ATTORNEY GENERAL V MPSC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
MIDLAND COGENERATION VENTURE
LIMITED PARTNERSHIP,
UNPUBLISHED
January 21, 1997
Appellant,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
et al,
Appellees.
__________________________________________
No. 178584
Public Service Commission
LC No. U-10445
ATTORNEY GENERAL,
Appellant,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
et al,
No. 178814
Public Service Commission
LC No. U-10445
Appellees.
Before: McDonald, P.J., and White and P. J. Conlin, JJ.*
PER CURIAM.
This case concerns repeatedly litigated questions regarding payments for energy produced by
the Midland Cogeneration Venture (MCV). This appeal arises specifically out of the annual power
supply cost recovery plan (PSCR) for 1994. The separate appeals of MCV and the Attorney General
from the August 18, 1994 decision of the Public Service Commission (MPSC), were consolidated by
this Court. We affirm.
* Circuit judge, sitting on the Court of Appeals by assignment.
-1
The factual background for this appeal was recently summarized by this Court in ABATE v
Public Service Commission, 216 Mich App 8, 12-18; 548 NW2d 649 (1996):
The Midland Cogeneration Venture (MCV) is a limited partnership formed for
the purpose of constructing and operating a gas-fired cogeneration plant. On
September 10, 1987, MCV filed an application with the MPSC for approval of
capacity charges in a contract for the sale of electricity to Consumers Power Company
(CP). The MPSC docketed MCV’s application as Case No. U-8871, and
consolidated it with other applications for QFs [qualifying facilities] and complaints
against CP.
* * *
In the appeals before us, CP, MCV, the AG, ABATE and other parties
appealed as of right from the MPSC’s series of orders. In Consumers Power Co v
Public Service Comm (Consumers Power I), [189 Mich App 151; 472 NW2d 77
(1991)], this Court affirmed in part and reversed in part the MPSC’s orders. We held
that the MPSC properly exercised its authority acting pursuant to MCL 460.6j; MSA
22.13(6j). It appropriately determined the avoided capacity cost which could be
passed on to ratepayers, the future capacity needs, the avoided costs using a
hypothetical coal-fired facility and a rate structure. We found that clear and satisfactory
evidence supported the use of a hypothetical coal-fired plant to determine CP’s future
avoided capacity costs.
* * *
In March, 1990, MCV began selling power under the unapproved 1987
contract with CP. CP filed a series of annual power supply cost recovery cases. In a
temporary order dated December 21, 1989, the MPSC limited CP’s power supply
cost recovery charges to the backloaded QF rate established in Case No. U-8871. In
Consumers Power Co v Public Service Comm, [192 Mich App 180; 481 NW2d 1
(1991)], this Court affirmed the temporary order. In a series of other orders, the
MPSC limited CP’s authorized charges to 3.77 cents/kWh, and allowed CP to charge
only for energy actually delivered, not for all available capacity. Various parties
appealed as of right.
In Consumers Power Co v Public Service Comm No 1, [196 Mich App
436; 493 NW2d 902 (1992)], this Court affirmed those orders. We held that the
MPSC was not required to accept new evidence regarding the reasonableness and
prudence of the capacity charges in the contract between CP and MCV. Rather the
MPSC was entitled to rely on evidence produced in Case No. U-8871, where those
issues had been litigated.
THE REVISED SETTLEMENT PROPOSAL
-2
Pursuant to the remand in Consumers Power I, supra, CP, ABATE, and the
MPSC staff filed a joint stipulation in a number of cases, including Case No. U-8871.
The MPSC rejected the stipulation on the basis that it allowed CP to pick and choose
among the findings in Case No. U-8871. Following the rejection of the stipulation, the
MPSC instructed its staff to attempt to negotiate a settlement. On September 8, 1992,
CP, the MPSC staff and several QFs filed a revised settlement proposal. The case was
docketed as Case No. U-10127.
* * *
The MPSC granted CP’s request to incorporate the record in Case No. U
-8871.
MCV filed a statement indicating that it did not object to the revised settlement plan.
* * *
In the body of the March 31, 1993, order the MPSC addressed numerous
arguments. It rejected the AG’s contention that a hypothetical gas-fired proxy should
be adopted to determine CP’s avoided costs, finding that such a proxy would not
necessarily be less expensive. The evidence showed that, over a period of twenty to
thirty years, a coal-fired plant is only slightly more costly. The MPSC concluded that,
when other assumptions were made, abandonment of the coal-fired proxy adopted in
Case No. U-8871 could not be justified.
* * *
The MPSC modified provisions of the revised settlement proposal dealing with
recovery of capacity charges. Based on its finding that the proposal allowed CP to
recover MCV payments in excess of the avoided costs of a coal-fired proxy plant, the
MPSC offered CP two options. Under the first, CP would be allowed to recover 3.62
cents/kWh for available capacity up to eighty percent of 915 MW. This rate
represented the avoided cost for a proxy coal plant based on an expected availability of
eighty percent, rather than on its expected capacity factor. The option would allow full
recovery of the avoided cost of 915 MW of coal-fired capacity.
Under the second option, MCV would be utilized whenever it was available, up
to the limits specified in the revised settlement proposal applied to 915 MW of capacity.
CP would recover 3.62 cents/kWh for capacity. That rate provided a 15 cents/kWh
reduction from the 3.77 cents/kWh approved in Case No. U-8871. Payments would
be based on actual energy delivered, rather than on availability. Consumers could
choose to run MCV out of economic order.
* * *
-3
On April 6, 1993, CP filed an acceptance of the MPSC’s March 31, 1993
order. CP chose option 2 for recovery of MCV capacity payments.
The panel proceeded to find that the MPSC order incorporating option 2 was lawful and
reasonable. Id, 20. Option 2 was supported by competent evidence. Id, 23. The Court found that
the decision to use a coal-fired proxy plant to determine avoided costs was supported by the evidence,
and had been affirmed in Consumers Power I, supra, 189 Mich App at 181-184.
The present case concerns the annual PSCR plan for 1994, under which the MPSC determines
the factor to be used by Consumers Power to calculate a reasonable recovery on its wholesale power
supply costs. MCL 460.6j; MSA 22.13(6j). As part of this review, Consumers sought clarification of
the MPSC orders in Case No. U-10127. MCV sought additional rate recovery on an availability,
rather than energy delivered basis, arguing that it should be paid an additional variable energy charge for
energy dispatched above the levels provided by the earlier MPSC orders. The AG again argued that
the energy payments to QFs should be based on a supply of high sulfur coal to the proxy coal-fired
plant, and not on the actual mix of coal used by Consumers.
In an opinion and order issued August 18, 1994, the MPSC stated that the methodology for
determining avoided energy payments to OFs adopted in Case No. U
-8871 combined a reasonable
approximation of the utility’s avoided energy costs based on a rolling average of the cost of fuel and
O&M expenses at the base load coal-fired generating units with a reasonable approximation of the
utility’s avoided capacity costs based upon a base load high sulfur coal-fired proxy plant. The MPSC
concluded that this method remained appropriate, and it rejected the exceptions raised by the AG and
ABATE. The MPSC noted that the parties were unable to agree regarding Consumers’ recovery of its
capacity and energy payments to the MCV for energy delivered above the 750.3 MW off-peak cap but
below the overall 915 MW ceiling. The MPSC held that in Case No. U-10127, it specifically found
that the RSP established limits on Consumers’ recovery of costs above the caps. Challenges to the
legality of that order should have been raised in Case No. U-10127, but they were not. The MPSC
rejected the challenges of MCV and Consumers.
Extensive discussion of the issues presented is not required in this opinion. As reflected in
ABATE v Public Service Commission, supra, p 14, this Court has repeatedly held that the MPSC
was entitled to rely on evidence produced in Case No. U-8871, and to not relitigate issues which it had
already decided. All the issues presented in this case were either specifically decided or waived in Case
Nos. U-8871 and U-10127. MCV acceded to a settlement in U-10127, and waived its appeal of that
decision. This Court affirmed those decisions in ABATE, supra. No further review is necessary, and
this Court will likely be disposed to find that any repeated presentation of these issues in the future
would be frivolous.
Affirmed.
-4
/s/ Gary R. McDonald
/s/ Helene N. White
/s/ Patrick J. Conlin
-5
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.