IN RE APP OF INTL TRANSMISSION CO FOR EXPEDITED SITING CERT (Per Curiam Opinion)

Annotate this Case
Download PDF
STATE OF MICHIGAN COURT OF APPEALS In re APPLICATION OF INTERNATIONAL TRANSMISSION COMPANY FOR EXPEDITED SITING CERTIFICATE ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY, FOR PUBLICATION November 6, 2012 9:00 a.m. Appellant, v MICHIGAN PUBLIC SERVICE COMMISSION, No. 303009 Public Service Commission LC No. 00-016200 Appellee, and INTERNATIONAL TRANSMISSION COMPANY, d/b/a ITC TRANSMISSION, Petitioner-Appellee, and CONSUMERS ENERGY COMPANY, MICHIGAN PUBLIC POWER AGENCY, and MICHIGAN MUNICIPAL ELECTRIC ASSOCIATION, Appellees.1 1 Michigan Public Power Agency and Michigan Municipal Electric Association are appellees in Docket No. 303009, but are appellants in Docket No. 303040. Similarly, Association of Businesses Advocating Tariff Equity (ABATE) is the appellant in Docket No. 303009, but an appellee in Docket No. 303040. However, because these cases are consolidated, these three parties, all of whom were intervenors in the underlying proceedings, only argue appellant positions, despite their status as appellees in the other appeal. For clarity, throughout this -1- MICHIGAN PUBLIC POWER AGENCY and MICHIGAN MUNICIPAL ELECTRIC ASSOCIATION, Appellants, v MICHIGAN PUBLIC SERVICE COMMISSION, No. 303040 Public Service Commission LC No. 00-016200 Appellee, and INTERNATIONAL TRANSMISSION COMPANY, d/b/a ITC TRANSMISSION, Petitioner-Appellee, and CONSUMERS ENERGY COMPANY and ABATE, Appellees. Before: FITZGERALD, P.J., and METER and BOONSTRA, JJ. PER CURIAM. In these consolidated cases, appellant Association of Businesses Advocating Tariff Equity (ABATE) (Docket No. 303009), and appellants Michigan Public Power Agency (MPPA) and Michigan Municipal Electric Association (MMEA) (Docket No. 303040) appeal the February 25, 2011, order entered by appellee Michigan Public Service Commission (PSC) granting appellee International Transmission Company, d/b/a ITC Transmission (ITC), an expedited siting certificate for a wind energy transmission line and authorizing construction of that line on ITC s proposed route. We hold that the PSC properly issued the siting certificate, but that its conclusion that construction is permitted by the certificate was erroneous. However, because we are mindful of the effects of our conclusion, we conclude that limiting our holding to prospective application is appropriate. opinion, the term appellants shall refer to only ABATE, MPPA, and MMEA and the term appellees shall refer to only the PSC and ITC. -2- I. BACKGROUND Before 2008, all location and construction of electric transmission lines of a certain size and length2 was governed by 1995 PA 30, known as the Electric Transmission Line Certification Act, MCL 460.561 et seq. (Act 30). In 2008, the Legislature passed 2008 PA 295, known as the Clean, Renewable, and Efficient Energy Act, MCL 460.1001 et seq. (Act 295). Part 4 of Act 295, MCL 460.1141 et seq., titled WIND ENERGY RESOURCE ZONE (Act 295(4)), included provisions for the creation of a wind energy resource zone board (WERZ Board) that would issue a report determining the regions in the state with the highest wind energy harvest potential. After receiving that report, the electric utilities, affiliated transmission companies, and independent transmission companies with facilities within or adjacent to the regions identified by the state would identify existing or new transmission infrastructure necessary to deliver maximum and minimum wind energy production potential for each of those regions and submit that information to the WERZ Board for review. MCL 460.1143, 460.1145. Based on the WERZ Board s report, the PSC would then designate an area or region of the state that would likely produce the most wind energy as the primary wind energy resource zone. MCL 460.1147(1), (2). Act 295(4) also provided provisions for electric utilities, affiliated transmission companies, and independent transmission companies to apply for and obtain an expedited siting certificate. MCL 460.1149, 460.1151, 460.1153. The WERZ Board was created on December 4, 2008. In its final report, dated October 15, 2009, the WERZ Board identified four regions in Michigan with the highest wind energy potential. Relevant to this case, Region No. 4, covering Huron, Bay, Saginaw, Sanilac and Tuscola counties, had a minimum wind energy generating capacity of 2,367 megawatts (MW) and a maximum of 4,236 MW. Pursuant to MCL 460.1145(6), on November 30, 2009, ITC informed the WERZ Board that [s]ignificant backbone transmission system enhancements would be required in [Region 4] due to the fact that the capacity of the transmission facilities in this region is already lower than the Board identified minimum and maximum generation capacity levels. Options presented include six 240 kV hightemperature circuits at an approximate cost of $560 million to support the minimum wind generation capacity level and eight 230 kV high-temperature circuits or four 345 kV circuits to support the maximum wind generation capacity level at approximate costs of $740 million and $510 million respectively. On January 27, 2010, pursuant to MCL 460.1147(1), the PSC formally accepted the WERZ Board s report and designated Region 4 as the primary wind energy resource zone. 2 Transmission lines of 5 miles or more in length wholly or partially owned by an electric utility, affiliated transmission company, or independent transmission company through which electricity is transferred at system bulk supply voltage of 345 kilovolts or more. MCL 460.562(g). -3- II. UNDERLYING FACTS AND PROCEEDINGS Pursuant to MCL 460.1149(4), on February 3, 2010, ITC submitted a letter to the PSC notifying it that, within 60 days or as soon as practicable thereafter, ITC intended to seek approval from the Midwest Independent Transmission System Operator, Inc. (MISO) for a transmission line that would enable realization of the wind power in Region 4. The PSC acknowledged receiving the letter and informed ITC that the letter fulfilled the notice requirements of MCL 460.1149(4). MISO ultimately approved ITC s proposed transmission line in August 2010. On August 30, 2010, ITC filed an application with the PSC requesting an expedited siting certificate authorizing the construction of a transmission line to enable the wind potential of Region 4 to be realized. The proposed transmission line included a new 345 kV double circuit tower line and four new substations. Along with the application, ITC filed direct testimony and exhibits addressing specific factors required by MCL 460.1151. The referee granted Consumers Energy, Detroit Edison, MMEA, and MPPA s petitions to intervene, and ABATE was allowed permissive intervention by the PSC. During the proceedings, appellants argued that ITC s proposed transmission line did not meet the requirements of Act 295(4) because (1) it was oversized, was too costly, and represented an unreasonable threat to the public convenience; (2) Act 295(4) did not provide authorization for construction of a transmission line because that authorization was reserved to Act 30; (3) ITC was still required to undergo the siting process of Act 30; and (4) Act 295(4) was unconstitutional and void because it displaced Act 30 s siting process. However, on February 25, 2011, the PSC issued an order granting ITC s application for an expedited siting certificate and authorizing it to construct the transmission line using the proposed route.3 The PSC determined that ITC s proofs fulfill[ed] all of the statutory requirements under MCL 460.1153 and concluded that the transmission line was of appropriate capability because it met or exceeded the maximum load and noted that the 10 percent requirement for production of electricity with renewable energy was a floor, not a ceiling. It also concluded that the size of the proposed transmission line was reasonable in light of the risk that underbuilding the line now could result in substantially higher costs and additional environmental impacts in the future if transmission capacity needed to be added. Finally, related to authorization for construction, the PSC concluded that resolving the alleged conflict between Act 295(4) and Act 30 belongs to the Commission s judicial superiors, but held that it was counterintuitive that the Legislature intended an expedited siting certificate to take 18 months4 (emphasis added). 3 There is neither a proposal for decision nor any exceptions because the PSC agreed to read the record in this case. 4 The 18-month period referred to consists of the provision in Act 295 for a maximum of 180 days to grant or deny an expedited siting certificate under this section, MCL 460.1153(6), and -4- In March 2011, appellants filed their appeals with this Court; the appeals were administratively consolidated. In re Application of Int l Transmission Co for Expedited Siting Certificate, unpublished order of the Court of Appeals, entered March 31, 2011 (Docket Nos. 303009; 303040). The PSC denied appellants motion for a stay pending resolution of this appeal. III. STANDARD OF REVIEW The standard of review for PSC orders is narrow and well-defined. All regulations, practices, and services prescribed by the PSC are presumed, prima facie, to be lawful and reasonable. MCL 462.25; Michigan Consolidated Gas Co v Public Serv Comm, 389 Mich 624, 635-636; 209 NW2d 210 (1973). A party aggrieved by a PSC order bears the burden of proving by clear and convincing evidence that the order is unlawful or unreasonable. MCL 462.26(8). To declare an order of the commission unlawful there must be a showing that the commission failed to follow some mandatory provision of the statute or was guilty of an abuse of discretion in the exercise of its judgment. The hurdle of unreasonableness is equally high. Within the confines of its jurisdiction, there is a broad range or zone of reasonableness within which the PSC may operate. [In re MCI Telecom Complaint, 460 Mich 396, 427; 596 NW2d 164 (1999) (quotation marks and citations omitted).] An order is also unreasonable if it is totally unsupported by admissible and admitted evidence. Associated Truck Lines, Inc v Public Serv Comm, 377 Mich 529, 279; 140 NW2d 515 (1966). A reviewing court gives due deference to the PSC s administrative expertise and may not substitute its judgment for that of the PSC. Attorney General v Public Serv Comm, 237 Mich App 282, 88; 602 NW2d 225 (1999). This Court gives respectful consideration to the PSC s construction of a statute that the PSC is empowered to execute and will not overrule that construction absent cogent reasons. In re Complaint of Rovas Against SBC Mich, 482 Mich 90, 103; 754 NW2d 259 (2008). If the language of a statute is vague or obscure, the PSC s construction serves as an aid to determining the legislative intent. Id. However, the PSC s interpretation is not binding on this Court and cannot conflict with the Legislature s intent as expressed in the language of the statute at issue. Id. Whether the PSC exceeded the scope of its authority is a question of law that is reviewed de novo. In re Complaint of Pelland Against Ameritech Mich, 254 Mich App 675, 682; 658 NW2d 849 (2003). the provision in Act 30 that [t]he commission shall grant or deny the application for a certificate not later than one year after the application s filing date, MCL 460.568(4). -5- IV. CONSTITUTIONALITY OF ACT 295(4) At issue in this case is the proper interpretation of Act 295(4) and Act 30. The primary goal of statutory interpretation is to determine the intent of the Legislature. Joseph v Auto Club Ins Ass n, 491 Mich 200, 205; 815 NW2d 491 (2012). The best indicator of that intent is the language of the statute itself. Id. at 205-206. The words used by the Legislature and any undefined terms are given their common and ordinary meaning. Nastal v Henderson & Assoc Investigations, Inc, 471 Mich 712, 720; 691 NW2d 1 (2005). This Court presumes that the Legislature intended the meaning clearly expressed in unambiguous statutory language and no further construction is required or allowed. Id. In addition, [s]tatutes are presumed constitutional, and courts have a duty to construe a statute as constitutional unless its unconstitutionality is clearly apparent. Taylor v Gate Pharm, 468 Mich 1, 6; 658 NW2d 127 (2003). Consistent with this mandate, apparently conflicting statutes should be construed, if possible, to give each full force and effect. In re Midland Publications, Inc, 420 Mich at 163, quoting State Hwy Comm r v Detroit City Controller, 331 Mich 337, 358; 49 NW2d 318 (1951). Appellants first contend that the PSC exceeded its authority by authorizing construction of ITC s transmission line because the expedited siting certificate authorized by Act 295(4) does not authorize actual construction of a transmission line. In addition, having interpreted Act 295(4) to authorize construction, the PSC rendered Act 295(4) unconstitutional because that interpretation created an exception to the mandatory requirements of Act 30, thereby violating Const 1963, art 4, § 25, which provides, No law shall be revised, altered or amended by reference to its title only. The section or sections of the act altered or amended shall be reenacted and published at length. There is no question that Act 30 was not re-enacted and published at length when Act 295 was passed. Therefore, to determine whether Act 295(4) violates the constitution, we must decide whether Act 295(4) seeks to revise, alter, or amend Act 30. A. AUTHORIZATION OF CONSTRUCTION Under Act 30, [i]If . . . an independent transmission company plans to construct a major transmission line in this state in the 5 years after planning commences, the . . . independent transmission company shall submit a construction plan to the commission. MCL 460.564 (emphasis added). There is no dispute that the transmission line for which ITC sought approval was a major transmission line as defined in Act 30. See MCL 460.562(g). MCL 460.565 then provides that [A]n . . . independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under [MCL 460.564] until the commission issues a certificate for that transmission line. Both of these statutes use the term shall, making them mandatory. Mich Ed Ass n v Secretary of State (On Rehearing), 489 Mich 194, 218; 801 NW2d 35 (2011). Thus, under Act 30, before beginning construction, ITC was required to submit an application for a certificate of public convenience and necessity. Appellees argue that ITC was not required to submit an application under Act 30 because the siting certificate under Act 295(4) authorized construction. The parties agree that none of the provisions in Act 295(4) expressly states that construction is authorized by issuance of a siting -6- certificate. The PSC argues that the Legislature s use of the term siting to describe the certificate which is granted evidences an intent to authorize construction. Specifically, site means to place in or provide with a site; locate or to put in position for operation. Random House Webster s College Dictionary (1997). Similarly, construction is defined under Act 295(4) as any substantial actions constituting placement or erection of the foundations or structures supporting a transmission line. MCL 460.1141(a) (emphasis added). Furthermore, certificates issued under Act 30 are not siting certificates, but certificates of public convenience and necessity for proposed major transmission lines, MCL 460.562(c), and under Act 295(4), a siting certificate is conclusive and binding as to the public convenience and necessity for that transmission line. MCL 460.1153(5). Therefore, interpreting a siting certificate to be a construction certificate would explain why there are separate construction provisions in Act 30 that are not present in Act 295(4) and why each act utilizes a different type of certificate. Furthermore, given that siting means placement, and that construction is statutorily defined as any substantial action constituting placement, construction could be interpreted as a subset of siting. Such an interpretation would satisfy the requirement that construction and siting have different meanings. See United States Fidelity Ins & Guaranty Co v Mich Catastrophic Claims Ass n, 484 Mich 1, 14; 795 NW2d 101 (2009) ( If the Legislature had intended the same meaning . . . it would have used the same word. ). Furthermore, accepting that interpretation, the application process itself is arguably a substantial action constituting placement and, therefore, constitutes construction. If that is true, then Act 295(4) necessarily authorizes construction because the very act of applying constitutes construction. Finally, authorization of construction appears implicit from the reference in MCL 460.1157, which provides, [t]his part does not prohibit an . . . independent transmission company from constructing a transmission line without obtaining an expedited siting certificate. It would be legitimate to interpret Act 295(4) s express statement that it does not prohibit construction of transmission lines without obtaining an expedited siting certificate to mean that construction is permitted with an expedited siting certificate. Under that reading, interpreting Act 295(4) not to permit construction would render MCL 460.1157 mere surplusage in violation of the rules of statutory interpretation. See Herald Co, Inc. v Eastern Michigan Univ Bd of Regents, 475 Mich 463, 470; 719 NW2d 19 (2006) (holding that courts must interpret every word, phrase, and clause in a statute to avoid rendering any portion of the statute nugatory or surplusage ). Accordingly, we hold that the PSC s interpretation of Act 295(4) to mean that issuance of an expedited siting certificate authorizes construction of the transmission line was reasonable. However, such an interpretation creates an exception to the mandatory nature of Act 30. 1. SUPREMACY CLAUSE Appellees argue that Act 295(4) has a supremacy clause that trumps the mandatory nature of Act 30. We disagree. Act 295(4) provides, in relevant part: If the commission grants an expedited siting certificate for a transmission line under this part, the certificate takes precedence over a conflicting local -7- ordinance, law, rule, regulation, policy, or practice that prohibits or regulates the location or construction of the transmission line. . . . [MCL 460.1153(4).] A general rule of statutory construction is that words and phrases shall be read in context and construed according to the rule of grammar and common usage. Duer v Newaygo Co Sheriff, 420 Mich 440, 445; 362 NW2d 698 (1984). Here, the context indicates that the term local modifies each noun in the phrase. See Hanselman v Killeen, 419 Mich 168, 179-180; 351 NW2d 544 (1984) (concluding that the introductory adjective modifies each and every one of the subsequent units or persons and does not merely modify the word directly following the adjective). This interpretation is also consistent with Act 30, which not only contains identical language in MCL 460.570, but also provides, This act shall control in any conflict between this act and any other law of this state. MCL 460.563(2). If the language of MCL 460.1153(3) in Act 295(4) was actually a supremacy clause, MCL 460.563(2) would have been unnecessary in Act 30 because MCL 460.570 would have already covered that issue. Thus, MCL 460.1153(3) is not a supremacy clause that trumps Act 30. Rather, it is Act 30 that controls any conflict. 2. THE MORE SPECIFIC, RECENTLY-ACTED STATUTE RULE Appellees also assert that Act 295(4) controls over Act 30 because it is the more specific and recently-enacted statute. The rule is that a later enacted statute operates as an exception or a qualification to a more general prior statute covering the same subject matter and . . . if there is an irreconcilable conflict between the two statutes, the later-enacted one will control. In re Midland Publications, Inc, 420 Mich 148, 163; 362 NW2d 580 (1984). Although we agree with appellees that Act 295(4) is both more specific and the more recently-enacted statute, we hold that the rule is inapplicable in this case because Act 30 explicitly states that it shall control in any conflict. MCL 460.563. Accordingly, unless and until Act 30 s supremacy clause is amended, Act 30 controls regardless of whether more specific, later-enacted statutes are passed. We conclude, then, that because Act 295(4) implicitly permits construction of wind energy transmission lines without undergoing the process in Act 30, Act 295(4) creates an exception to the mandatory nature of Act 30. Therefore, Act 295(4) revises, alters, or amends Act 30 in violation of Const 1963, art 4, § 25. B. EXCEPTION TO RE-ENACTMENT AND PUBLICATION REQUIREMENTS The parties agree that amendment by implication is an exception to Const 1963, art 4, § 25. See Alan v Wayne Co, 388 Mich 210; 200 NW2d 628 (1972); Nalbandian v Progressive Mich Ins Co, 267 Mich App 7; 703 NW2d 474 (2005). The exception was first recognized in People v Mahaney, 13 Mich 481, 496 (1865). Alan, 388 Mich at 270; Nalbandian, 267 Mich App at 12. The Mahaney court determined that the act it was considering does not assume in terms, to revise, alter or amend any prior act, or section of an act, but by various transfers of duties it has an amendatory effect by implication. . . . Mahaney, 13 Mich at 496; Alan, 388 Mich at 276-277. It continued: An amendatory act which purported only to insert certain words, or to substitute one phrase for another in an act or section which was only referred to but not republished, was well calculated to mislead the careless as to its effect, and was, -8- perhaps, sometimes drawn in that form for that express purpose. Endless confusion was thus introduced into the law, and the constitution wisely prohibited such legislation. But an act complete in itself is not within the mischief designed to be remedied by this provision, and cannot be held to be prohibited by it without violating its plain intent. [Mahaney, 13 Mich at 497.] Thus, an act complete in itself will not be found to violate Const 1963, art 4, § 25. Alan, 388 Mich at 277; Nalbandian, 267 Mich App at 14-15. The Alan court then adopted Justice Potter s dissent in People v Stimer, 248 Mich 272, 293; 226 NW 899 (1929), for the manner in which the determination of whether an act was complete in itself would be made: The character of an act, whether amendatory or complete in itself, is to be determined not by its title, alone, nor by the question whether it professes to be an amendment of existing laws, but by comparison of its provisions with prior laws left in force, and if it is complete on the subject with which it deals it will not be subject to the constitutional objection, but if it attempts to amend the old law by intermingling new and different provisions with the old ones or by adding new provisions, the law on that subject must be regarded as amendatory of the old law and the law amended must be inserted at length in the new act. [Alan, 388 Mich at 278-279 (quotation marks and citations omitted; emphasis deleted).] Thus, [i]f a bill under consideration is intended whether directly or indirectly to revise, alter, or amend the operation of previous statutes, then the constitution, unless and until appropriately amended, requires that the Legislature do in fact what it intends to do by operation. Id. at 285 (emphasis in original). However, [w]hat we say in no way affects those limited kinds of cases where because of a special fact situation a court is faced with two accidently absolutely conflicting statutes requiring a determination that one or the other applies (and thus an amendment or repeal of the other by implication follows in the fact circumstances). These kinds of cases do not result from any deliberate misleading by the Legislature or failure to make all reasonable efforts to make clear in the statutes what is intended, but rather. . . [i]t is probable that if the requirement has at any time been disregarded by the legislature, the default has proceeded from inadvertence merely. [Alan, 388 Mich at 285-286, quoting Detroit Bldg & Savings Ass n v Mok, 30 Mich 511, 517 (1875).] Accordingly, even though Act 295(4) violates the re-enactment and publication requirements of Const 1963, art 4, § 25, the act is not unconstitutional if the conflict is accidental or the act meets the requirements of being an act complete in itself. 1. ACCIDENTAL OR INADVERTENT Looking at Act 295(4), it does not appear that the conflict between Act 30 and Act 295(4) was accidental or inadvertent. Rather, Act 295(4) quite clearly resulted from the Legislature s knowledge of [Act 30] and an intent to abrogate that rule with respect to specific wind energy -9- transmission lines. Nalbandian, 267 Mich App at 14. Indeed, the definitions applicable to Act 295 include explicit references to and adopt definitions from Act 30. See MCL 460.1003(d); MCL 460.1007(c). The conflict between Act 295(4) and Act 30 was not the result of inadvertence merely, but a failure to make all reasonable efforts to make clear in the statutes what is intended. Alan, 388 Mich at 286 (citation omitted). Because the Legislature intended to amend Act 30, it was required to comply with the plain and unequivocal requirements of . . . Const 1963, art 4, § 25. Id. at 275. Appellees reliance on Alan, 338 Mich at 282, to argue that re-enactment and publication was unnecessary because it would have been unduly burdensome is similarly unavailing. Appellees rely on the following quote from Alan: If, whenever a new statute is passed, it is necessary that all prior statutes, modified by it by implication should be re-enacted and published at length as modified, then a large portion of the whole code of laws of the State would require to be re-published at every session, and parts of it several times over, until, from mere immensity of material, it would be impossible to tell what the law was. Stimer, [248 Mich at] 279, quoting Mahaney, [13 Mich at] 497. [Id.] However, the very next paragraph in Alan refuted this position and, in fact, adopted the position of the dissent in Stimer. Alan, 388 Mich at 282-283. The Supreme Court then went on to note further reasons why the objection that it will be hard work to comply with the constitution is not well taken, including technological advances in printing and copying and the Legislature s own sophisticated bill drafting and research services. Id. at 283-284. 2. COMPLETE IN ITSELF We also hold that Act 295 is not complete in itself. Comparing Act 295 s provisions with the prior laws left in force, i.e. Act 30, Act 295 is not complete on the subject with which it deals. Appellees contend that Act 295(4) is complete on the subject with which it deals because it only deals with transmission lines for electricity generated by wind energy conversion. Appellants argue that Act 295(4) deals with transmission lines and, because transmission lines are already addressed under Act 30, Act 295(4) is simply an amendment of Act 30. Both of these arguments miss the mark because they have limited their focus to Act 295(4). The relevant inquiry is whether the act, i.e. Act 295 in its entirety, is complete in itself. Nevertheless, even if the focus is limited to Act 295(4) and its purpose is defined as appellees argue, the act is still not complete by its own terms because Act 295(4) is optional. Act 295(4) provides that construction of transmission lines is not precluded without a siting certificate. MCL 460.1157. That means there is a mechanism other than Act 295(4) for permitting construction of transmission lines. Indeed, companies can utilize Act 30 to construct transmission lines, even for those delivering electricity from wind energy conversion. Thus, Act 295(4) does not even comprehensively address that limited subset of transmission lines, let alone all transmission lines. Consequently, Act 295 cannot be an act complete in itself, rendering any -10- provisions that amend Act 30 a violation of Const 1963, art 4, § 25. Nalbandian, 267 Mich App at 15-16.5 3. ABSURD RESULTS RULE Appellees suggest that the republication requirement creates an absurd and unduly burdensome result that, somehow, would preclude the conclusion that Act 295(4) is unconstitutional. [T]he so-called absurd-results rule applies in Michigan. Detroit Int l Bridge Co v Commodities Expert Co, 279 Mich App 662, 664; 760 NW2d 565 (2008). [A] statute should be construed to avoid absurd results that are manifestly inconsistent with the legislative intent. . . . Id. at 674 (quotation marks and citations omitted). Put another way, a statute need not be applied literally if no reasonable lawmaker could have conceived of the ensuing result. Id. at 675. Looking at Act 295 in its entirety, it was intended to issue certificates to companies that would permit them to begin construction on transmission lines to harness wind energy in an expedited manner, so that companies could meet their renewable energy requirements by the 2015 deadline. See MCL 460.1027. The interpretation suggested by appellants, that a company must still comply with Act 30 after completing the process under Act 295(4), eliminates any benefit for proceeding under Act 295(4) and results in the expedited process taking up to 18 months, while the traditional process takes up to 12 months. Appellants assert that the process is not necessarily longer because the two processes can be implemented simultaneously, or Act 30 s process could be started first. However, there is no logical reason why a company would ever utilize Act 295(4) if Act 30 is still required. Act 30 permits construction once a certificate of public convenience and necessity had been obtained, MCL 460.565, but a siting certificate under Act 295 is conclusive and binding as to the public convenience and necessity for that transmission line. MCL 460.1153(5). Thus, having to comply with both Act 295(4) and Act 30 wastes the time and money of both the applicant company and the PSC and provides nothing of value to either the company or the public that cannot be achieved moving forward solely under Act 30. Rather, the result of each process is a certificate regarding public convenience and necessity, only one of which actually permits construction. Thus, even if the process could be structured so that compliance with both acts did not take any longer than simply moving forward under Act 30, Act 295(4) is still rendered useless because no company would ever utilize it. Therefore, we conclude that the interpretation suggested by appellants constitutes an absurd result that is manifestly inconsistent with the legislative intent. The absurd-results rule, however, cannot render an unconstitutional act constitutional. Rather, it will simply prevent the absurd result. 5 Appellees rely on People v Cavaini, 172 Mich App 706; 432 NW2d 409 (1988), Meridian Twp v City of East Lansing, 101 Mich App 805; 300 NW2d 703 (1980), and Eyde v Lansing Twp, 79 Mich App 358; 261 NW2d 321 (1977), to support their argument that Act 295 is complete within itself. However, these cases are not binding on this Court, but Nalbandian is. MCR 7.215(J)(1). Thus, to the extent that those cases would permit a different conclusion, this Court is bound to follow Nalbandian, which implicitly rejected those cases. See 267 Mich App at 11 n 3. -11- C. A HARMONIOUS INTERPRETATION Thus, although we conclude that the PSC s interpretation of Act 295(4) to permit construction with the issuance of an expedited siting certificate was both reasonable and consistent with the legislative intent, that interpretation creates an exception to the mandatory provisions in Act 30 in violation of Const 1963, art 4, § 25. Furthermore, this Court is obligated, when possible, to construe apparently conflicting statutes in a manner that gives each statute full force and effect, In re Midland Publications, Inc, 420 Mich at 163, and to do so in a manner that not render either statute unconstitutional. Taylor v Gate Pharm, 468 Mich 1, 6; 658 NW2d 127 (2003). Here, there is an interpretation of Act 295 and Act 30 that would give each full force and effect without violating the constitution: a company that obtains a siting certificate under Act 295 must also obtain a certificate of public convenience and necessity under Act 30 before beginning construction. Even though this interpretation appears contrary to the legislative intent and violates the absurd-results rule, neither of these doctrines can render an unconstitutional provision constitutional. The only way to interpret the statutes harmoniously, without rendering Act 295 unconstitutional, is to conclude that, regardless of whether a siting certificate is obtained under Act 295, Act 30 mandates compliance with its provisions (relating to public convenience and necessity) before construction can commence. Accordingly, we so hold. V. PROSPECTIVE APPLICATION Having concluded that there is only one interpretation of Act 295(4) that renders it constitutional, we are, nevertheless, mindful of the effect of our decision. There is no question in our minds that the Legislature did not intend this result, but correcting the unintended result rests with the Legislature. Even so, after taking into account the entire circumstance confronting this Court, we conclude that our decision should have only prospective application. Although the general rule is that judicial decisions are given full retroactive effect, a more flexible approach is warranted where injustice might result from full retroactivity. Pohutski v City of Allen Park, 465 Mich 675, 695-696; 641 NW2d 219 (2002) (citations omitted). The threshold question is whether the decision clearly established a new principle of law. Id. at 696. If so, there are three factors to be considered in determining whether a decision should not have retroactive application: (1) the purpose to be served by the new rule, (2) the extent of reliance on the old rule, and (3) the effect of retroactivity on the administration of justice. Id. Although this opinion interprets Act 295(4) in the only manner possible without rendering it unconstitutional, because that result is both absurd and clearly contrary to the intent of the Legislature, our holding is akin to the announcement of a new rule of law, particularly given the erroneous, albeit reasonable, interpretation adopted by the PSC. Id. Having passed the threshold question, application of the three-part test is appropriate and leads us to conclude that prospective application is appropriate here. First, the purpose of the new rule is to correct an error in the interpretation of Act 295(4) in order to prevent it from being rendered unconstitutional. We believe this purpose would best -12- be furthered by applying it only to applications made under Act 295(4) after this opinion s date. See id. at 697; Riley v Northland Geriatric Center (After Remand), 431 Mich 632, 646; 433 NW2d 787 (1988) (GRIFFIN, J.). Second, we take into account that ITC and unknown other companies relied on the reasonable assumption, and the PSC s holding, that construction was authorized under Act 295(4) without also having to comply with the requirements of Act 30. Indeed, ITC has already invested at least $110 million in construing this project in accordance with the PSC s prima facie lawful and reasonable and order. See Michigan Consolidated Gas Co, 389 Mich at 635-636. Monopoles have been placed, wires strung, and substations built and dedicated. Prospective only application recognizes those actions taken in reliance on that interpretation. Third, prospective application minimizes the effect of this decision on the administration of justice. Retroactive application could result in additional litigation as the parties attempt to determine whether ITC s completed construction can remain and whether ongoing construction must be stopped. Prospective application eliminates these uncertainties as well as prevents tying up PSC resources on duplicative reconsideration of evidence under Act 30 in cases where it has already been thoroughly considered under Act 295(4) and construction has already begun. In addition, it provides the Legislature the opportunity to fix the absurd result created by this required interpretation without placing the energy companies at a disadvantage by stopping the ongoing construction of transmission lines that are necessary to help them meet the 2015 deadline for green energy mandates while time and money are spent on duplicative efforts under Act 30.6 Accordingly, this decision shall have immediate effect pursuant to MCR 7.215(F)(2) and shall apply only to applications brought under Act 295(4) on or after the date of this opinion. VI. APPROPRIATE CAPABILITY Appellants also assert that the PSC erroneously concluded that the transmission line proposed by ITC was of an appropriate capability, as required by MCL 460.1153(3)(d), which provides, The proposed transmission line will be of appropriate capability to enable the wind potential of the wind energy resource zone to be realized. The PSC held: Region 4 wind production capability was estimated on the record at between 2,367 MW and 4,236 MW. 3Tr. 466. The proposed transmission line will have a 5,000 MW capacity. The Commission finds that the proposed 6 We are also mindful that Proposal 12-3 -- a proposal to amend the state constitution to establish a standard for renewable energy -- is currently on the ballot in the upcoming election. Should this proposal pass, an expedited process such as the one intended by Act 295(4) may be necessary to facilitate the requirements of the proposal. However, that is for the Legislature to determine. If the Legislature finds our interpretation unacceptable, one possible solution is to amend Act 30 by adding Except as otherwise provided for by the clean, renewable, and efficient energy act to MCL 460.564(1). -13- transmission line will be of the appropriate capability to enable the wind potential of the wind energy resource zone to be realized. It is axiomatic that a planned transmission line should not be built to a size that may become overloaded. Further, building to a minimum load is wasteful and results in duplicative efforts (and costs) due to piecemeal construction. It is undisputed that the Thumb Region has the greatest potential for the development of wind farms. There is also no dispute that the current transmission capability in the Thumb Region is not sufficient to move much more electric power to market. There is unrebutted testimony on the record to the effect that the current transmission system is at or near capacity at this time and failure to add additional transmission capacity will frustrate the Legislature s direction for the Commission to facilitate the development of wind power in this state. Contrary to the assertions of ABATE and MPPA and MMEA, the requirement in Section 27 of Act 295 does not require electric providers to generate 10% of the electric requirement by 2015 via renewable energy, but to generate not less than 10% of their needs by 2015 through use of renewable resources, such as wind power. Thus, the limitation on renewable energy systems in Section 27 is a floor, not a ceiling. We conclude that the PSC s interpretation is consistent with the language of MCL 460.1153(3)(d). Contrary to appellants positions, the PSC did not equate appropriate capability with maximum. Indeed, because ITC s proposed transmission line has a 5,000 MW capacity, it exceeds the maximum estimate. The PSC also explained that preventing duplicative efforts and costs from piecemeal construction and not building to a size that could become overloaded were considerations for determining what capability was appropriate. ABATE argues that the PSC erred by declining to determine that appropriate capability means the minimum capacity, not the maximum capacity. However, this contention is at odds with ABATE s own reasoning. If it is erroneous for the PSC to read maximum into the statute, then it is equally erroneous for it to read minimum into the statute. Furthermore, interpreting the appropriate capability to be the minimum wind potential is contrary to MCL 460.1153(3)(d) which requires the line to enable the wind potential of the wind energy resource zone to be realized. Because the wind potential in Region 4 is a range that goes significantly higher than the minimum, a transmission line built only to handle the minimum wind potential would not enable the wind potential to be realized, only some wind capability. Notably, the minimum and maximum numbers were simply estimates. Thus, there is at least some possibility that more power could be generated. Therefore, the PSC s decision to require the capacity to be greater than the estimated maximum makes sense. MPPA and MMEA argue that wind potential means the amount of wind power reasonably expected to be realized. However, this definition inserts language into the statute that is not there. MCL 460.1153(3)(d) requires an appropriate capacity for the wind potential [of Region 4] to be realized. MPPA and MMEA attempt to insert a reasonability requirement that does not exist and then attempt to define what would be reasonable. Again, the statute does not authorize a transmission line that will realize some, most, or even a reasonably anticipated -14- amount of wind potential. It says the line must be capable of enabling the realization of the wind potential. Any number less than the maximum estimated capacity arguably fails to meet this standard. Finally, appellants argument that the capacity it too large because it exceeds the 10 percent renewable energy standard is meritless. Appellants have ignored the PSC s basis for rejecting that argument that the 10 percent figure represents a floor, not a ceiling. Indeed, MCL 460.1027(1) explicitly provides that companies shall achieve a renewable energy capacity portfolio of not less than the specified amounts. Thus, the fact that ITC s transmission line would exceed the 10 percent requirement is in keeping with the Legislature s mandate of a 10 percent minimum. Accordingly, appellants have failed to provide a cogent reason to overrule the PSC s construction of appropriate capability. 7 VII. FEASIBLE AND REASONABLE ROUTE Finally, ABATE argues that the PSC s conclusion that the route was both feasible and reasonable was erroneous because a letter from the Department of Agriculture indicated disagreement with ITC s position that the transmission lines would have no impact on PA 116 land and because they were concerned that property in the transmission line route might be acquired via some other property interest other than an easement. We decline to consider this issue because it is unpreserved and abandoned. ABATE not only never argued before the PSC about the specific letter from the Department of Agriculture, but it never argued any grounds to the PSC for concluding that the route was not feasible or reasonable. In addition, there is no evidence that the PSC even considered the letter on which ABATE rests its argument. The letter is not marked as received by the PSC until February 1, 2011, long after the December 1, 2010 close of the evidentiary record, and only 24 days before the PSC issued its order. Finally, ABATE has not cited a single legal citation for its argument. A party may not simply announce its position and then leave it to this Court to discover and rationalize the basis for its claims. Furthermore, a party may not give an issue cursory treatment with little or no citation of supporting authority. In re Application of Ind Mich Power Co, 275 Mich App 369, 376; 738 NW2d 289 (2007) (citations omitted). Accordingly, this issue has been abandoned. Id., citing Yee v Shiawassee Co Bd of Comm rs, 251 Mich App 379, 406; 651 NW2d 756 (2002). 7 Because the PSC appropriately interpreted the term, there is no reason to consider whether the evidence supports its decision. Appellants arguments are premised on the interpretation being erroneous. None of them argued that the PSC s decision was still erroneous even if its interpretation was proper. -15- VIII. CONCLUSION We hold that the PSC properly issued the siting certificate to ITC, but that it erroneously concluded that construction was authorized by the certificate. The only way to interpret Act 295 harmoniously with Act 30 that does not render Act 295 unconstitutional is to conclude that, regardless of whether a siting certificate is obtained under Act 295, Act 30 mandates compliance with its provisions before construction can commence. Nevertheless, after consideration of the effects of this decision, we hold that this decision is limited to prospective application. Therefore, we affirm the PSC s order in this case. /s/ E. Thomas Fitzgerald /s/ Patrick M. Meter /s/ Mark T. Boonstra -16-

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.