KEA-HAM CONTRACTING, INC. v. FLOYD COUNTY DEVELOPMENT AUTHORITY and BURL WELLS SPURLOCK
Annotate this Case
Download PDF
RENDERED:
AUGUST 4, 2006; 10:00 A.M.
NOT TO BE PUBLISHED
Commonwealth Of Kentucky
Court of Appeals
NO. 2005-CA-001450-MR
KEA-HAM CONTRACTING, INC.
v.
APPELLANT
APPEAL FROM FLOYD CIRCUIT COURT
HONORABLE JOHN DAVID CAUDILL, JUDGE
CIVIL ACTION NO. 97-CI-00172
FLOYD COUNTY DEVELOPMENT AUTHORITY and
BURL WELLS SPURLOCK
APPELLEES
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
JUDGE.
COMBS, CHIEF JUDGE; MINTON,1 JUDGE; HUDDLESTON,2 SENIOR
HUDDLESTON, SENIOR JUDGE:
Kea-Ham Contracting, Inc. appeals
from a summary judgment in favor of the Floyd County Development
Authority (FCDA) and its former chairman, Burl Wells Spurlock.
Kea-Ham contends that the Floyd Circuit Court erred in granting
summary judgment because genuine issues of material fact exist
1
Judge John D. Minton, Jr. concurred in this opinion prior to his resignation
effective July 25, 2006, to accept appointment to the Kentucky Supreme Court.
Release of the opinion was delayed by administrative handling.
2
Senior Judge Joseph R. Huddleston sitting as Special Judge by assignment of
the Chief Justice pursuant to Section 110(5)(b) of the Kentucky Constitution
and KRS 21.580.
regarding the alleged breach of a construction contract between
the parties.
First, Kea-Ham charges that the FCDA negligently
or fraudulently misrepresented the status of funding for a
construction project which induced Kea-Ham to enter into a
contract to excavate the work site.
Kea-Ham also claims the
FCDA is liable for allegedly erroneous specifications supplied
by Summit Engineering that Kea-Ham relied on in submitting its
bid.
Finally, Kea-Ham alleges that Spurlock, as chairman of the
FCDA, negligently or fraudulently induced Kea-Ham to enter into
the contract by making material misrepresentations as to
financing for the project.
This litigation arose after the FCDA solicited bids
for a construction project to develop land that could be sold
for industrial purposes.
On October 1, 1995, the FCDA began
accepting bids for excavation work on the project.
The bid
advertisement outlined the project specifications and estimates
calculated by an engineering and consulting firm, Summit
Engineering.
The bid invitation required all bidders to inspect
the work site and conditions of the land.
bid for the excavation work.
Kea-Ham submitted a
When the FCDA unsealed the bids on
October 16, 1995, Kea-Ham’s bid was more than $500,000.00 lower
than the next-lowest bid.
Kea-Ham’s bid was also substantially
lower than the costs calculated in the Summit Engineering
estimate.
The FCDA had reservations about the disparity in Kea-
-2-
Ham’s bid, and its members were concerned about Kea-Ham’s
ability to complete the job.
In response, Kea-Ham’s president,
David Hamilton, penned a letter of assurance to the FCDA stating
that the company was satisfied it could complete the project for
the amount of its bid.
The FCDA subsequently awarded the
contract for the project to Kea-Ham.
On November 2, 1995,
Spurlock wrote a letter at the request of Kea-Ham’s insurance
and bonding agent for the project, River City Insurance.
The
letter, addressed to Thomas Lafferty of River City Insurance,
stated:
Per your request, this is to advise that
Kea-Ham Contracting, Inc., will be paid
pursuant to invoices presented on a monthly
basis by them to the Floyd County
Development Authority. The invoices will be
reviewed by Summit Engineering, the
consulting engineering company, for
verification of labor performed and
materials supplied, and compliance with all
terms of their contract, and then
transmitted to the Authority for payment.
The Authority has interim financing approved
in the amount of $1.5 million from The Bank
Josephine, Prestonsburg, Kentucky, which
will be supplemented by LGEDF (coal
severance tax) of $1,460,000 and a CDBG of
$595,555.
Should you need additional information,
please advise.
Kea-Ham began work pursuant to the contract on or
about November 13, 1995.
The contract stated that the project
was funded through grants obtained by the FCDA as well as other
-3-
community funds.
The contract further provided that if work on
the project was delayed for reasons beyond the control of the
FCDA, Kea-Ham had no claim for damages.
In March 1996, Kea-Ham abandoned work on the project
because two of the FCDA’s payments were overdue.
The funds were
withheld by the Floyd County Fiscal Court at the behest of the
Floyd County Judge-Executive.3
According to the affidavit of
Spurlock, the Fiscal Court retained and disbursed the money for
the project.
Kea-Ham returned to work in May 1996 after
receiving payment.
However, Kea-Ham ultimately abandoned the
project in January 1997.
Kea-Ham sued the FCDA alleging breach of contract,
breach of warranty, negligent misrepresentation, estoppel and
fraud.
Kea-Ham’s complaint also included allegations of fraud
and negligent misrepresentation against Spurlock individually.
This Court reviewed this case in an earlier appeal
from a summary judgment based on sovereign and official
immunity.4
This Court affirmed the trial court’s order, and the
Supreme Court granted discretionary review.
That court
3
Apparently, Floyd Fiscal Court was involved in a financial dispute with the
company which planned to purchase the site upon completion of the project.
4
Kea-Ham Contracting, Inc. v. Floyd County Development Authority, 97-CA002144-MR (Ky.App. 1998).
-4-
reversed, holding the FCDA and Spurlock were not immune from
Kea-Ham’s lawsuit.5
On remand to Floyd Circuit Court, Kea-Ham claimed that
the specifications supplied by Summit Engineering were
inaccurate thereby causing Kea-Ham’s bid to be lower than
necessary for the work the project required and entitling it to
additional compensation.
Kea-Ham also focused on the letter
written by Spurlock on November 2, 1995, which assured River
City Insurance of the available funding for the project.
Kea-
Ham asserted that the funding was never really in place, which
resulted in the March 1996 work-stoppage.
Likewise, Kea-Ham
charged that Spurlock misrepresented the funding of the project
in his November 2, 1995, letter and that Kea-Ham relied to its
detriment on Spurlock’s assurances.
In April 2005, Kea-Ham failed to respond to the FCDA’s
and Spurlock’s motions for summary judgment.
Although the
circuit court granted both motions,6 Kea-Ham successfully moved
the court to vacate the judgment and filed a belated response to
the FCDA’s and Spurlock’s motions.
In May 2005, the FCDA and
Spurlock renewed their motions for summary judgment.
Kea-Ham
5
Kea-Ham Contracting, Inc. v. Floyd County Development Authority, 37 S.W.3d
703 (Ky. 2000).
6
Spurlock’s motion was granted on the ground that Kea-Ham could not sustain
its burden of proving fraud or misrepresentation related to Spurlock’s
November 2, 1995, letter. The FCDA was granted partial summary judgment on
the same issues arising out of the financial assurances contained in the
letter.
-5-
did not respond to the motions, nor did the corporation take any
depositions over the course of this litigation.
Following a
June 2005 hearing, the circuit court granted the renewed motions
for summary judgment in favor of the FCDA and Spurlock.
Upon review of a summary judgment, we consider whether
there is a genuine issue as to any material fact and, if not,
whether the moving party is entitled to judgment as a matter of
law.7
“Only when it appears impossible for the nonmoving party
to produce evidence at trial warranting a judgment in his favor
should the motion for summary judgment be granted.”8
We first address Kea-Ham’s contention that the FCDA is
liable for breach of contract and negligence because the
specifications supplied by Summit Engineering were inaccurate.
Kea-Ham argues that it relied on the Summit plans to calculate
its bid and because of inaccuracies, Kea-Ham lost money on the
extra work required by the project.
The FCDA argues, however, it is absolved from
liability for any errors because Summit was an independent
contractor.
“As a general rule, an employer is not liable for
the torts of an independent contractor in the performance of his
7
Ky. R. of Civ. Proc. (CR) 56.03; Scifres v. Kraft, 916 S.W.2d 779, 781
(Ky.App. 1996).
8
Steelvest, Inc. v. Scansteel Service Center, Inc., 807 S.W.2d 476, 482 (Ky.
1991).
-6-
job.”9
To determine whether the relationship constitutes an
employer and independent contractor relationship, the most
important factor is whether the employer retains the right to
supervise and control the work.10
In this case, the FCDA entered
into a written contract for professional services with Summit
Engineering.
Nothing in the record indicates that Summit was
anything other than an independent contractor hired by the FCDA
to draft engineering specifications for the construction site.
"[A] party opposing a properly supported summary judgment motion
cannot defeat it without presenting at least some affirmative
evidence showing that there is a genuine issue of material fact
for trial."11
Kea-Ham produced no such evidence.
Consequently,
summary judgment was proper on this issue.
Next, we turn to Kea-Ham’s claim that the November 2,
1995 letter from Spurlock constituted fraud or, alternatively,
negligent misrepresentation.
In a Kentucky action for fraud, the party
claiming harm must establish six elements of
fraud by clear and convincing evidence as
follows: a) material representation b) which
is false c) known to be false or made
recklessly d) made with inducement to be
9
Miles Farm Supply v. Ellis, 878 S.W.2d 803, 804 (Ky.App. 1994).
10
United Engineers & Constructors, Inc. v. Branham, 550 S.W.2d 540, 543 (Ky.
1977).
11
Steelvest, supra, note 7, at 482.
-7-
acted upon e) acted in reliance thereon and
f) causing injury.12
Furthermore, a colorable claim of negligent
misrepresentation requires a showing that
One who, in the course of his business,
profession or employment, or in any other
transaction in which he has a pecuniary
interest, supplies false information for the
guidance of others in their business
transactions, is subject to liability for
pecuniary loss caused to them by their
justifiable reliance upon the information,
if he fails to exercise reasonable care or
competence in obtaining or communicating the
information.13
In this case, Spurlock wrote the letter after the FCDA
accepted Kea-Ham’s bid, and Kea-Ham’s president admitted that
once Kea-Ham was named the low-bidder on the project, it was
obligated to perform.
Furthermore, evidence is lacking that
funding was not in place at the time the invoices were due.
Kea-Ham did not receive payment due to the unilateral action of
Floyd Fiscal Court and the Floyd County Judge-Executive.
Because no factual dispute exists on this issue, summary
judgment was appropriate.
The judgment is affirmed.
ALL CONCUR.
12
United Parcel Service Co. v. Rickert, 996 S.W.2d 464, 468 (Ky. 1999),
citing Wahba v. Don Corlett Motors, Inc., 573 S.W.2d 357, 359 (Ky.App. 1978).
13
Presnell Construction Managers, Inc. v. EH Construction, LLC, 134 S.W.3d
575, 580 (Ky. 2004), quoting Restatement (Second) of Torts § 552 (1977).
-8-
BRIEF FOR APPELLANT:
Michael de Bourbon
James P. Pruitt, Jr.
PRUITT & de BOURBON LAW FIRM
Pikeville, Kentucky
BRIEF FOR APPELLEE
FLOYD COUNTY DEVELOPMENT
AUTHORITY:
Michael J. Schmitt
PORTER, SCHMITT, BANKS &
BALDWIN
Paintsville, Kentucky
BRIEF FOR APPELLEE
BURL WELLS SPURLOCK:
Robert E. Maclin, III
John N. Billings
McBRAYER, McGINNIS, LESLIE &
KIRKLAND, PLLC
Lexington, Kentucky
-9-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.