THOMAS ENVIRONMENTAL CONTRACTING VS. BOYD FISCAL COURT
Annotate this Case
Download PDF
RENDERED: JULY 25, 2008; 10:00 A.M.
NOT TO BE PUBLISHED
Commonwealth of Kentucky
Court of Appeals
NO. 2007-CA-000570-MR
THOMAS ENVIRONMENTAL CONTRACTING
v.
APPELLANT
APPEAL FROM BOYD CIRCUIT COURT
HONORABLE C. DAVID HAGERMAN, JUDGE
ACTION NO. 06-CI-01173
BOYD FISCAL COURT
APPELLEE
OPINION
AFFIRMING
** ** ** ** **
BEFORE: DIXON, LAMBERT, AND STUMBO, JUDGES.
STUMBO, JUDGE: This is an appeal of an order granting a declaratory judgment
which deemed Thomas Environmental Contracting (hereinafter Appellant) legally
ineligible to be awarded a contract for the construction of a pump station for the
Boyd County sanitary sewer system expansion. At issue is a Boyd County Fiscal
Court (hereinafter Appellee) ordinance which states “[u]nless prohibited or
otherwise inconsistent with law, no contract for construction shall be awarded to
any bidder who is not a participant in an accredited apprenticeship training
program as defined under KRS Chapter 343.” Ordinance No. 149-98. KRS
343.060 provides that an apprenticeship program is not in affect until approved by
the Supervisor of apprenticeship training appointed by the Executive Director of
the Apprenticeship and Training Council. See KRS 343.020-030.
Appellant first contends that the apprenticeship program does not
have to be in place at the time of the bid, only before the awarding of the contract.
Appellee responds that whether or not the program must be in place before the bid
is irrelevant because Appellant’s program was not in place before the awarding of
the contract. The trial court held that because Appellant’s apprenticeship program
was not in place before the contract was awarded, it was not an eligible bidder.
We agree.
On August 28, 2006, Appellee opened up bidding for a contract for
the construction of a pump station for a sewer system expansion project. Appellant
submitted the lowest bid and was so advised on September 1, 2006. Appellant
admits that it was also advised on that day that it needed to have an accredited
apprenticeship program in order to be awarded the contract.
On October 3, 2006, at its regular meeting, Appellee awarded the
contract to Appellant. When notified of the award, Appellee submitted an
application for approval of its apprenticeship training program to the
2
Apprenticeship and Training Council. The program was approved by the
Supervisor two days later.
Appellee, having been advised that the necessary approval had not
been timely obtained, advised Appellant it would not receive the contract on
October 6, 2006. This declaratory action was filed thereafter.
Appellee contended below and repeats here that its failure to have the
necessary approval is not fatal to receipt of the contract because it was misled by
Appellees’ engineer, Thomas Reed, who advised Appellee that he had “plenty of
time to deal with the apprenticeship Program” and that the fiscal court did not want
to award the contract until the next month. Appellee contends that it relied to its
detriment upon this representation. Further Appellant argues that the trial court
erroneously ruled without permitting the introduction of further evidence on this
issue.
On January 29, 2007, the Boyd Circuit Court entered an opinion in
which it held that under the ordinance, the apprenticeship program must be in place
in order for a party to be an eligible bidder in the first place. Additionally it held
that Appellant’s program was not in place until October 5, 2006, which would be
too late even if the court interpreted the ordinance in accordance with Appellant’s
theory.
Appellant then filed a motion to vacate, alter and reconsider on
February 12, 2007. It was overruled and this appeal followed.
3
After reviewing the record and case law, we affirm the trial court’s
declaratory judgment. Notwithstanding the trial court’s holding that a bidder must
have the apprentice program in place before he can be an eligible bidder, we find
the secondary holding to be dispositive of the issue.
Regardless of the trial court’s interpretation of the ordinance, even if
we agree with Appellant that the apprentice program only needed to be in place by
the time the contract was awarded, it still cannot prevail. The contract was
awarded on October 3, 2006, but the apprentice program was not approved and in
place until October 5, 2006. The ordinance states that a bidder must be a
participant in an “accredited training program” in order for the contract to be
awarded. Even though it was only two days late, Appellant did not comply with
the ordinance requirement in time. In regard to Appellant’s contention that the
court erred in ruling without the taking of further proof, we note that when the trial
court extended the briefing schedule “to allow counsel for the parties to interview
or otherwise depose state officials,” Appellee neither objected nor requested
further time to complete its proof.
Accordingly we affirm the trial court’s decision and find Appellant
was ineligible to be awarded the construction contract.
ALL CONCUR.
4
BRIEFS AND ORAL ARGUMENT
FOR APPELLANT:
BRIEF FOR APPELLEE:
Phillip Bruce Leslie
Greenup, Kentucky
James W. Lyon, Jr.
Greenup, Kentucky
ORAL ARGUMENT FOR
APPELLEE:
Shauna Rhodes
Greenup, Kentucky
5
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.