EMMETT E. COOMER v. CSX TRANSPORTATION, INC.
Annotate this Case
Download PDF
RENDERED: JULY 30, 2004; 2:00 p.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NO.
2003-CA-001721-MR
EMMETT E. COOMER
APPELLANT
APPEAL FROM JEFFERSON CIRCUIT COURT
HONORABLE DENISE M. CLAYTON, JUDGE
ACTION NO. 01-CI-006866
v.
CSX TRANSPORTATION, INC.
APPELLEE
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
BARBER, KNOPF, AND TACKETT, JUDGES.
KNOPF, JUDGE:
In October 2001, Emmett Coomer brought suit
against CSX Transportation, Inc., a railroad company, under the
Federal Employers’ Liability Act (“FELA”),1
He alleged that the
company had negligently failed to provide him reasonably safe
working conditions and that the negligence had caused him to
develop bilateral carpal tunnel syndrome and ulnar neuropathy (a
1
45 U.S.C. §§ 51 et seq.
disorder of the ulnar nerve that caused Coomer pain in his
elbow).
By summary judgment entered July 22, 2003, the
Jefferson Circuit Court dismissed the complaint because, in the
court’s judgment, Coomer had failed to come forward with any
evidence of the company’s negligence.
that Coomer has appealed.
It is from that judgment
He contends that the trial court
erred by denying his request for a continuance to conduct
additional discovery and by disregarding sufficient evidence of
the company’s negligence to withstand the motion for summary
judgment.
We affirm.
Coomer began working for CSX in 1976, and until August
2001, he was engaged primarily as a laborer on track-maintenance
crews.
His duties frequently required him to use heavy,
vibrating pneumatic tools and to perform strenuous repetitive
motions with his arms and wrists.
He alleges that the
cumulative trauma of this work resulted in the nerve problems he
has experienced and that CSX failed to do all it should have
done to minimize the risk of such injuries.
The trial of this matter was twice continued, once at
the request of either party.
In October 2002, following the
second continuance, the trial court set July 29, 2003, as the
new trial date and ordered that witnesses and exhibits be
identified by June 13, 2003.
CSX filed its motion for summary
judgment on April 30, 2003.
2
A few days later, on May 5, Coomer informed CSX that
he wished to have an ergonomist inspect his work site and tools.
He asked that the inspection take place on either June 4 or June
5.
On May 7, CSX replied that those were inconvenient dates and
proposed three others.
Coomer did not immediately respond.
Instead, on May 22, arguing that CSX had been obstructive, he
moved for another continuance.
order entered May 28.
The court denied the motion by
At the same time it extended the deadline
for Coomer’s response to the summary judgment motion, but it
refused to extend the deadline for identifying witnesses and
exhibits.
Coomer immediately moved the court to reconsider his
request for a continuance.
On May 30, Coomer rejected CSX’s proposed inspection
dates and requested another, June 3.
On June 2, CSX again
replied that that was an inconvenient date and proposed others.
Apparently convinced that an inspection any later than June 3
would leave him too little time to meet the witness-and-exhibit
deadline, on June 3 Coomer rejected CSX’s proposals and
suggested no alternatives.
On June 13, the court denied Coomer’s motion for
reconsideration.
motion on June 20.
Coomer responded to the summary judgment
The court heard oral arguments at the pre-
trial conference on July 1, and granted the motion by order
entered July 22.
Coomer contends that the court abused its
3
discretion by denying him a continuance to conduct the site
inspection.
We disagree.
As the parties note, an application for a continuance
is addressed to the trial court’s sound discretion.2
Factors
courts have considered in exercising that discretion include
length of delay; previous continuances; inconvenience to
litigants, witnesses, counsel, and the court; whether the delay
is purposeful or is caused by the movant; complexity of the
case; and whether denying the continuance will lead to
identifiable prejudice.3
Here, the case had been pending for about eighteen
months and had already been continued twice, once at Coomer’s
request.
The trial court could reasonably believe that Coomer
had been afforded ample opportunity to arrange for a site
inspection, that he knew or should have known following similar
difficulties scheduling depositions that scheduling the
inspection might require considerably advanced planning, and
thus that his failure to arrange the inspection within the
deadline for identifying witnesses and exhibits was a problem of
his own making.
The court did not abuse its discretion,
therefore, by denying Coomer’s request for yet another
continuance.
2
Wells v. Salyer, Ky., 452 S.W.2d 392 (1970).
3
Pendleton v. Commonwealth, Ky., 83 S.W.3d 522 (2002).
4
Nor did the court err by granting CSX’s motion for
summary judgment.
A FELA claimant is obliged to prove that he
was injured as a result of his employer’s negligence, and
summary dismissal is proper unless he proffers more than a
scintilla of evidence in support of each element of his claim.4
Coomer was thus obliged to proffer at least some evidence that
CSX knew or should have known that the particular conditions of
his workplace posed an unreasonable risk of cumulative-trauma
injury.5
We agree with the trial court that Coomer failed to
meet this burden.
Coomer testified at his deposition that some of the
equipment he used vibrated such that it “would shake you all
over.”
He argues that this testimony together with the fact
that he is a large man weighing in excess of 400 pounds would
permit a juror to infer that the vibrations to which he was
exposed were excessive and apt to be injury causing.
We do not
believe, however, that a lay juror would be qualified to reach
this conclusion, for the long-term effects of vibration are not
within the average person’s experience.
Nor would those facts
permit an inference that CSX knew or should have known that the
4
Doty v. Illinois Central Railroad Company, 162 F.3d 460 (7th
Cir. 1998); Aparicio v. Norfolk & Western Railroad Company, 84
F.3d 803 (6th Cir. 1996), abrogated on other grounds by Reeves v.
Sanderson Plumbing Products, Inc., 530 U.S. 133, 147 L. Ed. 2d
105, 120 S. Ct. 2097 (2000).
5
Doty v. Illinois Central Railroad Company, supra.
5
risk of injury posed by the equipment was unreasonable.
Coomer
conceded as much in his motion for a continuance when he argued
that the ergonimist’s testimony would be essential to his claim.
Coomer thus having failed to proffer more than a scintilla of
evidence that CSX was negligent, the trial court did not err by
granting its motion for summary judgment.
Accordingly, we
affirm the July 22, 2003, judgment of the Jefferson Circuit
Court.
ALL CONCUR.
BRIEFS FOR APPELLANT:
BRIEF FOR APPELLEE:
Alva A. Hollon, Jr.
Sams & Hollon, P.A.
Jacksonville, Florida
Edward H. Stopher
Darryl S. Lavery
Boehl, Stopher & Graves, LLP
Louisville, Kentucky
6
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.