OAKLAND CNTY BD OF CNTY ROAD COMMRS V JBD ROCHESTER LLC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
OAKLAND COUNTY BOARD OF COUNTY
ROAD COMMISSIONERS,
Plaintiff-Appellant,
v
UNPUBLISHED
March 23, 2006
APPROVED FOR
PUBLICATION
May 16, 2006
9:05 a.m.
No. 263123
Oakland Circuit Court
LC No. 03-046566-CC
JBD ROCHESTER, L.L.C., and THE VILLA,
Defendants-Appellees.
Official Reported Version
Before: Owens, P.J., and Kelly and Fort Hood, JJ.
PER CURIAM.
Plaintiff appeals by leave granted the trial court's order denying its motion in limine to
exclude appraisals of defendants' property that took into consideration a posttaking road
construction delay caused by congressional funding problems. Defendants contend that the
evidence is relevant to a determination of their cost to cure severance damages. We reverse.
Evidentiary rulings are reviewed for an abuse of discretion. Dep't of Transportation v
VanElslander, 460 Mich 127, 129; 594 NW2d 841 (1999). "An abuse of discretion occurs when
an unprejudiced person considering the facts upon which the decision was made would say that
there was no justification or excuse for the decision." City of Novi v Robert Adell Children's
Funded Trust, 473 Mich 242, 254; 701 NW2d 144 (2005).
The federal and state constitutions prohibit the taking of private property for public use
without just compensation. VanElslander, supra at 129. "'Just compensation means the full
monetary equivalent of the property taken.'" Id. (citation omitted). "Just compensation . . . must
put the party injured in as good a position as he would have been if the inquiry had not
occurred." State Hwy Comm'r v Eilender, 362 Mich 697, 699; 108 NW2d 755 (1961).
The proper measure of damages in a case involving a partial taking consists of the fair
market value of the property taken, plus severance damages to the remaining property if
applicable. Dep't of Transportation v Sherburn, 196 Mich App 301, 306; 492 NW2d 517 (1992).
Severance damages are damages to the remaining property that are attributable to the taking. Id.
-1-
at 305. "To calculate the severance damages, the parties may present evidence of the cost to
cure." Id. at 306.
Plaintiff contends that the appraisals at issue should have been excluded because they
consider posttaking factors and defendants are only entitled to recover the fair market value of
their property at the time of the taking. In support of its position, plaintiff relies on Dep't of
Transportation v Haggerty Corridor Partners Ltd Partnership, 473 Mich 124; 700 NW2d 380
(2005), in which our Supreme Court considered the admissibility of evidence that severed land
subject to a partial taking was later rezoned as commercial and therefore more valuable. Though
the lead and concurring opinions offered different rationales, a majority of the Court agreed that
the trial court abused its discretion in admitting evidence of the rezoning after the retaking. Id. at
148 (opinion by Young, J.);1 id. at 164 (Kelly, J, concurring). The lead opinion concluded that
the actual posttaking rezoning was irrelevant:
In short, a posttaking zoning change is irrelevant to the just compensation
calculation because it does not make the fact of consequence—that information
regarding the reasonable possibility of a zoning change may have impacted the
market value of property on the date of the taking—more probable or less
probable. [Id. at 140-141 (opinion by Young, J.) (emphasis in original).]
"[B]ecause just compensation must be calculated on the basis of the market value of a property
on the date of the taking, the relevance of any such evidence is wholly dependent on whether,
and how, the particular factor at issue would have affected the market participants on that date."
Id. at 136 (opinion by Young, J.) (emphasis in original). Justice Kelly agreed that the evidence
was inadmissible. However, she reasoned that the evidence was inadmissible under MRE 403
because its probative value was substantially outweighed by its prejudicial effect. Id. at 149
(Kelly, J, concurring).
Defendants assert that a critical factual distinction between this case and Haggerty is that,
in this case, they are not asserting that the posttaking construction delay affected the fair market
value of their property; rather, they are seeking severance damages caused by the posttaking
construction delay. As noted above, severance damages are damages to the remaining property
that are attributable to the taking. Sherburn, supra at 305.
In this case, however, the delay in funding, and not the taking itself, caused the alleged
severance damages. No market actor could have possibly known that problems in congressional
funding would halt the road project. Defendants' development project commenced and
continued. Only later did defendants learn of their predicament. The road project would not be
completed when expected, and commercial tenants would soon arrive once defendants' buildings
were constructed. The strip of land that plaintiff now owned sat as a sort of buffer obscuring the
presence of the commercial development, which would rely on the business of passing motorists.
Buildings slated for demolition continued to stand on the strip. Powerless to obtain federal
1
Chief Justice Taylor and Justice Corrigan joined the lead opinion.
-2-
funding, defendants paid for the demolition and road pavement to secure their investment from
wholesale failure. They did not ask for reimbursement for improvements that local authorities
would have required in any event, which included entranceways and acceleration/deceleration
lanes.
Defendants placed unwarranted reliance on the expectation that the road project would be
completed. Delays caused by lack of funding occur with some regularity, as the situation in
Congress had national effect and stalled many projects. Had the taking not happened until later,
the funding situation would have remained the same and defendants would still have been
pressed to decide to pave the road themselves. The only difference would have been that
defendants would have owned the strip of land and could have pursued demolition and
improvement with greater haste, assuming permits from local authorities were forthcoming.
Defendants may not impose their own construction timetable on plaintiff under the
banner of just compensation. Defendant's choice between undertaking the road project
themselves or watching their investment fail is not a consequence of the taking, but of their
market decision to presume that they could take advantage of an expected public works project.
When that project met delay caused by a public funding problem, defendants were not deprived
of value inherent in the land or made to suffer noxious effects of the taking. They instead lost a
convenient coincidence to which they had no claim in the first place. Allowing evidence of the
paving would invite the jury to enrich defendants at the public's expense, which is not just
compensation. VanElslander, supra at 129. Nor does excluding the evidence impermissibly
enrich the public at defendants' expense. Id. Defendants made a business decision to secure
their investment as soon as possible. They got what they paid for and cannot now impose the
price of their business decision on plaintiff as a matter of just compensation.
The trial court erred in admitting appraisals of defendants' property that took into
consideration the posttaking road construction delay because the claimed severance damages
were not caused by the taking.
Reversed and remanded for further proceedings. We do not retain jurisdiction.
/s/ Donald S. Owens
/s/ Kirsten Frank Kelly
/s/ Karen M. Fort Hood