEPT OF TRANSPORTATION
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
PCL CIVIL CONSTRUCTORS, INC.,
MCCARTHY BUILDING COMPANIES, INC.,
and PCL MCCARTHY,
UNPUBLISHED
November 18, 2003
Plaintiffs-Appellants,
v
No. 237184
Court of Claims
LC No. 99-017413-CM
DEPARTMENT OF TRANSPORTATION,
Defendant/Third Party Plaintiff-
Appellee,
and
MODJESKI & MASTERS, INC., BUCKLAND &
TAYLOR, LTD., and MODJESKI & MASTERS,
INC/BUCKLAND & TAYLOR, LTD.,
Third Party Defendants-Appellees.
Before: Neff, P.J., and Fort Hood and Borrello, JJ.
PER CURIAM.
Plaintiffs appeal as of right from the trial court’s order granting defendant Michigan
Department of Transportation’s (MDOT) motion for summary disposition. We affirm.
This litigation arises out of the construction of the second Blue Water Bridge linking Port
Huron, Michigan to Point Edward, Canada. Defendant retained third party defendants to design
the bridge and act as project engineer, supervising the construction of the bridge. Plaintiffs were
the successful bidders of the contract and began construction. However, plaintiffs brought a
claim for additional compensation, contending that the terms of the construction contract were
ambiguous and material modifications were made to the contract. Defendant filed a motion for
summary disposition, alleging that the terms of the contract were plain and unambiguous and
-1-
that plaintiffs had failed to comply with the contractual provisions necessary to obtain relief.
The trial court granted defendant’s motion.
Plaintiff1 first alleges that the trial court erred in concluding that the notice provision in
the parties’ contract had not been invoked. We disagree. Our review of the grant or denial of
summary disposition is de novo. Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817
(1999). The construction and interpretation of a contract presents a question of law that is
reviewed de novo. Bandit Industries, Inc v Hobbs Int’l, Inc (After Remand), 463 Mich 504, 511;
620 NW2d 531 (2001). The goal of contract construction is to determine and enforce the parties’
intent from the plain language of the contract itself. Old Kent Bank v Sobczak, 243 Mich App
57, 63; 620 NW2d 663 (2000). If contract language is clear and unambiguous, its meaning
presents a question of law for the court to determine. UAW-GM Human Resource Center v KSL
Corp, 228 Mich App 486, 491; 579 NW2d 411 (1998). On the other hand, where the contract
language is unclear or susceptible to multiple meanings, interpretation becomes a question of
fact. Id. Where a contract is not ambiguous, evidence of custom and practice is inadmissible.
Independence Twp v Reliance Building Co, 175 Mich App 48, 54; 437 NW2d 22 (1989).
Furthermore, the duty to interpret and apply the law is allocated to the courts, not the parties’
witnesses. See Hottman v Hottman, 226 Mich App 171, 179; 572 NW2d 259 (1997).
As an initial matter, we note that plaintiffs repeatedly allege that the contract was
ambiguous such that the parties’ intent becomes relevant, creating questions of fact, and the
construction of the contract is construed against defendant as the drafter. However, we note that
the contract in the present case expressly delegated the authority to determine the intent of the
plans to the project engineer.2 Thus, any question regarding the performance testing of the welds
and the visual, radiographic, and ultrasonic test inspections should have been directed to the
project engineer to determine the degree of time and monetary expenditure for this aspect of the
contract. There is no indication that plaintiffs raised such an issue with the project engineer
before submission of the bid or before commencement of this work.3 Furthermore, plaintiffs’
contention that the construction of the contract should consider common practice and procedure
and testimony from plaintiffs’ witnesses is without merit. Hottman, supra; Independence Twp,
supra. Therefore, applying the plain language of the contract, plaintiffs’ allegation that their
intention regarding the specifications governs is without merit. Old Kent, supra.
1
Plaintiff has subdivided the trial court’s ruling into eighteen different claims of error. For ease
of reference, we will address the issues as presented and ruled upon in the lower court.
2
The contract provided that the bidder had inspected the proposal forms, plans, and
specifications, and submission of a bid was prima facie evidence that the bidder was satisfied as
to the “conditions to be encountered in performing the work.” Additionally, regarding the
authority of the engineer, it provided: “The Engineer will decide the intent of the plans and
specifications when an inconsistency, omission, conflict or uncertainty is discovered.”
3
Thus, where the request for extra compensation was governed by the specifications of the
contract, the request was specious at best.
-2-
Furthermore, review of the construction contract at issue reveals that the contractor had to
provide notice in writing before commencing work in order to seek extra compensation, and the
failure to comply with this requirement resulted in waiver of the claim. Old Kent, supra. The
purported notice proffered by plaintiffs failed to comply with this requirement, and thus, the trial
court properly granted summary disposition of this claim. See Reynolds v Allstate Ins Co, 123
Mich App 488, 490-491; 332 NW2d 583 (1983). Additionally, the contention that defendant
cannot demonstrate prejudice from any deficiency in the notice is without merit. There is no
such conditional requirement imposed within the plain language of the contract. Old Kent, supra.
Finally, we conclude that there is no merit to plaintiffs’ contention, that the closure of the
weld access holes was a constructive change to the contract, in light of the plans submitted by
plaintiffs and the discretion afforded the project engineer pursuant to the terms of the contract.
Affirmed.
/s/ Janet T. Neff
/s/ Karen M. Fort Hood
/s/ Stephen L. Borello
-3-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.