FAVALORA CONSTRUCTORS, INC. Vs. GRILLOT ELECTRIC COMPANY, INC.

Annotate this Case
Download PDF
FAVALORA CONSTRUCTORS, INC. * NO. 2016-CA-0550 * VERSUS COURT OF APPEAL * GRILLOT ELECTRIC COMPANY, INC. FOURTH CIRCUIT * STATE OF LOUISIANA ******* APPEAL FROM CIVIL DISTRICT COURT, ORLEANS PARISH NO. 2015-10615, DIVISION “E” Honorable Clare Jupiter, Judge ****** Judge Edwin A. Lombard ****** (Court composed of Chief Judge James F. McKay, III, Judge Edwin A. Lombard, Judge Madeleine M. Landrieu) LANDRIEU, J., CONCURS WITH REASONS Jerry W. Sullivan LEEFE, GIBBS, SULLIVAN & DUPRE' 3900 North Causeway Boulevard Suite 1470 Metairie, LA 70002 COUNSEL FOR DEFENDANT/APPELLANT Gary J. Giepert Jonathan S. Giepert THE GIEPERT LAW FIRM, LLC 4603 South Carrollton Avenue New Orleans, LA 70119 COUNSEL FOR PLAINTIFF/APPELLEE AFFIRMED NOVEMBER 30, 2016 This appeal is from a judgment denying the petition for vacatur of an Award of Arbitrator filed by the plaintiff/appellant Favalora Constructors, Inc., and affirming the arbitration award in favor of defendant/appellee, Grillot Electric Company. After review of the record in light of the arguments of the parties and the applicable law, the district court judgment is affirmed. Relevant Facts and Procedural History In this dispute arising out of a construction subcontract between the parties, Favalora, the contractor, subcontracted electrical work to Grillot. Upon conclusion of the construction work, Favalora submitted final invoices of all services, including those of the subcontractors, to the property owner. Because the cost of the finished project exceeded the original estimate by $230,000.00, the property owner disputed the amount over the original estimate and the matter went to arbitration. The arbitrator found that Favalora failed to submit timely “Control Estimates” as required by the construction contract between the parties and, accordingly, Favalora did not receive the $230,000.00 claimed in excess of the construction contract estimate. 1 In turn, because Favalora did not receive the disputed $230,000.00, Favalora did not pay its subcontractor, Grillot, in full. Grillot then filed for arbitration of the disputed amount ($16,484.88) and, after a hearing, the arbitrator awarded Grillot the sum of $16,484.88.1 Favalora then filed its petition for vacatur in the district court. After a hearing on the petition, the district court found in favor of Grillot, denied Favalora’s petition for vacatur, and confirmed the arbitration award. Favalora filed this timely devolutive appeal. Standard of Review We review a district court judgment confirming an arbitration award de novo. Brice Bldg. Co. L.L.C. v. Southland Steel Fabricators, Inc. 15-1110, p. 3 (La. App. 4 Cir. 6/17/16), 194 So.3d 1285, 1288-1289 (citation omitted). Applicable Law The purpose of the arbitration process is to speedily resolve disputes and avoid “the delay, the expense, and the vexation of ordinary litigation.” Brice, 151110, p. 4, 194 So.3d at 1289 (quoting Mack Energy Co. v. Expert Oil & Gas, L.L.C., 14-1127, p. 7 (La. 1/28/15), 159 So.3d. 437, 441-43). Thus, strong public policy supports arbitration and arbitration awards are presumed valid and highly favored. Brice, 2015-1110, pp. 3-4, 194 So.3d at 1289. In seeking to overturn an arbitrator’s award, the burden of proof is on the party attacking the award. Brice, 2015-1110, p. 4, 194 So.3d at 1289 1 This sum is taken from the Award of Arbitrator found in the record before this court. We note that the Award states that the issue was the balance due Grillot and “[t]here is no dispute that the Claimant’s contract price is [sic] $57, 580.00 increased to $58, 976.54 and that all but $16,482,88 is in dispute in this Arbitration.” We can only assume that this statement is a 2 Discussion Favalora argues on appeal that the district court manifestly disregarded the law because the subcontract between the parties contained a “pay if paid” clause. Favalora bases this argument on the judicially created doctrine that an arbitration award may be overturned when the arbitrator commits an error “which is obvious and capable of being readily and instantly perceived by an average person qualified to serve as an arbitrator,” thereby implying that “the arbitrator appreciates the existence of a clearly governing legal principle but decides to ignore it.” Brice, 2015-1110, p. 5, 194 So.3d at 1289 (citations omitted). Although Favalora asserts that the district court erred in affirming the arbitration award because the arbitrator ignored a clause within the contract at issue, the record before the court does not contain a copy of the contract at issue nor does it appear that Favalora submitted a copy of the contract to the court below. Rather, according to the docket sheet included in the record, a 3-page petition for vacatur was filed in the district court by Favalora on November 5, 2015, and, although the “pay if paid” contract provision is alluded to in Favalora’s petition, the contract itself was neither attached nor submitted to the district court. Grillot filed its answer and reconventional demand to affirm the arbitration award on November 9, 2015, attaching as “Exhibit 1” a copy of the “Award of Arbitrator” at issue in this appeal. The arbitrator’s award references (1) a stipulation by the parties that the legal issue in the arbitration matter pertained to the “Paid if Paid” clause; and (2) that the contract documents were submitted to the arbitrator; and (3) that “[i]ncluded in the evidence submitted via stipulation is the typographical error and the amount in dispute (and ultimately awarded) was the balance due under the contract. 3 opinion rendered in No. 01 15 0003 3799.” In his reasoning, the arbitrator observes: The findings in that proceeding are relevant to the instant matter. In the sub contract with Claimant there is typical language setting for the incorporation of the terms of the Prime Contract and various contract documents. Once would assume that the requirement that Respondent [Favalora] submit Control Estimates is part of the contract, is only applicable to the General Contractor and not the subcontractors. As with many Construction Contracts this language by incorporating in each sub contract all contract documents is read to include only such provisions of the Prime Contract that are applicable to ALL SUBCONTRACTORS and such provisions that are only applicable to each subcontractors trade or specialty. It is difficult to understand how an electrical subcontractor in this case would know that he is bound to assume the risk of payment for failure of the Prime Contractor to submit “CONTROL ESTIMATES” OR whether SCHEDULES OF VALUE are equivalent. It is, at the very minimum, an ambiguity and is not what the Claimant and the Respondent could have contemplated when entering into the contract. Moreover, even if one were to have accepted the argument that “Pay if Paid” is a bar to Claimant’s recovery, this Claimant was not a party to the proceeding between Respondent and the Owner. Based on the Schedule of Values submitted by the parties both the Respondent and the Owner were on notice of the amounts scheduled for this Claimant. Finally, it appears that the Paid if Paid [sic] provision, in the context of this case, is a harsh and unconscionable defense where the Prime Contractor’s breach of the contract is imputed to the subcontractor who had fully performed its scope of work. Thus, the arbitrator based his findings, conclusions, and award on documents that do not appear in the record before this court and were not presented to the district court. This is a court of record and the burden is on the appellant to show that the district court erred in affirming the arbitrator’s award because the arbitrator manifestly disregarded the law. In this case, Favalora (the appellant) argues that the district court’s judgment affirming the arbitration award should be overturned based on a provision in the contract between the parties but did not submit the contract and related documents to the district court and, likewise, does not submit the contract and related documents to this court. The Award of Arbitration 4 attached to Grillot’s answer to Favalora’s petition of vacatur does reference a stipulation that the contract between the parties included a “pay if paid” provision but, even accepting arguendo that a reference in the arbitration award is adequate evidence of the existence of the clause, the arbitrator based his conclusions and findings on the whole record before him, including the Schedule of Value. Accordingly, based upon our de novo review of the record before this court, Favalora did not meet his burden of establishing that the arbitrator made an obvious legal error or ignored a governing legal principle. Thus, Favalora’s appeal is without merit. Conclusion The judgment of the district court is affirmed. AFFIRMED. 5

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.