BODDY CONSTRUCTION CO INC V MICHIGAN DEPT OF TRANSPORTATION
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
BODDY CONSTRUCTION COMPANY, INC.,
UNPUBLISHED
February 28, 2003
Plaintiff-Appellant,
No. 237471
Court of Claims
LC No. 00-017592-CM
v
MICHIGAN DEPARTMENT OF
TRANSPORTATION,
Defendant-Appellee.
Before: Sawyer, P.J., and Jansen and Donofrio, JJ.
PER CURIAM.
Plaintiff appeals as of right the opinion and order granting the motion for summary
disposition brought by defendant Michigan Department of Transportation (“MDOT”) under
MCR 2.116(C)(8) and (10). We reverse and remand.
In this case, plaintiff is seeking $724,954.66 in additional compensation for highway
reconstruction work performed along M-29 in St. Clair County. According to defendant, the
construction contract expressly prohibited extra compensation in this case because plaintiff failed
to provide timely notice to the MDOT engineer about its intention to seek additional
compensation. Plaintiff counters that it was entitled to extra compensation because defendant
waived this contractual provision. The trial court, without specifying the subrule under which it
granted defendant’s motion for summary disposition, found that plaintiff was not entitled to extra
compensation because there was nothing in the record to indicate that defendant had given prior
approval as required under the contract.
Because the trial court pierced the pleadings in granting summary disposition in
defendant’s favor, we review the grant of summary disposition under MCR 2.116(C)(10). In
reviewing a motion for summary disposition brought under MCR 2.116(C)(10), this Court
considers affidavits, pleadings, depositions, admissions, and other evidence submitted by the
parties in a light most favorable to the nonmoving party. Maiden v Rozwood, 461 Mich 109,
119-120; 597 NW2d 817 (1999). As clarified by the Supreme Court in Maiden:
The reviewing court should evaluate a motion for summary disposition under
MCR 2.116(C)(10) by considering the substantively admissible evidence actually
proffered in opposition to the motion. A reviewing court may not employ a
standard citing the mere possibility that the claim might be supported by evidence
-1-
produced at trial. A mere promise is insufficient under our court rules. [461 Mich
at 121.]
In this case, the parties entered into a highway contract, which was governed by the 1990
Standard Specifications for Construction. Under § 1.05.12(a), the Notice of Claim provision,
“the Contractor shall notify the [MDOT] Engineer in writing of the Contractor’s intention to
make claim for such extra compensation before beginning work on which the Contractor intends
to base a claim. . . .” It is undisputed that plaintiff failed to provide the MDOT engineer in
question with written notice of its intent to file a claim before beginning the work upon which
plaintiff’s claim is based.
Nevertheless, we agree with plaintiff’s contention that defendant waived strict
compliance with § 1.05.12. See Jacob v Cumings, 213 Mich 373; 182 NW 115 (1921). Here,
the record indicates that defendant waived strict compliance with the written notice requirement
by agreeing with plaintiff to resolve disputes arising with the plans and specifications of the
project without the need of filing a written notice of intent to file a claim. Thus, the trial court
erred, as a matter of law, in ruling that defendant did not waive strict compliance with
§ 1.05.12(a) of the 1990 Standard Specifications for Construction.
Further, there was a genuine issue of material fact whether plaintiff was entitled to
additional compensation for its highway reconstruction work. Specifically, although defendant
maintains that plaintiff has failed to attach any records substantiating its alleged claims, we note
that Horace Boddy, in his deposition testimony, indicated that there were handwritten notations
documenting the cost for excavating and disposing of temporary aggregate off site in the amount
of $91,407.37. On remand, the trial court is thus instructed to determine whether plaintiff was
entitled to additional compensation and in what amount.
Reversed and remanded for further proceedings. We do not retain jurisdiction.
/s/ David H. Sawyer
/s/ Kathleen Jansen
/s/ Pat M. Donofrio
-2-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.