WABASH VALLEY POWER ASSN INC V MPSC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
WABASH VALLEY POWER ASSOCIATION,
UNPUBLISHED
July 21, 1998
Plaintiff-Appellant,
v
No. 205498
MPSC
LC No. 11013
FRUIT BELT ELECTRIC COOPERATIVE,
and MICHIGAN PUBLIC SERVICE
COMMISSION,
Defendants-Appellees.
Before: Fitzgerald, P.J., and Holbrook, Jr., and Cavanagh, JJ.
PER CURIAM.
Washtenaw Valley Power Association appeals from a May 7, 1997, decision of the Michigan
Public Service Commission and a July 31, 1997, decision on rehearing which denied Wabash Valley’s
December 28, 1995, application for approval of certain rates and tariffs. The PSC found that the
proposed rates should not be approved “at this time” because of the limited record available, the lack
of any existing or planned qualifying facility to which the rates would apply, and the consequent lack of
any basis for evaluating how the rates would affect the parties, ratepayers, potential developers of
qualifying facilities, or the public. Wabash Valley contends that the PSC was required to approve its
rates, which Wabash Valley contends were based upon its properly calculated avoided costs. We
conclude that the PSC’s orders were neither unlawful nor unreasonable.
Wabash Valley is an Indiana-based collection of rural power companies known as a generation
and transmission cooperative, or a “G & T.” One of Wabash Valley’s members is Fruit Belt Electric
Cooperative, a rural electrification cooperative (“REC”) based in southwestern Michigan. Fruit Belt
joined Wabash Valley in 1977. Fruit Belt entered into an “all requirements” contract with Wabash
Valley which obligates Fruit Belt to purchase its power from Wabash Valley.
In 1978 Congress enacted the Federal Public Utility Regulatory Policies Act of 1978
(“PUPRA”), PL 95-617, 92 Stat 3117, as part of a package of legislation designed to combat a
-1
nationwide energy crises. See Consumers Power Co v Public Service Comm, 189 Mich App 151,
156-160; 472 NW2d 77 (1991), for a discussion of PURPA. Among other things, PURPA
encouraged the development of alternative sources of power. PURPA required utilities to offer to
purchase power from “qualifying facilities” (“QFs”) at just and reasonable rates which may not exceed
the utility’s “avoided costs.” 16 USC 824a-3(b), (d). Particularly relevant to this appeal is PURPA’s
requirement that states implement the rules of the Federal Energy Regulatory Commission (“FERC”)
relating to PURPA. 16 USC 824a-3(f)(1) provides:
(1) Beginning on or before the date one year after any rule is prescribed by the
Commission under subsection (a) of this section or revised under such subsection, each
State regulatory authority shall, after notice and opportunity for public hearing,
implement such rule (or revised rule) for each electric utility for which it has ratemaking
authority.
In 1980 the FERC adopted regulations implementing PURPA, codified at 18 CFI 292.101-292.602.
Consumers Power Co, supra at 157. These regulations were issued as FERC’s order No. 69 and
became effective March 20, 1980.
In recognition of PURPA and the FERC’s regulations, on March 17, 1981, the PSC initiated
case U
-6798 to implement PURPA. The final order in U
-6798 was entered on August 27, 1982.
Case U
-6798 largely consisted of PSC approval of settlement agreements involving utilities, electric
cooperatives, the PSC staff and others. One of those settlement agreements involved most, if not all,
RECs in Michigan and the only G & T operating in Michigan, Wolverine Power Supply Cooperative.
Fruit Belt was a signatory to the settlement agreement. Consistent with PURPA and the FERC
regulations, the settlement agreement provided that the sales of a QF which was connected to a REC
and subject to an all-requirements contract would, if the G & T agreed, be deemed to be made to the G
& T. This provision was based upon a FERC regulation designed to avoid breach of contract problems
by providing an alternate means for a utility to meet its PURPA obligation, providing the QF consented
to the arrangement. 18 CFR 292.303(d). Rates were established in U-6798, including rates for Fruit
Belt to purchase power from a QF even though no QF existed in Fruit Belt’s area and even though Fruit
Belt did not then purchase power from a QF.
At the time U-6798 was settled, the PSC had not yet exercised jurisdiction over Wabash
Valley. Wabash Valley did not participate in U-6798. The PSC eventually exercised jurisdiction over
Wabash Valley on June 26, 1983, in U-7963.
In 1987 our Legislature amended MCL 460.6j; MSA 22.13(6j) by, among other things, adding
most of what is now MCL 460.6j(13)(b); MSA 22.13(6j)(13)(b). Section 6j(13)(b) deals with
capacity charges for power purchased QFs in the context of power supply costs reconciliation
proceedings. See Attorney General v Public Service Comm, 220 Mich App 561, 564; 560 NW2d
348 (1996), and Ass’n of Businesses Advocating Tariff Equity v Public Service Comm, 173 Mich
App 647, 657; 434 NW2d 648 (1988). Section 6j(13) authorizes the PSC to determine the “scope
and manner of the review of capacity charges for a qualifying facility,” and also requires approvals
-2
sought after June 1, 1987, to proceed before the PSC as contested cases. Wabash Valley sought ex
parte relief rather than initiating a contested case proceeding.
Wabash Valley sought approval of rates based upon its avoided costs as recently determined in
a proceeding before Indiana regulatory authorities. Wabash Valley asserted that U-6798 applied to its
application, since Fruit Belt was a party to the settlement agreement in U-6798 and Fruit Belt had an
all-requirements contract with Wabash Valley. Wabash Valley requested approval of proposed rates,
tariff sheets and a standard contract form covering purchases from qualified facilities located in Fruit
Belt’s service area. Fruit Belt objected and argued that Wabash Valley had no right to “step into its
shoes” despite its all-requirements contract with Wabash Valley. At the time, and presently, there was
no QF in existence or planned in Fruit Belt’s service area.
The PSC denied Wabash Valley’s application. The PSC did not reach the merits of the issues
presented by the parties and did not decide whether Wabash Valley’s proposed rates were just and
reasonable. Rather, after recognizing that no QF existed or was even proposed in Fruit Belt’s service
area, the PSC simply declined “to express an opinion in the absence of an actual controversy.” The
PSC found that:
. . . There is no basis for evaluating how the tariff would affect Wabash Valley, Fruit
Belt, their ratepayers, or potential developers. In light of the circumstances, it is unclear
how the tariff would affect the public interest.
Wabash Valley has not satisfied its burden of showing by clear and satisfactory evidence that
the PSC’s order was unlawful or unreasonable. MCL 462.26(8); MSA 22.45(8); Attorney General v
Public Service Comm, 206 Mich App 290, 294; 520 NW2d 636 (1994). This Court’s review of
PSC orders is narrow. Attorney General, supra, 206 Mich App at 294. Pursuant to MCL 462.25;
MSA 22.44 all rates, fares, charges, regulations, practices, and services prescribed by the PSC are
presumed, prima facie, to be lawful and reasonable. A final order of the PSC is reviewed to determine
whether it is authorized by law and whether it is supported by competent, material, and substantial
evidence on the whole record. Const 1963, art 6, §28; Attorney General, supra, 206 Mich App at
294. A reviewing court gives deference to the PSC’s administrative expertise and should not substitute
its judgment for that of the PSC. Attorney General, supra, 206 Mich App at 294.
The PSC was faced with an application for approval of rates to purchase power from a QF
which neither existed nor was even shown to be contemplated by anyone. The rate request affected
Fruit Belt which opposed the application. The application sought ex parte relief, although MCL
460.6j(13)(b); MSA 22.13(6j)(13)(b) indicates that a contested case proceeding was called for. The
rate requested in the application was not the same as the rate recommended by the PSC staff or by the
ALJ. The application was based upon an “alternate” scheme which required the consent of the affected
QF, 18 CFR 292.303(d), and yet no QF existed to give consent and the position of any potential QF
of course could not be ascertained. Given these circumstances, and the role of the PSC in protecting
the public interest, the PSC’s denial of the application was a prudent exercise of its legislative authority.
Michigan Consolidated Gas Co v Public Service Comm, 389 Mich 624, 644-645; 209 NW2d 210
-3
(1973) (Williams, J., dissenting on other grounds); Colony Park Apartments v Public Service
Comm, 155 Mich App 134, 138; 399 NW2d 32 (1985).
PURPA did not require the PSC to determine rates as requested in Wabash Valley’s
application. PURPA required the PSC to “implement” the FERC rules and regulations governing
PURPA for each electric utility over which the PSC has ratemaking authority. 16 USC 24a-3(f)(1).
The PSC implemented PURPA and its associated rules and regulations when it issued its final order in
U-6798 on August 27, 1982. Consumers Power Co, supra, 189 Mich App at 160; Association of
Businesses Advocating Tariff Equity, supra at 650-651. The FERC regulations on implementing
PURPA left the states considerable latitude. Implementation of PURPA could consist of adopting the
FERC’s rules, following a dispute resolution process, or “any other action reasonably designed” to
implement PURPA requirements. 18 CFR 292.401. Wabash Valley is not persuasive in arguing that
PURPA and its regulations mandate a rate determination in the largely hypothetical context presented by
Wabash Valley. In fact, the FERC regulations do not mandate that a G & T be the entity to purchase
power from a QF. 18 CFR 292.303(d).
Wabash Valley was not a party in the U
-6798 proceeding. While Fruit Belt was one of the
stipulating parties in U-6798, Fruit Belt might have taken a different position if Wabash Valley had been
involved in the settlement. Moreover, since U-6798 was decided our Legislature has required
contested case proceedings regarding approvals of capacity charges in contracts with QFs. MCL
460.6j(13)(b); MSA 22.138(6j)(13)(b). Given these circumstances, the PSC’s decision thirteen years
before in U-6798 did not require the PSC to determine a specific rate as requested by Wabash Valley.
Nor was the PSC’s decision arbitrary or capricious. See Bundo v Walled Lake, 395 Mich
679, 703; 238 NW2d 154 (1976). It is true that the PSC fixed rates in U-6798 in some instances
(including rates for Fruit Belt) which did not involve an existing QF, while in the instant case the PSC
refused to do so. However, U-6798 was a major PSC proceeding to implement PURPA involving
numerous parties and in which the parties stipulated to the result. It was not unreasonable for the PSC
at that time to establish what rates it could. In contrast, Wabash Valley filed an ex parte application
which did not apply to any actual QF and to which the most affected party objected. The PSC did not
face similar situations in 1982 and 1995.
Wabash Valley briefly argues that the result of the PSC’s refusal to approve Wabash Valley’s
rate requests was unreasonable in part because the effect of the PSC’s refusal was to jeopardize
Wabash Valley’s rights under its all-requirements contract with Fruit Belt. This argument lacks merit
since there is no indication of any contract breach, now or in the future, and since Wabash Valley is not
precluded from again applying to the PSC if circumstances change.
As part of its answer Fruit Belt argues that this Court does not have jurisdiction over the PSC
orders appealed by Wabash Valley. This Court has jurisdiction to consider a claim of appeal filed by
an aggrieved party from a judgment or order of a tribunal from which an appeal by right to this Court
has been established by law. MCR 7.203(A)(2). A final order is the first order that disposes of all the
claims and adjudicates the rights and liabilities of all the parties. MCR 7.202(8)(a)(i). MCL 462.26(1);
MSA 22.45(1) establishes, by law, appeals by right to this Court from PSC orders “fixing any rate or
-4
rates, fares, charges, classifications, joint rate or rates, or any order fixing any regulations, practices, or
services.” In effect, the PSC’s order prohibited Wabash Valley from the “practice” of purchasing from
QFs in Michigan at any rate. An appeal from such
-5
an order is reasonably within the broad grant of appellate jurisdiction in MCL 462.26(1); MSA
22.45(1). The PSC’s order was also “final.” It put a complete end to Wabash Valley’s application
and to U-11013. Wabash Valley’s appeal was timely filed and this Court must consider it.
Affirmed.
/s/ E. Thomas Fitzgerald
/s/ Donald E. Holbrook, Jr.
/s/ Mark J. Cavanagh
-6
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.