BLUE SKY SEWER SERVICE COMPANY, INC. v. COMMONWEALTH OF KENTUCKY, NATURAL RESOURCES AND ENVIRONMENTAL PROTECTION CABINET
Annotate this Case
Download PDF
RENDERED:
NOVEMBER 7, 2003; 2:00 p.m.
NOT TO BE PUBLISHED
Commonwealth Of Kentucky
Court of Appeals
NO. 2002-CA-001591-MR
BLUE SKY SEWER SERVICE
COMPANY, INC.
v.
APPELLANT
APPEAL FROM FRANKLIN CIRCUIT COURT
HONORABLE WILLIAM L. GRAHAM, JUDGE
ACTION NO. 01-CI-01262
COMMONWEALTH OF KENTUCKY,
NATURAL RESOURCES AND
ENVIRONMENTAL PROTECTION
CABINET
APPELLEE
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
EMBERTON, CHIEF JUDGE; KNOPF AND SCHRODER, JUDGES.
SCHRODER, JUDGE.
The Blue Sky Sewer Service Company, Inc.,
(Blue Sky) appeals a summary judgment granted to the Natural
Resources and Environmental Protection Cabinet (NREPC) enforcing
an “Agreed Order” and disposing of certain administrative
violations issued against Blue Sky.
We agree with the trial
court that relief, if any, should have been sought below and we
therefore affirm.
Blue Sky is a privately owned wastewater treatment
plant located in Fayette County operating under a Kentucky
Pollution Discharge Elimination System (KPDES) permit issued by
the NREPC.
Blue Sky was designed to treat domestic sewage but
now treats about 125 businesses.
Over the years, the wastewater
has become more akin to commercial or industrial sewage which is
obviously more difficult to treat.
This led to increasing
discharge problems and numerous notices of violation from the
NREPC.
In an effort to resolve the notices of violation, Blue
Sky entered into an “Agreed Order”1 with the NREPC whereby Blue
Sky would upgrade the plant to comply with its discharge
allowances under the KPDES permit.
This agreed order provided a
time frame for specific upgrades and a civil penalty for delays
in the construction as well as penalties for failure to bring
the plant into full compliance with its permits.
The
construction permit provided that there could be no deviations
from the plans and specifications submitted with the approved
application.
The extended date for completion of the
construction was April 1, 2001, with a compliance date of
June 1, 2001 (for the plant to be up and running within the
KPDES permit allowances).
1
This was actually the second agreed order.
-2-
On June 1, 2001, an inspector from the NREPC visited
the plant and discovered four problems, per the trial court’s
findings:
a bypass of the sewage system taking place
because of a leaking intake pipe and that
Blue Sky had not notified NREPC as required
by 401 KAR 5:015; the Parshall flume had not
been installed as required by the
construction permit, instead the facility
had installed a less expensive device; the
clarifier was not installed as required by
the permit; KPDES permit levels for the
effluent from the plant were also being
exceeded in violation of the Agreed Order.
The NREPC filed suit in circuit court to enforce the agreed
order.
Blue Sky did not disagree that it was not in compliance
with the agreed order but sought to defend by justifying its
noncompliance.
The trial court would not hear excuses and
granted summary judgment to the NREPC.
On appeal to this Court, Blue Sky contends the trial
court erred in granting summary judgment to the NREPC because
Blue Sky was entitled to a trial on why it failed to perform
according to the agreed order.
First, Blue Sky argues the
notice of violation (NOV), which cited Blue Sky for the
existence of a “bypass”, should not be enforced because there
was no “bypass” constructed at the facility, merely an
accidental leak in the pipeline that occurred during
construction, and that the water was collected in an excavated
pit and actively pumped from there into the lagoon for further
-3-
treatment.
The NREPC counters that on April 6, 2001, the
inspector observed the leaking pipe which was still leaking on
April 13, 2001, when the inspector returned to the site.
In
addition, the inspector observed the effluent discharged into a
creek, that the discharge was “turbid and odorous”, and water
samples collected from the plant’s discharge point as well as
downstream, revealed fecal coliform bacteria colonies too
numerous to count.2
2001.
The NOV was issued to Blue Sky on April 30,
The NOV cited Blue Sky for bypassing the requirements of
401 KAR 5:045 and not notifying the NREPC of the leak as
required by 401 KAR 5:015.
Instead of addressing the
violations, Blue Sky contends that under 401 KAR 5:002(36), a
bypass is defined as “the intentional diversion of sewage or
wastestreams from a portion of the facility or industrial user’s
treatment facility [,]” and Blue Sky installed no such device.
Rather, the waste leaked out.
We agree with the trial court
that Blue Sky is misstating the facts.
Blue Sky is not charged
with installing a “bypass” but charged with not reporting the
spill and bypassing the treatment requirements.
Blue Sky does
not contest the fact that there was a leak in the pipe nor the
readings by the inspector (although Blue Sky claims it recovered
and treated the leak, its own records show the treatment was
2
The monthly average for fecal coliform bacteria for April 2001 was 10,810
colonies per 100 milliliters, whereas the 401 KAR 5:045, Section 4 allowance
is up to 200 colonies per 100 milliliters during a thirty-day period.
-4-
inadequate), nor does Blue Sky deny it failed to report the leak
or spill.
Steelvest, Inc. v. Scansteel Service Center, Inc.,
Ky., 807 S.W.2d 476, 482 (1991), recognized the “original
purpose of summary judgment procedure is to expedite the
disposition of cases and to avoid unnecessary trials where no
genuine issues of material fact are raised.”
omitted).
(citations
The Steelvest Court did caution that summary judgment
“should not be used as a substitute for trial.”
Id. at 483.
In
adopting the Paintsville Hospital Co. v. Rose3 standard, the
Steelvest Court recognized summary judgment should be used only
“to terminate litigation when, as a matter of law, it appears
that it would be impossible for the respondent to produce
evidence at the trial warranting a judgment in his favor and
against the movant.”
Id. at 483, citing Paintsville Hospital.
We believe the trial court was correct in finding no real issue
regarding a bypass system.
Blue Sky was cited for not reporting
the spill (leak) and the use of the word bypass was referring to
not treating the waste adequately rather than accusing Blue Sky
of intentionally installing a “bypass” system.
Blue Sky also contends the NOV should not have been
issued for not installing a “‘new 20’ diameter circular
Clarifier with a design peak flow of 265,000 GPD”, as required
by the construction permit.
3
Blue Sky readily admits the
Ky., 683 S.W.2d 255 (1985).
-5-
clarifier was not installed, and that the clarifier was a
requirement of the final construction permit.
However, Blue Sky
wanted a trial to show the clarifier was unnecessary and
extraordinarily expensive which made the requirement
unreasonable.
That argument should have been presented to the
NREPC when Blue Sky was negotiating for the “Agreed Order”.
trial court was merely enforcing the agreed order.
The
401 KAR
5:005, Section 7 requires Blue Sky to request and justify a
deviation from the “Recommended Standards for Wastewater
Facilities, 1990 Edition”, which is what the NREPC used.
No
deviation was requested or authorized.
Further, 401 KAR 5:005, Section 24(4)(b) states:
“The
following conditions shall apply to all construction permits:
1.
There shall be no deviations from the plans and
specifications submitted with the application or the conditions
specified in this subsection, unless authorized in writing by
this cabinet.”
Again, we must agree with the trial court that
there was no issue of fact before it and summary judgment on
this issue was proper under Steelvest, 807 S.W.2d 476.
Blue Sky’s third contention is that the NOV for
failure to install the “Parshall Flume” should not be enforced.
Again, the parshall flume was a specification of the permit
which was a part of the agreed order.
Blue Sky substituted a
“90° V-Notch Weir” in the place of the “Parshall Flume”.
-6-
Blue
Sky wanted to prove that its substitution was just as effective
as the original specifications, and even offered evidence from
NREPC employees that the substitution could do the job.
However, this argument too should have been presented to the
NREPC below before signing the agreed order, or in a subsequent
request for modification.
Blue Sky cannot simply agree to these
requirements and then seek relief in court.
It must first seek
its administrative relief, and if unsuccessful, appeal to
circuit court.
See Kentucky Labor Cabinet v. Graham, Ky., 43
S.W.3d 247, 254 (2001); Natural Resources And Environmental
Protection Cabinet v. Coleman, Ky. App., 876 S.W.2d 614, 616
(1993); and Sobolewski v. Louisville Downs, Inc., Ky. App., 609
S.W.2d 943, 945 (1980).
Blue Sky’s final argument is that the issuance of the
NOV for “Exceedences” during construction was unfair,
inequitable, and should not be enforced.
Blue Sky admitted its
KPDES permit and the construction permit required compliance
with the Clean Water Act4 during construction of improvements,
but contends the plant was in such bad shape that it could not
be improved without these exceedences and that the NREPC
inferred that it would look the other way during construction in
order to get the plant upgraded.
The trial court summed up the
argument as Blue Sky “offering a myriad of excuses blaming
4
33 U.S.C. 1251, et seq.
-7-
everyone except Blue Sky”.
We must agree.
inadequate before the new construction.
The facility was
There were exceedences
before the construction which necessitated the additional
construction.
Blue Sky cites Weiand v. Board of Trustees of
Kentucky Retirement Systems, Ky., 25 S.W.3d 88, 91 (2000), for
the proposition that equitable estoppel can be invoked against a
governmental entity in “unique circumstances where the court
finds exceptional and extraordinary equities involved.”
Blue
Sky wants the NREPC estopped from trying to enforce the NOV for
exceedences.
Blue Sky contends the promises are issues of fact
that should be tried.
The NREPC included the construction
permit in the record which required compliance during
construction.
What initially appears to be an issue of fact is
another mere claim or allegation with no evidence to support it.
There are no affidavits by anyone from Blue Sky reporting this
“promise”, or any other evidence of such.
An allegation is not
enough to overcome a motion for summary judgment.
In City of
Florence, Kentucky v. Chipman, Ky., 38 S.W.3d 387, 390 (2001),
our Supreme Court stated, “The party opposing . . . summary
judgment motion cannot defeat it without presenting at least
some affirmative evidence showing the existence of a genuine
issue of material fact for trial.”
The Court then cited Hoke v.
Cullinan, Ky., 914 S.W.2d 335 (1995), with approval, for the
statement “upon the trial court’s determination that there are
-8-
no such disputed facts, summary judgment is appropriate.”
Chipman, 38 S.W.3d at 390.
Blue Sky presented no evidence of
promises that could be used to consider the estoppel argument.
For the foregoing reasons, the judgment of the
Franklin Circuit Court is affirmed.
ALL CONCUR.
BRIEF FOR APPELLANT:
BRIEF FOR APPELLEE:
Brent L. Caldwell
Stephen G. Amato
Lexington, Kentucky
Mary Stephens
Frankfort, Kentucky
-9-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.