ATTORNEY GENERAL V MPSC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
_________________________________________
In re APPLICATION OF DETROIT EDISON
COMPANY
ATTORNEY GENERAL,
FOR PUBLICATION
July 3, 2007
9:10 a.m.
Appellant,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
DETROIT EDISON CO., and CONSTELLATION
NEWENERGY, INC.,
No. 259845
MPSC
LC No. 00-013808
Appellees.
In re APPLICATION OF DETROIT EDISON
COMPANY
_________________________________________
DETROIT EDISON COMPANY,
Appellant,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
ASSOCIATION OF BUSINESSES
ADVOCATING TARIFF EQUITY, MICHIGAN
ENVIRONMENTAL COUNCIL, PUBLIC
INTEREST RESEARCH GROUP IN
MICHIGAN, CONSTELLATION NEWENERGY,
INC., and ATTORNEY GENERAL,
Appellees.
In re APPLICATION OF DETROIT EDISON
COMPANY
-1-
No. 264099
MPSC
LC No. 00-013808
________________________________________
MICHIGAN ENVIRONMENTAL COUNCIL and
PUBLIC INTEREST RESEARCH GROUP,
Appellants,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
DETROIT EDISON CO., and CONSTELLATION
NEWENERGY, INC.,
No. 264131
MPSC
LC No. 00-013808
Appellees.
In re APPLICATION OF DETROIT EDISON
COMPANY
_________________________________________
ASSOCIATION OF BUSINESSES
ADVOCATING TARIFF EQUITY,
Appellant,
v
MICHIGAN PUBLIC SERVICE COMMISSION,
DETROIT EDISON CO., ENERGY MICHIGAN,
INC., CONSTELLATION NEWENERGY, INC.,
and ATTORNEY GENERAL,
No. 264156
MPSC
LC No. 00-013808
Appellees.
In re APPLICATION OF DETROIT EDISON
COMPANY
_________________________________________
ATTORNEY GENERAL,
Appellant,
No. 264191
MPSC
LC No. 00-013808
v
-2-
MICHIGAN PUBLIC SERVICE COMMISSION,
DETROIT EDISON CO., ENERGY MICHIGAN,
INC., CONSTELLATION NEWENERGY, INC.,
and ASSOCIATION OF BUSINESSES
ADVOCATING TARIFF EQUITY,
Official Reported Version
Appellees.
Before: Markey, P.J., and Saad and Wilder, JJ.
SAAD, J.
I. Introduction
On June 20, 2003, the Detroit Edison Company (Edison) filed its application for an
increase in its rate schedules that govern the distribution and supply of electric energy. The
hearings before the Michigan Public Service Commission (PSC) were extensive.1 And, as the
PSC noted, the proceedings before it were "among the most complex cases ever considered by
the Commission."2 Indeed, as the PSC opined in its November 23, 2004, opinion and order, this
case "affects not only the operations of the utility, but also the finances of over two million of its
residential and business customers in ways that no proceeding brought before this agency has
ever done."3
Many of the issues decided by the PSC in this rate case have not been appealed by any
party,4 but those issues appealed by Edison, the Attorney General, the Michigan Environmental
1
The PSC noted that the documents contained in the docket of this case encompass nearly
13,000 pages of testimony, exhibits, comments, and pleadings. See In re Application of Detroit
Edison Co, opinion and order of the Public Service Commission, issued November 23, 2004
(Case No. U-13808) (November 23, 2004 order), p 4 n 4.
2
In re Application of Detroit Edison Co, order of the Public Service Commission, issued
November 4, 2003 (Case No. U-13808), p 8.
3
November 23, 2004 order, supra at 1.
4
As part of this rate case, the PSC: (1) concluded that use of the staff 's proposed 2004 test year,
which was based on the historical 2002 year adjusted for inflation and other measurable changes,
was reasonable and appropriate because that year was based on known and measurable facts,
whereas Edison's proposed 2004 test year, which was fully projected and based on proposed
operating plans, budgets, and capital acquisitions, was based on assumptions as well as proposals
that had not been approved by management; (2) accepted the staff 's recommended base rate of
$7,123,560,000 for Edison, finding that that rate was reasonable because it was based on the
2002 historical test year adjusted for various known factors; (3) accepted the staff 's proposed
capital structure of 54 percent debt and 46 percent equity; (4) rejected Edison's request that it be
allowed to recover $61.6 million of the control premium paid to acquire MCN Energy; (5) found
that Edison's operation and maintenance (O&M) expenses should be reduced by $45,359,000
(continued…)
-3-
Council and the Public Interest Research Group in Michigan (MEC/PIRGIM), and the
Association of Businesses Advocating Tariff Equity (ABATE), were fully explored at a special
three-hour hearing before this Court on February 21, 2007, wherein all parties presented their
respective positions.
In Docket Nos. 259845, 264099, 264131, and 265156, the Attorney General of Michigan
(AG), Edison, MEC/PIRGIM, and ABATE appeal the PSC's November 23, 2004, order
regarding Edison's application for a rate increase. In Docket No. 264191, the AG appeals from
the PSC's order of June 30, 2005, granting in part and denying in part Edison's petition for
rehearing. These appeals have been consolidated for purposes of hearing and decision. We
affirm in part and reverse in part.
II. Facts and Underlying Proceedings
The Michigan Legislature enacted 2000 PA 141, the Customer Choice and Electricity
Reliability Act (Act 141), MCL 460.10 et seq., as part of its decision to restructure and
deregulate the electric utility industry in Michigan. Attorney General v Pub Service Comm, 249
Mich App 424, 426; 642 NW2d 691 (2002). Among other things, Act 141 reduced rates and
imposed caps on the rates that an electric utility could charge its customers. MCL 460.10d
provides in pertinent part:
(…continued)
and rejected Edison's assertion that because of the age of its generation fleet, its O&M expenses
would outstrip inflation in the coming years, and (6) rejected Edison's assertion that the 2002
historical figures, adjusted for inflation for 2003 and 2004, should be adjusted for an additional
year of inflation; (7) rejected Edison's request to recover $9.4 million in costs incurred during
2000 and 2001 to divest transmission assets, an action taken as a step toward complying with
MCL 460.10w(1), and instead adopted the staff 's position that the costs, which were incurred
when Edison transferred transmission assets to an affiliate in preparation for sale of those assets
to a third party, should be treated as an offset to the sale price in determining the premium
realized from the sale; (8) adopted the staff 's proposed transitional power supply rate (TPSR)
tariff to be applied to contracts into which Edison entered with certain large manufacturing
customers, but rejected the argument that all large manufacturing customers should be allowed to
take service under the TPSR tariff; (9) affirmed that rate caps permitted netting rate reduction
against rate increases to achieve rate adjustments, as long as the overall rate paid by customers
did not increase; (10) emphasized that it had not rejected Edison's application to establish a
PSCR factor under MCL 460.6j(18), and (11) determined that all PSCR issues not addressed in
the order could be raised in the 2004 PSCR reconciliation filing; (12) approved the inclusion of
$39,858,000 in O&M costs to fund the low-income and energy efficiency fund (LIEEF), but
rejected Edison's and the AG's assertion that the funds should be used only to serve low-income
customers in its service territory; (13) found that the hearing referee correctly concluded that
issues regarding spent nuclear fuel (SNF) should not be considered in the instant proceeding
because related issues had been addressed in other proceedings; (14) found that the PSC had
statutory authority under MCL 460.10b(1) and (6) to require Edison to establish a renewable
energy program (REP), concluded that Edison should do so, and (15) found that Edison should
raise revenue to cover any shortfall in the amounts received under the REP by implementing a
five-cent per meter, per billing cycle surcharge on all customers whose rates are no longer
capped.
-4-
(1) Except as otherwise provided under subsection (3) or unless otherwise
reduced by the commission . . . the commission shall establish the residential rates
for each electric utility with 1,000,000 or more retail customers in this state as of
May 1, 2000[5] that will result in a 5% rate reduction from the rates that were
authorized or in effect on May 1, 2000. Notwithstanding any other provision of
law or commission order, rates for each electric utility with 1,000,000 or more
retail customers established under this subsection become effective on June 5,
2000 and remain in effect until December 31, 2003 and all other electric retail
rates of an electric utility with 1,000,000 or more retail customers authorized or in
effect as of May 1, 2000 shall remain in effect until December 31, 2003.
(2) On and after December 31, 2003, rates for an electric utility with
1,000,000 or more retail customers in this state as of May 1, 2000 shall not be
increased until the earlier of December 31, 2013 or until the commission
determines, after notice and hearing, that the utility meets the market test under
[MCL 460.10f] and has completed the transmission expansion provided for in the
plan required under [MCL 460.10v]. The rates for commercial or manufacturing
customers of an electric utility with 1,000,000 or more retail customers with
annual peak demands of less than 15 kilowatts shall not be increased before
January 1, 2005. There shall be no cost shifting from customers with capped rates
to customers without capped rates as a result of this section. In no event shall
residential rates be increased before January 1, 2006 above the rates established
under subsection (1).
Edison's rates had not been comprehensively reviewed and set by the PSC since 1994,
before Act 141 was enacted. Because of an expressed need to increase its rates and in
anticipation of the expiration of the Act 141 caps, on June 20, 2003, Edison filed an application
for a general rate case to increase its rates6 and to implement a power supply cost recovery
(PSCR)7 plan and five-year forecast. MCL 460.6j(18) permits an electric utility to conduct a
PSCR proceeding in the context of a general rate case. Edison sought an increase in its rates on
5
Edison is such a utility.
6
A "general rate case" is "a proceeding initiated by a utility in an application filed with the
commission that alleges a revenue deficiency and requests an increase in the schedule of rates or
charges based on the utility's total cost of providing service." MCL 460.6a(2)(b).
7
A utility is entitled to recover the reasonable costs incurred in generating electricity. A "PSCR
clause" is "a clause in the electric rates or rate schedule of a utility which permits the monthly
adjustment of rates for power supply to allow the utility to recover the booked costs, including
transportation costs, reclamation costs, and disposal and reprocessing costs, of fuel burned by the
utility for electric generation and the booked costs of purchased and net interchanged power
transactions by the utility incurred under reasonable and prudent policies and practices." MCL
460.6j(1)(a). The PSC "may incorporate a [PSCR] clause in the electric rates or rate schedule of
a utility, but is not required to do so." MCL 460.6j(2).
-5-
both an interim and a permanent basis, approval of a regulatory asset recovery surcharge,
reinstatement of its PSCR clause, a determination of its stranded costs,8 implementation of a
mitigation adjustment mechanism, approval of an earnings-sharing mechanism, termination of its
securitization and transition charges for choice customers, and authorization to use excess
securitization savings to recover stranded costs.
The PSC entered interim orders on December 18, 2003, and February 20, 2004, that
required Edison to reinstate its PSCR clause as of January 1, 2004,9 and granted Edison interim
relief in the amount of $248,430,000, respectively.
On November 23, 2004, the PSC granted in part and denied in part Edison's request for
relief. In an order entered on June 30, 2005, the PSC granted Edison's petition for rehearing in
part and denied it in part.11 The PSC reaffirmed its holdings regarding Edison's capital structure,
rate base, and capitalization; denied Edison's request to include the control premium paid in the
acquisition of MCN in Edison's rates; and reaffirmed its holdings regarding the adjustment for
inflation of the base rate and the availability of the low-income and energy efficiency fund
(LIEEF) for customers throughout the state. More specifically, regarding Edison's assertion that
the PSC rejected its PSCR proposal pursuant to MCL 460.6j(18), the PSC concluded that it
should treat Edison's request for PSCR reinstatement and establishment of a PSCR base as
having been raised under MCL 460.6j(3) through (7), which provide for the filing of annual
PSCR plan and reconciliation cases.
10
III. Standard of Review
The standard of review for PSC orders is narrow and well-defined. Pursuant to MCL
462.25, all rates, fares, charges, classification and joint rates, regulations, practices, and services
prescribed by the PSC are presumed, prima facie, to be lawful and reasonable. Michigan
Consolidated Gas Co v Pub Service Comm, 389 Mich 624, 635-636; 209 NW2d 210 (1973). A
party aggrieved by an order of the PSC has the burden of proving by clear and satisfactory
8
The PSC has defined "stranded costs" as costs incurred during an era of regulation that are
above market prices and costs associated with the transition to competitive markets. Stranded
costs include: "(1) regulatory assets, consisting of unrecovered costs of demand-side
management programs and other similar costs, (2) capital costs of nuclear plants, (3) contract
capacity costs arising from power purchase agreements, (4) employee retraining costs, and (5)
costs related to the implementation of restructuring." Consumers Energy Co v Pub Service
Comm, 268 Mich App 171, 181; 707 NW2d 633 (2005).
9
In Detroit Edison Co v Pub Service Comm, unpublished opinion per curiam of the Court of
Appeals, issued October 4, 2005 (Docket No. 252966), another panel of this Court affirmed the
PSC's decision.
10
The hearing referee conducted extensive hearings in April 2004. Those hearings generated
3,329 pages of transcript and 235 exhibits.
11
Other parties also sought rehearing of the PSC's November 23, 2004, order.
-6-
evidence that the order is unlawful or unreasonable. MCL 462.26(8). To establish that a PSC
order is unlawful, the appellant must show that the PSC failed to follow a mandatory statute or
abused its discretion in the exercise of its judgment. In re MCI Telecom Complaint, 460 Mich
396, 427; 596 NW2d 164 (1999). And, of course, an order is unreasonable if it is not supported
by the evidence. Associated Truck Lines, Inc v Pub Service Comm, 377 Mich 259, 279; 140
NW2d 515 (1966). In sum, a final order of the PSC must be authorized by law and supported by
competent, material, and substantial evidence on the whole record. Const 1963, art 6, § 28;
Attorney General v Pub Service Comm, 165 Mich App 230, 235; 418 NW2d 660 (1987).
Consistently with the law regarding appellate review of an administrative agency's
decisions, we give due deference to the PSC's administrative expertise and will not substitute our
judgment for that of the PSC. Attorney General v Pub Service Comm No 2, 237 Mich App 82,
88; 602 NW2d 225 (1999). Importantly, we "give great weight to any reasonable construction of
a regulatory scheme that the PSC is empowered to administer," Champion's Auto Ferry, Inc v
Pub Service Comm, 231 Mich App 699, 708; 588 NW2d 153 (1998), but we may not abandon
our responsibility to interpret statutory language and legislative intent. Miller Bros v Pub
Service Comm, 180 Mich App 227, 232; 446 NW2d 640 (1989). Whether the PSC exceeded the
scope of its authority is a question of law that we review de novo. In re Complaint of Pelland
Against Ameritech Michigan, 254 Mich App 675, 682; 658 NW2d 849 (2003).
IV. Analysis
A. AG's Appeal in Docket No. 259845
1. Impact of Surcharges
The PSC possesses only that authority granted to it by the Legislature. Attorney General
v Pub Service Comm, 231 Mich App 76, 78; 585 NW2d 310 (1998). The statutes that confer
power on the PSC must be strictly construed. Authority must be granted by clear and
unmistakable language. Words and phrases in the PSC's enabling statutes must be read narrowly
and in the context of the statutory scheme. See Consumers Power Co v Public Service Comm,
460 Mich 148, 155-159; 596 NW2d 126 (1999).
As part of its effort to deregulate the electric power industry, the Legislature provided
relief to residential customers by reducing rates by 5 percent, freezing rates at that level until
December 31, 2003, and capping rates at the reduced level until January 1, 2006. MCL
460.10d(1) and (2). In its November 23, 2004, order, the PSC authorized Edison to impose new
surcharges on those customers during those periods, ruling that such surcharges were lawful
because they were offset by reductions in other rates.
The AG argues that the PSC's order is unlawful and unreasonable because it violates the
statutory prohibition against rate increases. Clearly, the imposition of a surcharge changes the
rate charged to a customer. We note that MCL 460.10d(2) uses the plural term "rates." Yet,
"every word importing the plural number may be applied and limited to the singular number."
MCL 8.3b. The AG contends that because MCL 460.10d(2) does not use the term "total rate" or
"total rates," the statute does not authorize the PSC to approve increases in some rates, even if
those increases are offset by decreases in other rates. We reject this argument.
-7-
A general rate case, and this is a general rate case, seeks an increase in rates or charges
based on the "total cost of providing service." MCL 460.6a(2)(b). The PSC has broad authority
to set just and reasonable rates and may, in the exercise of its discretion, determine what factors
are relevant in a particular case. Attorney General, supra, 231 Mich App at 79; Attorney
General v Pub Service Comm No 1, 133 Mich App 719, 725-726; 349 NW2d 539 (1984). The
PSC is not bound by any particular ratemaking methodology, and can make pragmatic
adjustments to respond to any particular circumstances in any given case. Attorney General v
Pub Service Comm, 189 Mich App 138, 148; 472 NW2d 53 (1991).
The AG contends that the term "rates" in MCL 460.10d(2) means each individual
component of a rate charged by a utility, and that each component is capped under the statute.
To accept this untenable assertion would mean that the PSC could not change a utility's rate
under any circumstances during the period in which the rate was capped. Were we to accept the
AG's position, such a ruling would undermine the PSC's broad ratemaking authority and
contradict the plain language of MCL 460.10d(8), which provides: "Except as provided under
subsection (3), until the end of the period in subsection (2), the commission shall not authorize
any fees or charges that will cause the residential rate reduction required under subsection (1) to
be less than 5%." The import of the language of MCL 460.10d(8) is that the PSC may authorize
raises in individual components of a rate as long as the raises do not increase an overall rate
above the (reduced) rate mandated by the Legislature as set forth in MCL 460.10d(1) and the
capped rate mandated by MCL 460.10d(2). This construction avoids conflict among the statutes,
and therefore should and does control. House Speaker v State Admin Bd, 441 Mich 547, 568569; 495 NW2d 539 (1993).
The PSC's decision to increase some rates while reducing others to avoid an overall
increase is clearly within the PSC's broad ratemaking authority and discretion, and is a
reasonable interpretation of the statutory scheme that it is empowered to administer. Champion's
Auto Ferry, supra.12
2. Transmission Expenses
Our review of this issue begins with the pertinent statutory provision. MCL 460.6j
provides in relevant part:
(1) As used in this act:
12
The filed-rate doctrine holds that a public utility can claim no right to a rate other than the
filed rate either fixed or accepted by the PSC. Detroit Edison Co v Pub Service Comm, 416
Mich 510, 516; 331 NW2d 159 (1982). Contrary to the AG's assertion, the PSC's November 23,
2004, order does not violate the filed-rate doctrine. All charges imposed by Edison are reflected
in filed tariffs.
-8-
(a) "Power supply cost recovery clause" means a clause in the electric
rates or rate schedule of a utility which permits the monthly adjustment of rates
for power supply to allow the utility to recover the booked costs, including
transportation costs, reclamation costs, and disposal and reprocessing costs, of
fuel burned by the utility for electric generation and the booked costs of
purchased and net interchanged power transactions by the utility incurred under
reasonable and prudent policies and practices.
(b) "Power supply cost recovery factor" means that element of the rates to
be charged for electric service to reflect power supply costs incurred by an
electric utility and made pursuant to a power supply cost recovery clause
incorporated in the rates or rate schedule of an electric utility.
The AG contends that the PSC's November 23, 2004, order is unlawful and unreasonable
because it allows Edison to include transmission expenses in its PSCR clause. Transmission
expenses are properly accounted for in a specific account established under the PSC's Uniform
System of Accounts for Major and Nonmajor Electric Utilities. Mich Admin Code, R 460.9001.
The AG asserts that the PSC had no authority to allow Edison to recover costs through a PSCR
clause if that recovery is not authorized by statute. Attorney General, supra, 231 Mich App at
78. We reject this position because it is contrary to the express language of the statute and
would lead to absurd results.
To comply with MCL 460.10w(1), Edison sold its transmission assets to International
Transmission Company (ITC), a member of Midwest Independent System Operators. Edison no
longer owns transmission assets, and now purchases transmission services pursuant to rates set
by the Federal Energy Regulatory Commission (FERC).13
Neither subsection MCL 460.6j nor any accounting rule prohibits an adjustment to a
PSCR clause to account for transmission costs. Obviously, power must be transmitted for it to
be distributed to a utility's customers. Payments made by Edison for transmission costs, which
are made to comply with federal law, are necessarily "transportation costs," and therefore are
properly recoverable in a PSCR clause. MCL 460.6j(1)(a). The PSC's decision to allow Edison
to recover transmission costs in its PSCR proceeding is (1) within the PSC's broad ratemaking
authority, Attorney General, supra, 231 Mich App at 79; (2) consistent with the language of Act
304 in general and MCL 460.6j in particular, Consumers Power Co, supra at 157 n 8, and,
importantly, (3) consistent with the PSC's previous decisions and decisions of this Court.14
13
FERC has jurisdiction over the rates, charges, and rules and regulations pertaining to
transmission services pursuant to various provisions of the Federal Power Act, 16 USC 824 et
seq.
14
See, e.g., Michigan Environmental Council v Pub Service Comm, unpublished opinion per
curiam of the Court of Appeals, issued May 11, 2004 (Docket Nos. 244354, 246744), slip op at
5-6. This decision lacks precedential authority, MCR 7.215(C)(1), but we consider its analysis
(continued…)
-9-
3. LIEEF: Assistance to Low-Income Customers
In Act 141, the Legislature created the LIEEF and charged the PSC with administering
the fund. MCL 460.10d(7) reads in pertinent part:
If securitization savings exceed the amount needed to achieve a 5% rate
reduction for all customers, then, for a period of 6 years, 100% of the excess
savings, up to 2% of the electric utility's commercial and industrial revenues, shall
be allocated to the low-income and energy efficiency fund administered by the
commission. The commission shall establish standards for the use of the fund to
provide shut-off and other protection for low-income customers and to promote
energy efficiency by all customer classes.
In its interim order, the PSC acknowledged that upon the issuance of interim relief
Edison would no longer have securitization savings, and therefore it approved the inclusion of
$39,858,000 in Edison's operation and maintenance (O&M) costs to fund the LIEEF in 2004 and
thereafter. In its November 23, 2004, order, the PSC concluded that those funds could be used
throughout the state, not only to serve low-income customers in Edison's service territory.
The AG asserts that the PSC's November 23, 2004, order is unlawful and unreasonable
because it requires Edison's customers to provide monies for the LIEEF that will not be used in
Edison's service territory which serves no rational purpose. We disagree.
Relevant statutes refer to "the" LIEEF, which strongly suggests that the Legislature
intended to create a single fund.15 Moreover, no statutory language limits the use of a utility's
funds to that utility's service territory. Further, the fact that only Edison and Consumers Energy
had 1 million or more retail customers as of May 1, 2000, and thus were the only electric utilities
required to reduce rates pursuant to MCL 460.10d(1) and (2), and so contribute securitization
savings to the LIEEF, supports the PSC's conclusion that securitization savings contributed to
the LIEEF by Edison and Consumers could be used throughout the state. Because the PSC's
interpretation of the authorizing legislation is reasonable, it is entitled to deference. Attorney
General, supra, 237 Mich App at 88; Champion's Auto Ferry, supra.
We also reject the AG's argument that the PSC's order should be reversed because, in the
AG's view, the decision to fund the LIEEF through Edison's O&M costs is unwise. A court's
function is simply to apply the public policy promulgated by the Legislature, not to rule on the
(…continued)
persuasive because it reflects judicial adoption of the PSC's interpretation of a statute that the
PSC is legislatively authorized to administer.
15
The use of the word "the" designates a definite object.
Oldsmobile, Inc, 266 Mich App 61, 79; 697 NW2d 558 (2005).
-10-
See Hashem v Les Stanford
wisdom of social policy.16 Hanson v Mecosta Co Rd Comm'rs, 465 Mich 492, 504; 638 NW2d
396 (2002).
4. Funding of Renewable Energy Program
The PSC maintains that MCL 460.10b(1) and MCL 460.10r(6) empower the PSC to grant
Edison the authority to impose a charge of $0.05 a meter, each month, to pay for the cost of
Edison's renewable energy program (REP). MCL 460.10b(1) authorizes the PSC to "establish
rates, terms, and conditions of electric service that promote and enhance the development of"
new energy technologies. MCL 460.10r(6) empowers the PSC to establish a REP designed to
inform customers of the availability of and the value of using renewable power, to promote the
use of existing sources of renewable power, and to encourage the development of new sources of
such power.
The AG acknowledges that the Legislature authorized the PSC to establish a REP
designed to achieve the aforementioned objectives. However, the AG argues here, as it
successfully maintained in Attorney General v Pub Service Comm, 269 Mich App 473; 713
NW2d 290 (2006), that the PSC lacked the statutory authority to empower Edison to impose an
additional charge of $0.05 a meter, each month on all customers (whose rates were not capped)
to subsidize the cost of Edison's REP. We agree.
In Attorney General v Pub Service Comm, supra, 269 Mich App 473, another panel of
this Court ruled that because neither MCL 460.10b(1) nor MCL 460.10r(6) specifically
authorized the PSC to enable a utility to compel all customers to pay a surcharge to support a
voluntary REP, the PSC "exceeded its authority in concluding to the contrary":17
We hold that the PSC lacked the statutory authority to authorize CEC to
impose an additional charge of $0.05 a meter each month on all customers,
including customers who had not agreed to pay a premium to receive green
power, to finance the development of renewable resource power programs. The
PSC established a renewable energy program, as required by MCL 460.10r(6).
The PSC's authority to set rates that facilitate the development of new energy
technologies is set out in MCL 460.10b(1); however, that authority does not
include the power to make management decisions on behalf of a utility. Union
Carbide Corp v Pub Service Comm, 431 Mich 135, 148; 428 NW2d 322 (1988).
The PSC's ability to consider a wide variety of factors when setting rates is wellestablished, Detroit Edison Co v Pub Service Comm, 221 Mich App 370, 375;
562 NW2d 224 (1997), but is not unlimited. MCL 460.10b(1) and MCL
460.10r(6) were enacted as part of CCERA [Act 141]. The Legislature clearly
16
We do not mean to suggest by this that we in fact question the wisdom of this specific policy.
Instead, we simply reiterate that this is not the judiciary's role.
17
Attorney General, supra, 269 Mich App at 480-482.
-11-
intended consumer participation in green power programs to be voluntary.
Neither MCL 460.10b(1) nor MCL 460.10r(6) specifically authorizes the PSC to
enable a utility to compel customers to pay to support a voluntary renewable
resource energy program even if they have not chosen to receive power from the
program. The PSC exceeded its authority in concluding to the contrary.
[Attorney General, supra, 269 Mich App at 481-482, citing In re Complaint of
Pelland, supra.]
This case is controlling law18 and therefore mandates our holding that the portion of the PSC's
November 23, 2004, order that authorized Edison to impose a surcharge of $0.05 a meter, each
month on all customers is unlawful.19 MCL 462.26(8). Accordingly, we reverse this part of the
PSC's ruling.
B. Edison's Appeal in Docket No. 264099
1. Calculation of Working Capital/Short-Term Debt
In order to calculate Edison's revenue requirements, the PSC had to determine the rate of
return to be applied to Edison's base rate.20 To do this, the PSC had to determine Edison's capital
structure as well as its cost of capital. The PSC rejected Edison's recommendation of a capital
structure of 50 percent debt and 50 percent equity for the test year 2004 in favor of the staff 's
proposed structure of 54 percent debt and 46 percent equity. The PSC observed that the
adoption of a 46 percent equity ratio presented a significant improvement over the 40 percent
ratio approved in Edison's previous rate case, and served to balance the interests of Edison and
its ratepayers.
The PSC found that Edison's long-term debt cost was 6.31 percent. The PSC rejected
Edison's claim of short-term debt of $98.9 million at an interest rate of 2.30 percent, and instead
agreed with the staff that Edison carried $279 million in short-term debt at an interest rate of
2.30 percent.
Edison argues that the PSC's November 23, 2004, order is unlawful and unreasonable
because the PSC failed to reduce Edison's short-term debt or increase its working capital so that
Edison's base rate, i.e., its assets, would equal its capitalization, i.e., its liabilities. Edison asserts
that the PSC uses uniform accounting methods, MCL 460.556; Attorney General v Pub Service
18
MCR 7.215(J)(1).
19
Indeed, our Supreme Court denied the PSC's appeal of our Court's holding and, on July 25,
2006, the PSC issued an order that implemented this Court's decision that the collection of a
monthly $0.05 a meter charge for green-power pilot costs is unlawful.
20
The hearing referee found that Edison's base rate is $7.12 billion, and noted that at the time of
the hearing, Edison had "about $3.5 billion in debt." Notice of Proposal For Decision at 14.
Case 11-13808.
-12-
Comm, 262 Mich App 649, 651, 658-659; 686 NW2d 804 (2004), and determined in a previous
rate case that the balance sheet method must be used for determining a utility's base rate,
including working capital, in a rate case.21 However, by adopting the staff 's conclusion that
Edison carried $279 million in short-term debt, the PSC found that Edison's total liabilities
exceeded its assets by approximately $125 million. Edison asserts that its total working capital
must be increased by $125 million, or in the alternative its short-term debt must be reduced by
$125 million, so that total capitalization and total assets match. Making this adjustment would
increase Edison's rates by $13.4 million. We disagree.
The staff used a six-month average to calculate Edison's short-term debt at $279 million,
whereas Edison contended that a 12-month average should have been used to calculate the debt
at $98.9 million. The PSC adopted the staff 's method to calculate short-term debt on the ground
that it was more reasonable. Edison disagrees with the PSC's conclusion, but, aside from
referring to the order in a previous case, does not specify in what way the PSC's decision is
unlawful, unreasonable, or not supported by the requisite evidence. Also, Edison's reliance on
the order in Case No. U-7350 is misplaced. That order addressed the appropriate methodology
for determining a working capital allowance, but did not fix the appropriate methodology for
determining short-term debt. Edison suggests that the PSC should have adopted its calculations
rather than those offered by the staff; however, the PSC was entitled to rely on the evidence
provided by the staff, notwithstanding the existence of contradictory evidence. See Great Lakes
Steel Div of Nat'l Steel Corp v Pub Service Comm, 130 Mich App 470, 481-482; 344 NW2d 321
(1983). Though this is a close question and we recognize that Edison's position has merit,
because the total impact of the PSC's decision regarding Edison's base rate and capitalization is
not unjust or unreasonable, and because we grant deference to the PSC, we will not interfere
with the PSC's exercise of its discretion. See Michigan Bell Tel Co v Pub Service Comm, 332
Mich 7, 38-39; 50 NW2d 826 (1952).
2. Recovery of Control Premium
As the PSC staff opined and the hearing referee recommended, we hold that the
substantial savings to Edison customers are a direct result of the acquisition of Michigan
Consolidated Gas Company (MichCon) and that these synergistic savings fully justify the pass-
21
In In re Proceedings on the Appropriate Methodology to be Used, for Ratemaking Purposes,
in Determining Working Capital Allowance of Regulated Gas, Electric and Telephone Utilities
in Michigan, opinion and order of the Public Service Commission, issued June 11, 1985 (Case
No. U-7350), the PSC investigated which method—the formula approach, the lead/lag method,
or the balance sheet method—was most appropriate for determining a working capital allowance
for ratemaking purposes. The PSC determined that the balance sheet method, which "is an
analysis of all of the assets of the utility to determine which are used to provide service and an
analysis of all utility liabilities to determine the extent to which assets are funded by capital that
is tied to the earnings of the utility," id. at 4, was the "most appropriate and fairest method for
determining a working capital allowance," and was "to be used for all rate cases filed after the
date of this order." Id. at 12.
-13-
through of the acquisition control premium. Edison seeks and is entitled to that portion of the
control premium that permits Edison to accomplish these synergistic savings. We hold that
Edison is clearly entitled to recover its share of the control premium that resulted in these
synergistic savings. Like the hearing referee, we reject the arguments of the AG and
MEC/PIRGIM in opposition to Edison's rate request regarding the control premium. Of course,
the PSC should determine the precise amount of the appropriate recovery and the period over
which to amortize Edison's recovery of its portion of this control premium.
In May 2001, DTE, Edison's parent company, paid $2.48 billion to acquire MCN Energy,
the parent company of MichCon. DTE paid a control premium of $894 million to acquire
MCN.22 DTE allocated 66 percent, or $589 million, of the control premium to Edison on the
basis of the estimated synergistic savings, i.e., the savings that arose from increased efficiency
resulting from the merger, to be realized by Edison, for the benefit of Edison's customers.
Therefore, in this rate case, Edison sought to recover its portion of the control premium through
amortization over a period of 40 years, and accordingly requested recovery of $61.6 million for
the year 2004.
Though the hearing referee rejected Edison's request for $61.6 million, he recommended
inclusion of $46.2 million in Edison's rates for 2004, which is the amount the PSC staff
recommended. The PSC staff and the hearing referee both opined that the synergistic savings
fully justifies Edison's recapture of its share of the control premium. The hearing referee
concluded that Edison introduced substantial, unrebutted evidence of cost savings that resulted
directly from the acquisition and merger which justified the pass-through of the control
premium. Though holding that recovery is justified, the hearing referee nonetheless rejected
Edison's request to recover the control premium over a 40-year amortized period because he
opined, and we agree, that it would be too speculative to forecast savings over such a lengthy
period. Therefore, the hearing referee concluded, and we hold, that Edison is required to
substantiate savings in its next rate case in order to continue recovering the control premium.
The PSC determined, incorrectly in our view, that no part of the premium should be
included in Edison's rates, and noted that DTE's decision to pay a premium for the acquisition of
MCN was not subject to oversight and came at a time when MCN was in financial distress.
Simply stated, these are not valid reasons to deny Edison the relief it seeks. The PSC's clearly
erroneous decision resulted in a reduction of $46.2 million in Edison's revenue requirement for
2004, and a significant reduction of hundreds of millions in the future.
22
A control premium, also known as an acquisition premium, is the difference between the
purchase price and the market value of the acquired company immediately before the
announcement of the acquisition. See In re Application of Michigan Gas Co, order of the Public
Service Commission, issued June 29, 1990 (Case No. U-9323), p 19 n 5. DTE paid $2.488
billion for MCN, a price that was $1.478 billion over MCN's book value. The difference
between MCN's market value immediately before the announcement of the acquisition and the
purchase price paid by DTE was $894 million.
-14-
Edison maintains that the PSC's decision to disallow recovery of Edison's portion of the
control premium is unlawful and unreasonable for three reasons. We agree. First, the decision
ignored the substantial savings that resulted from the acquisition and merger, and, by denying
recovery of the cost of the investment, denied Edison its right to earn a reasonable rate of return
on its investment in providing service. See, e.g., Michigan Consolidated Gas Co, supra at 640.
Second, the PSC failed to apply the "net benefit" standard it articulated in a previous case23 for
determining whether Edison should be allowed to recover control premium costs. Edison's
customers benefited from the acquisition in the form of lower costs resulting from acquisitionrelated cost savings. Third, the PSC ignored its own role in allowing the acquisition to go
forward. The PSC approved a contract between Michigan Consolidated Gas Company and
Exelon, a Chicago-based energy company, as a prerequisite to the Federal Trade Commission's
approval of the acquisition. Thus, because the PSC was aware of the acquisition while it
happened, and took no steps to register any objections, the PSC cannot now disavow its actions
and deny Edison the benefit of the acquisition. See, e.g., Consumers Energy Co v Pub Service
Comm No 2, 261 Mich App 455, 459-460; 683 NW2d 188 (2004).
Edison also asserts that the PSC's decision is not supported by competent, material, and
substantial evidence on the whole record. Again, we agree. The PSC purported to question why
DTE paid a premium for a company that was in financial distress, but acknowledged that it had
no basis to question the appropriateness of the acquisition or the price paid by DTE for MCN.
Furthermore, record evidence showed that MCN's market value reflected the diminished
financial position of the company, and that the purchase price was within the range for
comparable transactions. The PSC's conclusion that the acquisition provided no benefit to
Edison's customers is simply unsupported by any record evidence. To the contrary, there is
substantial evidence on the record that the acquisition resulted in a savings of $112.6 million in
2004. Indeed, Edison showed by clear evidence that if Edison were permitted to recover $61.6
million of the control premium, Edison's customers would realize more than $50 million in
savings in 2004 alone.
Moreover, though DTE, not Edison, paid the control premium, we hold that that is not a
sufficient reason to deny Edison recovery of its portion of the control premium. As the hearing
referee noted, parent companies routinely incur costs and apportion those costs to subsidiaries.
Further, the hearing referee properly found that Edison's customers recognized significant
tangible benefits in the form of reduced expenses as a direct result of this merger. Therefore, we
conclude that it is reasonable to allow Edison to recover its portion of the costs incurred to
realize those savings. See Michigan Bell Tel Co, supra at 21-22.24
23
Case No. U-9323.
24
We reject Edison's assertion that the PSC improperly disavowed the acquisition it had
previously approved, at least implicitly. The PSC had no authority to approve the acquisition,
Consumers Power Co, supra at 155, and had no role in doing so.
-15-
Similarly, we hold that Edison is entitled to recover its allocated share of the control
premium. Thus, we reverse that portion of the PSC's decision denying Edison's request to
recover its allocated portion of the control premium and remand this matter to the PSC for
further proceedings to establish the precise amount and timing of this recovery.
3. Adjustment of Test Year
Edison's application for a rate increase was based on a forecasted 2004 test year. The
PSC rejected Edison's test year and adopted the staff 's methodology of using a 2002 historical
test year adjusted for inflation at the rate of 2 percent annually for both 2003 and 2004.
Edison notes that the PSC's final order was not released until November 2004, a full 17
months after Edison's application was filed,25 which postponed the effect of the rate adjustments
until the end of 2004. Edison contends that the PSC's failure to adjust the staff 's 2004 test year
for an additional year of inflation at 2 percent, which would have increased Edison's O&M
expenses by $24.6 million, is unlawful and unreasonable. We disagree.
The proceeding before the PSC combined Edison's first general rate case in more than 10
years with Edison's request to reinstate its PSCR clause. A test year used to set rates need not
coincide precisely with the year that such rates are implemented. Detroit Edison Co v Pub
Service Comm, 127 Mich App 499, 508; 342 NW2d 273 (l983). The establishment of the test
year was within the PSC's discretion. There is no evidence that the PSC did not act with all
appropriate dispatch. Edison has not shown by clear and satisfactory evidence that the PSC's
decision not to adjust the test year for an additional year of inflation is unlawful or unreasonable.
MCL 462.26(8).
C. MEC/PIRGIM's Appeal in Docket No. 264131
We note at the outset of our analysis of MEC's and PIRGIM's appeal that these same
plaintiffs challenged the PSC's identical determination regarding spent nuclear fuel (SNF) issues
in In re Application of Indiana Michigan Power Co, 275 Mich App 369; ___ NW2d ___ (2007).
In Indiana, we rejected each and every legal challenge MEC and PIRGIM raise here. Therefore,
for the reasons and on the grounds set forth in our decision in Indiana and under the doctrine of
collateral estoppel, we reject all of plaintiff's arguments regarding the SNF-related issues and
hold that the PSC properly rejected all of MEC/PIRGIM's SNF-related challenges.
D. ABATE's Appeal in Docket No. 264156
1. Special Manufacturing Contracts
25
MCL 460.6a(2) directed the PSC to decide the rate case within nine months, and MCL
460.6a(3) required the PSC to file reports explaining the reason for any delay beyond those nine
months.
-16-
Edison entered into special manufacturing contracts (SMCs) with large manufacturing
customers, including General Motors Corporation, Ford Motor Company, and Chrysler
Corporation. The PSC approved the SMCs26 and allowed Edison to offer service to these large
customers at a rate below what they would have paid absent these contracts.
Over time, other utilities became able to offer service to these large customers at
competitive rates. To avoid seeking recovery from other customers of a portion of the loss
incurred from serving the large customers, Edison sought to recover at least a portion of the
discounts by imputing the discounts into its rates. To avoid the PSC disallowing recovery of the
discounts, as the PSC had indicated that it would, the staff recommended a transitional power
supply rate (TPSR) tariff for former SMC customers. The staff 's proposed tariff set rates
midway between those charged under the SMCs and those in Edison's regular industrial tariffs.
Edison and ABATE also proposed TPSR tariffs, and ABATE proposed that all large
manufacturing customers, and not just former SMC customers, be charged under the TPSR tariff.
In its November 23, 2004, order, the PSC adopted the staff 's recommendation that the
TPSR tariff be applied to former SMC customers only. The PSC found that the adoption of a
TPSR tariff for former SMC customers only did not "violate the prohibition against
discriminatory rates, as special contract customers differ in circumstance from those customers
that have not been served under those contracts." The PSC reasoned that adoption of a TPSR
tariff was "a rational method to mitigate the harm that other customers might endure should the
special contract customers leave the system entirely."
ABATE sought a rehearing and challenged the PSC's decision to limit the applicability of
the TPSR tariff to former SMC customers. In an order entered on June 30, 2005, the PSC denied
the petition.
MCL 460.557(4) provides, in pertinent part:
The rates of an electric utility shall be just and reasonable and a consumer
shall not be charged more or less than other consumers are charged for like
26
In its November 23, 2004, order, supra at 74-75, the PSC noted that in its orders approving the
SMCs, Edison agreed that it
would have the burden to demonstrate that either the prices of the special contract
are justified on a cost of service basis, or that the benefits for other customers are
substantial and outweigh the costs that are not recovered from the special contract
customer.
The Commission consistently affirmed that Detroit Edison's
shareholders should expect to bear much if not all of any revenue shortfall that
results from the special contracts. . . . In addition, the Commission has found that
before any recovery related to these contracts, Detroit Edison would be required
to demonstrate that service provided in conjunction with the contracts has not,
and will not in the future, impede the development of competition in its service
territory.
-17-
contemporaneous service rendered under similar circumstances and conditions.
An electric utility doing business within this state shall not, directly or indirectly
by a special rate, rebate, draw-back, or other device, charge, demand, collect, or
receive from a person, partnership, or corporation, a greater or lesser
compensation for a service rendered than the electric utility charges, demands,
collects, or receives from any other person, partnership, or corporation for
rendering, a like contemporaneous service.
ABATE argues that the PSC's adoption of a TPSR tariff limited to former SMC
customers discriminates against other large manufacturing customers, and thus is unlawful under
MCL 460.557(4). We disagree.
The PSC has broad ratemaking authority. See MCL 460.6. The PSC is not bound by any
single ratemaking formula, and may make pragmatic adjustments when warranted by the
circumstances of the particular matter before it. Detroit Edison Co, supra, 221 Mich App at
373-375. Rate design is legislative in nature, and we will not disturb a rate-design decision
absent a showing that the decision is arbitrary, capricious, or an abuse of discretion. Id. at 381.
The PSC determined that in light of the rate shock that the SMC customers would
experience if subjected to regular tariff rates and the possibility that these customers might
therefore leave Edison's service entirely, thereby depriving Edison of a significant portion of its
revenues,27 the implementation of a TPSR tariff was a pragmatic solution. Edison rendered
service to customers covered by SMCs "under similar circumstances and conditions" that
differed from the conditions under which it rendered service to other large manufacturing
customers and the PSC's decision to limit the applicability of the TPSR tariff to SMC customers
continued this practice. The TPSR tariff conforms to MCL 460.557(4) in that it treats all SMC
customers the same and applies the same ratemaking methodology to each of these customers.
ABATE's reliance on City of Ishpeming v Pub Service Comm, 370 Mich 293; 121 NW2d
462 (1963), as support for its position that the PSC erred by limiting the applicability of the
TPSR tariff to SMC customers, is misplaced. In that case, the Upper Peninsula Power Company
(UPPC) eliminated four separate tariffs being charged for similar service in a ten-county area,
and implemented an area uniform rate. The city of Ishpeming had a contract with a successor to
the UPPC, and pursuant to that contract, received electric power at a lower rate than that charged
under the UPPC's new uniform tariff. The city sought to set aside the PSC's order that the UPPC
implement a uniform tariff for the area. Our Supreme Court held that the PSC's order was valid,
noting that the PSC "had a right and duty to eliminate discrimination" under MCL 460.557 as the
statute read at that time. Id. at 302.
27
In an order approving the SMCs for General Motors, Ford, and Chrysler, the PSC noted that
the automotive facilities covered by the contracts accounted for 9 percent of Edison's retail
electric revenues. Furthermore, the evidence showed that extending the TPSR tariff to all large
manufacturing customers would have decreased Edison's revenues by $10 million a year.
-18-
The Ishpeming Court's decision that the city was not entitled to continue receiving power
at its former rate was based on the finding that no evidence showed that the city was entitled to
rate disparities or differentials that had been in place before implementation of the uniform rate.
Id. at 312. Here, there is simply no evidence that all large manufacturing customers would
experience the same rate shock as would the SMC customers upon returning to Edison's regular
tariff rates. The PSC was within its ratemaking authority to address this discrepancy by limiting
the applicability of the TPSR tariff to SMC customers. Detroit Edison Co, supra, 221 Mich App
at 373-375. The PSC's decision to limit the applicability of the TPSR tariff to SMC customers
did not violate MCL 460.557(4), and the PSC's order is not unlawful. In re MCI Telecom
Complaint, supra at 427.
2. Sufficiency of the Evidence
A decision of the PSC must be supported by competent, material, and substantial
evidence on the whole record, and must include findings of fact and conclusions of law that
allow for appellate review. Const 1963, art 6, § 28; MCL 24.285. ABATE argues that the PSC's
decision adopting the TPSR tariff violates Const 1963, art 6, § 28, MCL 24.285, and the doctrine
of due process in that it is not based on competent, material, and substantial evidence on the
whole record. ABATE asserts that the PSC cited no evidence to support its finding that limiting
the applicability of the TPSR tariff to SMC customers did not violate MCL 460.557(4). We
disagree.
The record in this case consists of more than 3,200 pages of transcript and more than 230
exhibits. To require the PSC to have set out in exhaustive detail the rationale behind every issue
before it would have required the PSC to produce an opinion and order of unmanageable length
and complexity. The PSC's discussion of the parties' competing proposals regarding
implementation of a TPSR tariff was based on sufficient evidence in the record, and the PSC
stated adequate reasons for its decision.
E. AG's Appeal in Docket No. 264191
MCL 460.6j(18) provides in pertinent part:
Notwithstanding any other provision of this act, the commission may,
upon application by an electric utility, set power supply cost recovery factors, in a
manner otherwise consistent with this act, in an order resulting from a general rate
case. . . . If the commission sets power supply cost recovery factors in an order
resulting from a general rate case:
(a) The power supply cost recovery factors shall cover a future period of
48 months or the number of months which elapse until the commission orders
new power supply cost recovery factors in a general rate case, whichever is the
shorter period.
(b) Annual reconciliation proceedings shall be conducted pursuant to
subsection (12) and if an annual reconciliation proceeding shows a recoverable
amount pursuant to subsection (15), the commission shall authorize the electric
-19-
utility to defer the amount and to accumulate interest on the amount pursuant to
subsection (16), and in the next order resulting from a general rate case authorize
the utility to recover the amount and interest from its customers in the manner
provided in subsection (15).
(c) The power supply cost recovery factors shall not be subject to revision
pursuant to subsection (10).
In its application for a general rate case filed with the PSC on June 20, 2003, Edison
requested interim and final rate relief, and also made the following request with respect to its
PSCR clause:
11. Applicant is requesting, pursuant to Act 304, MCL 460.6j(18), that
the Commission reinstate the Company's PSCR mechanism for 2004 in this case,
coincident with approval of the Company's request for a mitigation adjustment to
operate in tandem with the PSCR mechanism. Because it is imperative that the
Company's overall revenue deficiency be considered in tandem with the
reinstatement of the 2004 PSCR mechanism, Applicant requests that the PSCR
clause remain suspended and that implementation of a new factor not begin until
the date of the Commission order authorizing adequate and compensatory relief
for the Company.
12. As stated above, Applicant requests the reinstatement of the proposed
PSCR mechanism and mitigation adjustment for the period commencing with the
later of January 1, 2004, or the issuance of a Commission order granting the
Company's request for adequate and compensatory relief, through December 31,
2004; and subsequently, through a separate PSCR Plan and factor for the 12month period January 1, 2005, through December 31, 2005. Pursuant to the
provisions of Act 304, each PSCR factor and plan established in this case will be
subject to the annual reconciliation procedures, as referenced in MCL 460.6j(18),
to be conducted in this docket.
Paragraph 12 of Edison's application contained the following footnote:
As part of this proposal, Applicant is requesting that in the event a
Commission order granting the necessary rate relief occurs subsequent to January
1, 2004, that the remaining months in 2004 be considered the first partial PSCR
reconciliation period. Thereafter beginning with 2005, PSCR reconciliation
would occur on a calendar year basis.
The PSC issued interim orders that held that Edison's PSCR clause automatically
reinstated on January 1, 2004, when the rate freezes imposed by MCL 460.10d(1) expired, and
granted, in part, Edison's request for interim rate relief. However, the PSC declined to act on
Edison's PSCR plan at that time on the ground that the PSCR clause had been automatically
reinstated.
-20-
In the proposal for decision (PFD), the hearing referee noted that Edison had stated that it
anticipated filing a separate 2005 PSCR plan case by September 30, 2004,28 and, on that basis,
concluded that Edison had withdrawn its request for approval of a PSCR plan as part of the
general rate case. Edison denied that it had withdrawn its PSCR plan, and contended that the
PSCR plan should continue to be addressed with the general rate case. Edison asserted that its
filing of a PSCR plan pursuant to MCL 460.6j(18) was proper, but that the PSC had, implicitly at
least, rejected that application and instead established a 2004 PSCR plan pursuant to MCL
460.6j(3)-(7).29
In its November 23, 2004, order, the PSC stated that it had not rejected Edison's
application to establish a PSCR plan under MCL 460.6j(18). However, the PSC stated that given
the hearing referee's failure to address the PSCR issues in the PFD, the PSC was left with the
problem of how to fashion an appropriate remedy. Furthermore, the PSC decided that all PSCR
issues not addressed could be addressed in Edison's 2004 PSCR reconciliation case, to be filed
no later than March 31, 2005. Finally, the PSC directed the hearing referee in Case No. U-14275
to address whether Edison's application for a 2005 PSCR plan was permitted in light of the
requirement of MCL 460.6j(18) that PSCR factors cover a period of 48 months.30
Edison sought rehearing of the PSC's November 23, 2004, order, and argued that its
PSCR proposal was consistent with MCL 460.6j(18) and that the PSC's order was inconsistent
with that statute. In its order granting in part and denying in part Edison's petition, the PSC
stated:
The Commission concludes that it should treat Detroit Edison's request for
PSCR reinstatement and establishment of PSCR base and factors to have been
properly raised under Section 6j(3)-(7), rather than Section 6j(18). The
Commission notes that the applicant did not present testimony to support factors
that would be in effect for 48 months. Nor did any of the parties treat the PSCR
base and factor issues as if they would be in effect for that period of time. Detroit
Edison made it clear that it intended to file a 2005 PSCR plan case and a 2004
PSCR reconciliation case outside of this docket. Everything except the citation in
its application suggests that Detroit Edison sought relief pursuant to Section 6j(3)(7), not Section 6j(18). The Commission further notes that the published notice
for this case did not specify under which subsection of Section 6j the Commission
28
Edison filed an application for a 2005 PSCR plan. The application was docketed as Case No.
U-14275.
29
A PSCR plan filed pursuant to MCL 460.6j(3)-(7) features an annual PSCR plan setting PSCR
factors for a 12-month period, a five-year forecast, and an annual reconciliation case.
30
The AG moved to dismiss Edison's 2005 PSCR plan case on the ground that it violated MCL
460.6j(18). In an order entered on June 30, 2005, in Case No. U-14275, the PSC denied the
AG's motion to dismiss. The AG's appeal from the PSC's decision is currently pending before
this Court (Docket No. 265869).
-21-
would consider Detroit Edison's request for PSCR factors. Moreover, any defect
in notice has not prejudiced the parties because the issues are essentially the same,
whichever subsection is used, and the parties have had ample opportunity to raise
and argue issues related to the reasonableness and prudence of the projected costs
and power supply. Therefore, the Commission concludes that it should grant
rehearing on this issue and amend the November 23 order to reflect that the PSCR
portion of that order was completed pursuant to MCL 460.6j(3)-(7).
The AG argues that the PSC's order of June 30, 2005, granting in part and denying in part
Edison's petition for rehearing is unlawful because it violates MCL 460.6j(18) by allowing
Edison to file annual PSCR plan cases. Edison's application for a general rate case and
implementation of its PSCR clause was filed pursuant to MCL 460.6j(18). Under that statute,
Edison must file annual reconciliation cases and refund over-recoveries to ratepayers, but is
precluded from filing any additional PSCR plan cases or surcharging ratepayers for underrecoveries for the 48-month period. The AG contends that the PSC's erroneous conclusion that
Edison sought implementation of a PSCR clause under MCL 460.6j(3)-(7) allows Edison to file
new PSCR plan cases annually and raise rates. We disagree.
The PSC's decision does not violate MCL 460.6j(18). Contrary to the AG's contention on
appeal, this issue involves more than the PSC's rote application of MCL 460.6j(18). On June 20,
2003, Edison filed an application for a general rate case and, in conjunction therewith, sought
reinstatement of its PSCR clause. In connection with its request for reinstatement of the PSCR
clause, Edison also requested that its PSCR clause remain suspended until the PSC authorized
rate relief. Edison cited MCL 460.6j(18).
However, the PSC concluded that Edison's PSCR clause automatically reinstated on
January 1, 2004, when the rate freezes imposed by MCL 460.10d(1) expired. Ultimately, and
after confusion engendered by unclear language in both the PFD and the PSC's November 23,
2004, order, the PSC concluded in its June 30, 2005, order granting in part and denying in part
Edison's petition for rehearing that it should treat Edison's request for reinstatement and
establishment of a PSCR base and factors pursuant to MCL 460.6j(3) through (7), rather than
MCL 460.6j(18). This conclusion is consistent with the PSC's finding that Edison's PSCR clause
was automatically reinstated.
Edison's actions in the proceedings before the PSC are consistent with the PSC's
conclusion that, Edison's citation of MCL 460.6j(18) in its application notwithstanding, Edison
intended to and did seek establishment of a PSCR base and factors pursuant to MCL 460.6j(3)
through (7). Edison filed a separate 2005 PSCR plan case. Such a case could only proceed
-22-
pursuant to MCL 460.6j(3) through (7) because it was not filed in conjunction with a general rate
case.31
Given the PSC's conclusion that Edison's PSCR clause was automatically reinstated, and
Edison's act of filing a separate 2005 PSCR plan case, we conclude that Edison's citation of
MCL 460.6j(18) was not controlling, and that the PSC correctly concluded that it should treat
Edison's request for establishment of a PSCR base and factors as having been brought under
MCL 460.6j(3) through (7). The PSC's construction of the applicable regulatory scheme is
reasonable and is entitled to deference. Champion's Auto Ferry, supra. The PSC's decision is
not unlawful, nor is it unreasonable. MCL 462.26(8).
V. Conclusion
We reverse that portion of the PSC's November 23, 2004, order that authorized Edison to
impose a surcharge of $0.05 a meter, each month, on all customers to subsidize its renewable
energy program, and reverse the PSC's ruling that Edison may not recover its allocated share of
the control premium, but affirm the PSC's orders in all other respects.
/s/ Henry William Saad
/s/ Jane E. Markey
/s/ Kurtis T. Wilder
31
The PSC's denial of the AG's motion to dismiss the 2005 PSCR plan case is consistent with the
PSC's determination in this matter that Edison intended to proceed pursuant to MCL 460.6j(3)
through (7).
-23-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.