NextEra Energy Resources, LLC v. Maine Public Utilities Commission
Annotate this Case
The Supreme Judicial Court affirmed the decision of the Maine Public Utilities Commission granting Central Maine Power Company's (CMP) petition for a certificate of public convenience and necessity (CPCN) for the construction and operation of the New England Clean Energy Connect (NECEC) project, holding that the Commission followed the proper procedure and that there was sufficient evidence in the record to support the Commission's findings.
In 2017, CMP filed a petition with the Commission for a CPCN for the NECEC project, a 145-mile transmission line. The Commission voted to grant CMP a CPCN for the construction and operation of the NECEC project. The Supreme Judicial Court affirmed, holding (1) the Commission did not commit legal error when it decided that CMP was not required to file the results of a third-party investigation into nontransmission alternatives; (2) the Commission did not err in its construction and application of Me. Rev. Stat. 35-A, 3132(6); and (3) the Commission did not abuse its discretion in approving a stipulation between the parties requiring the project to provide myriad benefits to ratepayers and the State as conditions to the recommended Commission approval of the stipulated findings and issuance of the CPCN.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.